Delivery and sequence

Delivery and sequence is the planning that brings each piece to site when the crew needs it and sets the order in which pieces go up, so that a partly built frame stays standing.

4

Milestones achieved, from 2011 to 2019.

1

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 2011

    Bracing left out

    On 27 July 2011 a systems-engineered metal building (a steel frame designed and supplied as a kit by its maker) collapsed while under construction in San Marcos, Texas, killing one worker and injuring another. OSHA's engineer found that neither the temporary bracing needed during erection nor the permanent wall bracing on the maker's drawings had been installed, and that following the maker's installation manual and OSHA's rules would have prevented the collapse.

    Lessonbracing has to go in as the frame goes up, as a step in the sequence, not after it.

    osha.gov

    Credit

    OSHA Directorate of Construction, Office of Engineering Services

  2. 2013

    Steel by night, no yard

    The Leadenhall Building in the City of London was built on a site with nowhere to lay down materials, so Laing O'Rourke prefabricated 85% of the project by value, by its construction director's count. Raked columns up to 27 m long and 70 tonnes were brought in and lifted at night, and were leaned against perimeter floors built first on trestles until the node above was set. The building's lean was corrected at each of its seven megaframe levels by adding or removing packing plates in bolted joints.

    LessonBuilding magazine reported that the complexity of the steelwork contributed to a £29m loss at the steelwork contractor, Severfield Rowen, that year.

    building.co.uk

    Credit

    Laing O'Rourke; Watson Steel Structures (now Severfield); Arup; Rogers Stirk Harbour + Partners

  3. 2015

    Fifty-seven floors in 19 days

    Broad Sustainable Building assembled Mini Sky City, a 57-story glass-and-steel tower of about 200 m in Changsha, China, from factory-made modules at three floors a day. The Associated Press reported 19 working days of assembly in two spells separated by winter weather. Liu Peng of Arup Beijing told AP the method was worth developing but "not perfect".

    Lessonthe 19 days count assembly only, and Broad's planned 838 m Sky City, which broke ground in 2013 to be finished in months, had stalled.

    globalnews.caconstructionmanagement.co.uk

    Credit

    Broad Sustainable Building, part of Broad Group

  4. 2019

    Brace unbolted for guardrails

    A report to CROSS, the UK's confidential reporting scheme for structural safety, described a four-story steel frame where a temporary diagonal brace had been unbolted from a column base so that edge protection could be fitted. On the same job the steel subcontractor and the main contractor each designed temporary stability for different stages, on different assumptions about the beam connections.

    Lessonthe CROSS panel said one designer should hold overall responsibility for stability during construction, when the risk of instability is highest.

    istructe.org

    Credit

    CROSS (Collaborative Reporting for Safer Structures) and the Institution of Structural Engineers

Watch for

  1. Structural progress read from photos

    Buildots says its AI now turns drone and 360-degree camera images of a building's structural phase into progress data linked to the elements and quantities in the building model, with production rates and cycle times meant to flag delays weeks before they hold up later trades. It says the feature was in beta on customer sites for over a year.

    Achieved whenan independent study compares its readings with an erector's installation records on a steel frame, member by member.

    aecmag.com

    Claimed by

    Buildots, July 2026

Open

  1. 01

    Piece marks read by camera

    A phone app that photographs steel members lying on dunnage in a yard or on a delivery trailer, reads the painted, stenciled or hand-written piece mark on each, and ticks it off against the piece list for the next erection sequence, flagging any piece that is missing before the crane is booked.

    The brief
    Credit · unclaimed
  2. 02

    Erection stages checked openly

    An open program that takes a steel frame model and a planned erection sequence and checks, stage by stage, whether the part-built frame stands under construction-stage wind and the weight of the next pieces, then lists which temporary braces or cables must stay in place at each stage.

    The brief
    Credit · unclaimed

Open 01 · the brief

Piece marks read by camera

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A phone app that photographs steel members lying on dunnage in a yard or on a delivery trailer, reads the painted, stenciled or hand-written piece mark on each, and ticks it off against the piece list for the next erection sequence, flagging any piece that is missing before the crane is booked.

Why it is still open

Research on tracking steel has tagged members or measured their final position with added hardware, as in NIST's 2002 prototype. Versatile, a construction software firm, reads piece marks from photos of the bills of lading that come with each delivery and matches them to the model and the erection sequence, not from the steel itself. Kinetic's PrimeCut app suggests a plate's heat or serial number from a photo of its stamp, and steel mills read painted slab numbers with cameras. No published test reads the marks fabricators put on the members themselves and checks them against an erection list.

nist.govversatile.aikineticusa.comroboflow.com

Built with what exists

A phone camera; an open text-recognition model such as PaddleOCR, or a vision-language model; the piece list exported from the detailing model as a spreadsheet; Python.

  1. First step

    With a fabricator's permission and a yard escort, photograph 100 marked members at ground level while no loads are moving, and label the marks by hand.

  2. Done looks like

    1,000 photographed members from at least two fabricators, with the share read correctly and the share sent to a person both published, checked against the shipping lists, and no wrong match accepted.

Open 02 · the brief

Erection stages checked openly

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

An open program that takes a steel frame model and a planned erection sequence and checks, stage by stage, whether the part-built frame stands under construction-stage wind and the weight of the next pieces, then lists which temporary braces or cables must stay in place at each stage.

Why it is still open

Kim, Park and Cho (2020) generate erection sequences from a building model that are stable in the sense of static determinacy, without checking them under loads. Pick Builder, posted on GitHub in November 2026, flags picks that break erectors' sequence rules on one sample frame, such as a freestanding column or a pick over 85% of a made-up crane chart, but runs no structural analysis. StruTrix Studio, a Windows program with closed source, analyzes structures built in stages in its paid version. CROSS (2019) reported a steel subcontractor's stability claim made without calculations, and OSHA's San Marcos report found no bracing installed at all. No open, tested tool for stage-by-stage checks was found.

doi.orggithub.comgithub.comistructe.org

Built with what exists

NIST's 23 free sample CIS/2 steel models, exported from programs including Tekla, SDS/2, Revit and RAM; NIST's SteelVis to convert them to IFC; IfcOpenShell; OpenSeesPy, a free structural analysis library; an AI coding agent that writes and runs its own tests (see the Note "Checked without being asked").

nist.gov

  1. First step

    Convert NIST's Tekla1 sample file to IFC with SteelVis and write the code that removes members to form the first stage.

  2. Done looks like

    Stage-by-stage reports for 10 of the NIST models; results within 5% of hand calculations on three textbook frames; every unstable stage shown with the brace that fixes it; the code and test cases published and reviewed by a licensed structural engineer. The reports are a desk study and are not used to direct real erection.