Industries / Construction and property / Commercial and residential construction / Steel erection
Detailing and fabrication
Detailing turns the engineer's design into drawings and machine files for every piece of steel, and fabrication cuts, drills and welds those pieces in a shop before they go to site.
7
Milestones achieved, from 1976 to 2018.
2
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
1976
Fabricators audited for quality
The American Institute of Steel Construction (AISC) set up its first certification program for steel fabricators in 1976. Plants that apply are audited against AISC's certification standards by a separate company, Quality Management Company (QMC), using contract auditors who work for neither AISC nor QMC, by AISC's account.
Credit
American Institute of Steel Construction
1980s
Models feed the machines
The beam punch lines of the 1970s punched a member's holes in one pass; in the early 1980s computer-controlled drill and saw lines replaced them, and by the late 1980s data could be downloaded from 3D CAD systems straight to the machines. Cut lengths, hole positions, layout marks, piece numbers and copes (notches cut at a beam's end) traveled in the DSTV file format, developed in Germany, which is still used worldwide.
Credit
German steel construction industry (DSTV format); account by Adrian Morrall of Voortman USA
1994
One model, every drawing
Tekla's Xsteel stored a steel structure as one 3D product model in a database, and drew the drawings, material lists and machine files from it as views, so a change made in the model carried through to all of them. A 1994 paper by Tekla's Miikka Kiiski said Xsteel was already in use at engineering and steelwork companies in Finland and abroad.
Credit
Tekla Oy, Espoo, Finland
2000
A shared file for steel
CIS/2, the CIMsteel Integration Standards, is a data format that lets analysis, design and detailing programs pass a steel model to each other. It was developed at the University of Leeds and the Steel Construction Institute in the UK from the European Eureka CIMsteel project, and AISC adopted it in 2000 as its data exchange format for structural steel. NIST's free set of 23 sample CIS/2 files is named after the programs that wrote them, among them Tekla, Design Data (SDS/2), Revit, RAM and STAAD.
Lessona format made for one material can be overtaken, and NIST says AISC's interoperability strategy now centers on IFC, the general building model format.
Credit
University of Leeds; Steel Construction Institute; AISC; Chuck Eastman of Georgia Tech, whom NIST calls "very instrumental"
2014
CE marks on fabricated steel
From 1 July 2014 all fabricated structural steelwork delivered to sites in the European Union had to carry a CE mark under the Construction Products Regulation (EU) No 305/2011 and the standard EN 1090-1. A fabricator needs a factory production control certificate and a welding certificate, both issued by a notified body (an approved outside assessor), and the engineer must specify an execution class, the grade of fabrication quality. In the UK, the British Constructional Steelwork Association says, some offenses can bring a fine, prison or both.
Credit
European Parliament and Council; CEN, the European standards body
2016
A robot fits beam parts
Fitting means setting plates and clips on a beam in exactly the right place before welding, and Prospect Steel's president told The Fabricator it was the one step no one had automated. In September 2016 Prospect Steel of Little Rock, Arkansas, installed a robotic beam assembly line from Zeman Bauelemente of Austria. One robot scans the loose parts on a table, matches them to the job's Tekla model and holds each in place while a second robot tack welds it, and the welding robots then finish the welds; the line was running seven days a week on three shifts when the magazine reported on it in 2018.
LessonProspect's president said rolled steel's wide mill tolerances had been the stumbling block for robots, so the parts fed to one must be accurate.
Credit
Zeman Bauelemente; Prospect Steel; Peddinghaus, Zeman's US representative
2018
Cracks from the cutting torch
On 25 September 2018, weeks after it opened, a worker found a crack in a steel girder at the Transbay (Salesforce) Transit Center in San Francisco; the center closed that day and reopened on 1 July 2019. A peer review panel for the Metropolitan Transportation Commission found that thermal cutting of slots in the girders' bottom flanges left microcracks in a thin hard layer of martensite, a brittle form of steel, and that shrinkage from a heavy weld beside the slots later grew them into larger cracks.
Lessonthe panel asked AISC and the American Welding Society to set clear rules for grinding and shaping thermally cut holes and corners in thick steel, not only those labeled weld access holes.
