Licensing

Licensing is the work of getting a regulator's permission to build a reactor, and later to run it, by showing that it can operate without undue risk to the public.

7

Milestones achieved, from 1989 to 2026.

2

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1989

    A single build-and-run licence

    On 18 April 1989 the US Nuclear Regulatory Commission (NRC) issued 10 CFR Part 52, a set of rules that added early site permits, standard design certifications and combined licences to the older two-step process of a construction permit followed by an operating licence. The NRC says the aim was to resolve safety and environmental questions early in the process and to standardize designs, so that a utility could refer to an approved design instead of having it reviewed again.

    federalregister.gov

    Credit

    US Nuclear Regulatory Commission

  2. 2022

    An application turned away

    In January 2022 the NRC denied Oklo's application to build and run its Aurora reactor, a 1.5 MWe fast reactor (one that uses unslowed neutrons), at Idaho National Laboratory. The NRC said the application still had "significant information gaps" in its description of possible accidents and in how it classed safety systems and components, so the review could not go on. The denial was without prejudice, which means Oklo may apply again. Oklo told World Nuclear News it was the first combined licence application for an advanced plant ever accepted for review.

    Lessona regulator cannot review what an application leaves out, so the accident analysis and safety classification have to be complete before the review clock starts.

    world-nuclear-news.org

    Credit

    US NRC (decision); Oklo (applicant)

  3. 2023

    First small design certified

    NuScale applied on 31 December 2016, and the NRC's rule certifying its design took effect on 21 February 2023. The NRC calls it the first small modular reactor design it reviewed: modules of 50 MWe each, up to 12 in one building, partly submerged in a shared pool of water that cools them. The certification also accepted that six licensed operators could run up to 12 modules from one control room. In May 2025 the NRC approved an uprated 77 MWe version, which the US Department of Energy (DOE) calls the second small modular reactor design the NRC has approved.

    federalregister.govenergy.gov

    Credit

    NuScale Power; US NRC

  4. 2023

    Permit for a salt-cooled reactor

    In December 2023 the NRC approved a construction permit for Kairos Power's Hermes reactor in Oak Ridge, Tennessee, two years after Kairos applied in September 2021. Hermes is a 35 MW thermal test reactor that makes no electricity. Its fuel is pebbles packed with tiny coated grains of uranium (TRISO fuel), and it is cooled by molten fluoride salt. DOE called it the first construction permit ever granted to a Generation IV reactor, the label for the newer, non-water-cooled designs. The NRC issued permits for two more units, Hermes 2, in November 2024. In May 2026 it moved Hermes's latest allowed completion date from 31 December 2026 to 30 April 2029, at Kairos's request.

    Lessona permit sets a deadline for building, not the pace; Hermes asked for more than two extra years.

    energy.govfederalregister.govfederalregister.gov

    Credit

    Kairos Power; US NRC; DOE's Advanced Reactor Demonstration Program

  5. 2025

    Canada licenses an SMR build

    On 4 April 2025 the Canadian Nuclear Safety Commission (CNSC) gave Ontario Power Generation (OPG) a licence to construct one GE Vernova Hitachi BWRX-300, a 300 MWe boiling water reactor, at Darlington, Ontario. The licence runs to 31 March 2035 and includes hold points, where OPG must give the regulator more information before building on. OPG applied for the construction licence in October 2022. Its site work was much older: it applied to prepare the site in 2006, and the site's environmental assessment was finished in 2012, nine years before OPG picked the BWRX-300 in December 2021. Ontario's energy minister called it the first SMR in the G7 countries.

    Lessonsettling the site years ahead let the construction licence follow about three years after the design was chosen.

    world-nuclear-news.org

    Credit

    Canadian Nuclear Safety Commission; Ontario Power Generation; GE Vernova Hitachi

  6. 2026

    A rulebook for any reactor

    On 30 March 2026 the NRC published 10 CFR Part 53, in force from 29 April 2026. It is an optional, risk-informed framework that applies to any reactor technology, written because the Nuclear Energy Innovation and Modernization Act (NEIMA), signed in January 2019, required one. The NRC says its older rules in Parts 50 and 52 were built around large light-water reactors, so other designs could only be licensed under them through flexibilities and exemptions.

    federalregister.gov

    Credit

    US NRC; US Congress (NEIMA)

  7. 2026

    Three permits in one year

    The NRC issued construction permit CPAR-1 on 9 March 2026 to TerraPower's Kemmerer Unit 1 in Wyoming, a sodium-cooled Natrium plant; CPAR-2 on 28 September 2026 to the Tennessee Valley Authority (TVA) for one BWRX-300 at Clinch River, Tennessee; and CPAR-3 on 9 November 2026 to Dow's Long Mott station in Texas, four X-energy Xe-100 gas-cooled reactors. The NRC said it finished the Clinch River review in 14 months, four months earlier than it had scheduled. World Nuclear News reports Clinch River as the first US construction permit for a BWRX-300 and Long Mott as the first US construction permit for a high-temperature gas-cooled reactor in nearly 60 years. A construction permit does not allow the reactor to run; each plant needs an operating licence later.

    federalregister.govworld-nuclear-news.orgworld-nuclear-news.org

    Credit

    US NRC; TerraPower; Tennessee Valley Authority; GE Vernova Hitachi; Dow; X-energy

Watch for

  1. Fixed deadlines for reviews

    Executive Order 14300 of 23 May 2025 orders the NRC to set binding deadlines, enforced by caps on the hourly fees it charges applicants, including no more than 18 months for a final decision on an application to build and run a new reactor. It also orders a "wholesale revision" of the NRC's rules, with final rules within 18 months, a date that falls on 23 November 2026. By mid-November 2026 the NRC had proposed rules on licensing, siting and microreactors, and had finalized some others, among them a rule, in force from 25 November 2026, that lets applicants build on a DOE or Department of War authorization of a demonstration reactor.