Credit
MTC Peer Review Panel, chaired by Michael Engelhardt of the University of Texas at Austin, drawing on LPI's laboratory report
Watch for
Robot fitting and welding, timed
Voortman, a Dutch maker of fabrication machines, says its engineers timed three beam assemblies made by hand and on its Fabricator robotic fitting and welding system, and the robot cut total fabrication time by 68% to 78%. In its example an HEA260 beam with 11 parts took 1 hour 8 minutes against 5 hours 6 minutes by hand. It adds that assemblies with fewer than four parts are quicker by hand.
Achieved whena fabricator or outside party publishes its own timed comparison on production work, with programming and setup time counted.
Claimed by
Voortman, June 2026
Reclaimed steel matched by software
William Hare, a UK steelwork contractor, says a custom tool it built on the Tekla Structures programming interface matched reclaimed sections to the members of 30 Duke Street St James's in London, in some cases cutting three or four new assemblies from one old section around its defects. About 77% of the frame, around 470 tonnes, is reclaimed steel, and the main contractor Mace's operations director estimates an embodied carbon saving of 744 tonnes of CO2e.
Achieved whenan independent embodied-carbon assessment confirms the reuse share and the saving, or the same tool is used on a second project with published figures.
Claimed by
William Hare and Mace, November 2026
Open
01
Donor steel read from drawings
A program that reads the archived shop and erection drawings of a steel-framed building due for demolition and writes a reuse inventory: each member's section, length, holes and copes, and where it sits in the frame. It is scored against a hand count of the same drawings.
The briefCredit · unclaimed02
Connection software checked blind
A public set of standard bolted and welded steel connections, each with loads and a hand-checked answer, run through several connection design programs, with the program's capacity and controlling failure mode recorded and every difference over 5% explained.
The briefCredit · unclaimed
Open 01 · the brief
Donor steel read from drawings
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A program that reads the archived shop and erection drawings of a steel-framed building due for demolition and writes a reuse inventory: each member's section, length, holes and copes, and where it sits in the frame. It is scored against a hand count of the same drawings.
Why it is still open
Brütting, Senatore, Schevenels and Fivet (2020) built their stock of reusable sections by inventorying shop drawings of deconstructed buildings by hand, and William Hare's 2026 automation started from reclaimed stock that had already been sourced and sorted, with the firm naming data quality as a remaining barrier. Buro Happold's Steel Reuse Inspector, a pair of Revit plugins published on GitHub, assesses steelwork that has already been modeled in Revit; it does not read drawings. No published tool turns old drawings into a reuse inventory and reports its error rate.
Built with what exists
Scanned drawing sets from a city archive, a university collection or a demolition contractor; a vision-language model that reads drawings and tables (see the Note "Seven more flagged"); IfcOpenShell to write the inventory as an IFC model; Python.
First step
Ask one building department or archive for the steel shop drawings of a demolished building and list 50 members by hand as the first answer key.
Done looks like
For three buildings, an inventory of at least 500 members in which section and length are right for at least 98% of members against a person's count, with every miss listed and the drawings and answer key published where the owners allow.
Open 02 · the brief
Connection software checked blind
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public set of standard bolted and welded steel connections, each with loads and a hand-checked answer, run through several connection design programs, with the program's capacity and controlling failure mode recorded and every difference over 5% explained.
Why it is still open
The Steel Tube Institute's 2025 comparison of 15 programs for hollow-section connections lists which connection types each program can design, not the answers they give. Vendors verify their own programs: ALLPLAN says SDS2 2026 adds standard verification problems for North America and Europe. No independent comparison of results on the same connections was found.
Built with what exists
AISC's published design examples as the answer key; trial or academic licenses of programs such as SDS2, IDEA StatiCa, RAM Connection and Qnect; free programs posted on GitHub, such as osoconn and CET.SteelConnDesign; a spreadsheet; Python.
First step
Pick ten shear and moment connections from AISC's design examples and run them through one program's free trial.
Done looks like
At least 40 connections run through at least three programs, a published table of capacity and controlling limit state for each, and a written reason for every result more than 5% from the hand answer.