    Achieved whenfinal rules that set binding review deadlines are in force and the NRC decides a new-reactor application within 18 months under them.

    federalregister.govfederalregister.gov

    Claimed by

    the White House, May 2025

  2. Leaning on other regulators

    In May 2026 Britain's three nuclear regulators (the Office for Nuclear Regulation, the Environment Agency and Natural Resources Wales) published a policy to use other countries' assessments of a design as evidence in their own, under the heading "produce once, use many times", while making their own final judgements. Until now the applicant had to supply that evidence itself.

    Achieved whena UK design assessment statement or licence records that it relied on a named foreign regulator's review for part of its judgement.

    onr.org.ukgov.uk

    Claimed by

    ONR, Environment Agency and Natural Resources Wales, May 2026

Open

  1. 01

    A ledger of granted exemptions

    An open table of every exemption the NRC has granted to small and advanced reactor applicants since 2016, one row per exemption, giving the rule it sets aside, the reason stated, the docket, the date and the Federal Register notice. An exemption is permission not to meet one specific rule; the pattern of them shows which rules do not fit small reactors.

    The brief
    Credit · unclaimed
  2. 02

    One topic, three regulators

    A public, clause-by-clause map of what the NRC, Canada's CNSC and Britain's ONR each require on one topic for the same design, the BWRX-300, with each pair of clauses marked as the same, stricter, looser or absent, and a link to every clause.

    The brief
    Credit · unclaimed

Open 01 · the brief

A ledger of granted exemptions

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

An open table of every exemption the NRC has granted to small and advanced reactor applicants since 2016, one row per exemption, giving the rule it sets aside, the reason stated, the docket, the date and the Federal Register notice. An exemption is permission not to meet one specific rule; the pattern of them shows which rules do not fit small reactors.

Why it is still open

Exemptions sit in separate notices. NuScale's certification carries exemptions for every future buyer, such as running 12 modules with six operators. TerraPower received one in May 2025 so that it could build non-safety buildings on its plant's "energy island" before its construction permit. The Federal Register's search returns 1,383 NRC notices since 2016 that mention exemptions, most of them for operating plants, and a search found no list limited to small and advanced reactors.

federalregister.govfederalregister.gov

Built with what exists

the Federal Register API (federalregister.gov/api/v1, free, no key); the regulations.gov API; a language model to pull the rule section and stated reason out of each notice; two people to check its output.

  1. First step

    Pull every NRC notice since 2016 with "exemption" in its title through the API and filter it to the NuScale, Kairos, Clinch River, Kemmerer and Long Mott dockets.

  2. Done looks like

    every exemption for at least 10 named SMR and advanced reactor dockets from 2016 to 2026, each tied to its rule section and notice; a second person re-checks a random 20% with at least 95% agreement; a column marks which exemptions Part 53 or the 2026 microreactor proposal would make unnecessary.

Open 02 · the brief

One topic, three regulators

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public, clause-by-clause map of what the NRC, Canada's CNSC and Britain's ONR each require on one topic for the same design, the BWRX-300, with each pair of clauses marked as the same, stricter, looser or absent, and a link to every clause.

Why it is still open

The BWRX-300 holds a Canadian licence to construct (April 2025), a US construction permit (September 2026) and a UK design assessment statement (December 2025). The NRC and CNSC have compared their approaches in joint reports since 2019, including one on safety classification; their comparison of risk-informed reviews found the differences "at the implementation level of detail" with "no impact on the outcome of regulatory decisions". Those reports cover two regulators. In May 2026 the UK regulators wrote that they will benchmark other regulators "through comparison of regulatory codes, standards and expectations at a topic specific level", which is future work, and that today the burden of using foreign reviews falls on the applicant.

cnsc-ccsn.gc.cacnsc-ccsn.gc.caonr.org.ukonr.org.uk

Built with what exists

NRC rules on ecfr.gov; the CNSC's REGDOC-2.5.2, Design of Reactor Facilities; ONR's Safety Assessment Principles; a language-model agent that proposes matches and quotes the clause behind each one (the Note "Findings that cite notes" covers an agent kit built for that kind of cited review); two reviewers with nuclear licensing training.

  1. First step

    Take safety classification, the topic the NRC and CNSC have already compared, and set ONR's matching Safety Assessment Principles beside each of their requirements.

  2. Done looks like

    for one topic, every clause in the three documents mapped, each pair labelled by both reviewers with their agreement reported (Cohen's kappa of 0.7 or more), and the table published as a CSV with links.