Building in a factory

This work makes reactor parts, or whole sections of a plant, in a factory or shipyard and moves them to the site, so that less is built in the open.

4

Milestones achieved, from 1982 to 2026.

2

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1982

    A licensed reactor factory

    Offshore Power Systems, a Westinghouse venture with the Newport News shipyard, built a factory on Blount Island in Jacksonville, Florida, to make floating nuclear plants of about 1,000 MWe each; Atomic Insights reports a planned rate of four plants a year and a 1,000-ton bridge crane sized to lift a containment dome. US regulators issued the company a manufacturing license in December 1982, a route now carried in 10 CFR Part 52. By then the buyer, Public Service Electric and Gas of New Jersey, had cancelled its orders after electricity demand fell following the 1973 oil embargo, and Sandia reports that the intended site withdrew its application in 1984 before any plant was made.

    Lessona reactor factory needs a steady stream of orders before it is built, not one buyer.

    osti.govatomicinsights.com

    Credit

    Offshore Power Systems (Westinghouse and Newport News Shipbuilding); Public Service Electric and Gas

  2. 2013

    A module shop stops work

    For the AP1000 reactors at Vogtle in Georgia, Shaw Modular Solutions opened a new shop in Lake Charles, Louisiana, to make structural submodules, wall and floor sections up to 69 ft long and 44 tons, by Georgia Power's figures. No supplier had made AP1000 modules before. A consultant to Georgia's utility regulator blamed frequent design changes and poor quality at the shop for rework and assembly delays, and the owners ordered a stop-work there in 2013. CB&I, which bought Shaw, then inspected and repaired the remaining CA20 submodules at the Vogtle site, and the owners sent some Unit 4 modules to four other shops.

    Lessonmoving work into a factory helps only when the design is settled and the shop already works to nuclear quality rules.

    eenews.netenr.com

    Credit

    Shaw Modular Solutions and CB&I; Georgia Power; consultant Charles Hutson (record)

  3. 2023

    Steel poured, then order lost

    Doosan Enerbility began forging parts for the first NuScale power module in May 2023, under an order for heavy forgings, steam generator tubes and weld material for six upper reactor vessels, more than 2,000 tonnes in all by NuScale's figure. The plant they were for, the Carbon Free Power Project in Idaho, was cancelled six months later. NuScale says it intends to move those parts to its next customer.

    Lessonfactory work started ahead of a firm order is stranded if the first buyer leaves.

    world-nuclear-news.orgworld-nuclear-news.org

    Credit

    Doosan Enerbility; NuScale Power

  4. 2026

    A reactor floor lowered whole

    At Darlington, Ontario, the basemat of the first BWRX-300 reactor building, 37 m across and nearly 2.1 million pounds, was assembled from steel modules made in several Ontario shops, finished in an on-site fabrication building and lowered by crane into a 35 m deep shaft on 22 April 2026. The reactor building will hold about 1,200 steel composite modules, more than 200 of them in its first level. In November 2026 OPG said this first unit would miss its 2030 date and budget (see Cost).

    ans.org

    Credit

    Ontario Power Generation; Aecon Kiewit Nuclear Partners; GE Vernova Hitachi Nuclear Energy

Watch for

  1. Doosan builds NuScale vessel tops

    NuScale has signed a contract for Doosan Enerbility to make the upper reactor coolant system, the top section of the reactor pressure vessel of a NuScale Power Module, at Doosan's plant in Changwon, South Korea. NuScale calls it a step in "converting our approved design into deliverable modules"; its first plant is now planned for Doicești, Romania.

    Achieved whena complete NuScale Power Module leaves a factory and is installed at a licensed site, as recorded by that site's regulator.

    world-nuclear-news.org

    Claimed by

    NuScale Power and Doosan Enerbility, October 2026

  2. Factory-built plant for Wylfa

    Rolls-Royce SMR and Great British Energy – Nuclear signed a contract for three Rolls-Royce SMRs, 1.4 GWe in all, at Wylfa in North Wales; Rolls-Royce says it lets the company order long lead-time equipment. Its chief executive, Chris Cholerton, says a "standardized, factory-built approach" gives "greater cost and schedule certainty." The contract is not a final investment decision, and earlier reports put first power in the mid-2030s.

    Achieved whena final investment decision is taken and factory-made modules reach Wylfa on the published schedule, as reported by the owner or the UK regulator.

    ans.orgrolls-royce.com

    Claimed by

    Rolls-Royce SMR and Great British Energy – Nuclear, April 2026

Open

  1. 01

    Largest pieces against route limits

    An open table of the largest factory-made piece of each small reactor design (mass, length, width and height, taken from public licensing and vendor documents), checked against the legal and permit limits for road, rail and barge in each country where the design is proposed, with a map of which candidate sites each piece can reach and by which mode.

    The brief
    Credit · unclaimed
  2. 02

    Machine checks for module paperwork

    A reviewer that reads a fabrication record package for a steel module (weld records, inspection reports, material certificates, sign-off sheets) and flags missing documents, missing signatures and mismatched part numbers, tested on a public set of made-up packages with planted errors.

    The brief
    Credit · unclaimed

Open 01 · the brief

Largest pieces against route limits

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

An open table of the largest factory-made piece of each small reactor design (mass, length, width and height, taken from public licensing and vendor documents), checked against the legal and permit limits for road, rail and barge in each country where the design is proposed, with a map of which candidate sites each piece can reach and by which mode.

Why it is still open

A 2019 study by Mignacca, Alawneh and Locatelli found "extremely limited information about SMR modules transportation" and had weight data for only one of the three designs it compared, NuScale's "~700 tons in total are shipped from the factory in three segments." Idaho National Laboratory's 2020 transport plan covers microreactors of 20 MWe or less, not larger modules. Clara Lloyd's 2019 Cambridge thesis models how much of a plant can go by road by plant size (up to 80% for an SMR), not by named design or route.

eprints.whiterose.ac.ukosti.govrepository.cam.ac.uk

Built with what exists

Design and permit documents filed with the US Nuclear Regulatory Commission, the Canadian Nuclear Safety Commission and the UK's Office for Nuclear Regulation; the UK road categories in Mignacca et al. (44 t normal, 150 t abnormal); the US National Bridge Inventory and OpenStreetMap for routes; QGIS and Python; an AI model that reads long PDFs to pull dimensions, each figure checked by a person (the Note "Seven more flagged" covers such a reviewer).

  1. First step

    Pull the largest-piece figures for NuScale, BWRX-300 and Rolls-Royce SMR from their licensing documents and set them against the UK road categories.

  2. Done looks like

    At least 15 designs with their largest piece sourced, each checked against road, rail and barge limits in at least two countries, route results for 50 named candidate sites, and a second person rechecking 20% of entries.

Open 02 · the brief

Machine checks for module paperwork

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A reviewer that reads a fabrication record package for a steel module (weld records, inspection reports, material certificates, sign-off sheets) and flags missing documents, missing signatures and mismatched part numbers, tested on a public set of made-up packages with planted errors.

Why it is still open

At Vogtle, Georgia's independent construction monitor named paperwork problems at the module shop, "missing documents and missing signatures," as a big reason for delays, and owners later re-inspected modules at the site. The nearest tool found, Idaho National Laboratory's MIRACLE, uses machine learning to screen condition reports, the problem reports that plant staff file, not fabrication records. A search found no published test of automated review on module fabrication packages.

eenews.netinlsoftware.inl.gov

Built with what exists

Blank weld and inspection record forms modeled on public examples; a Python script that generates packages with known errors; an AI model that reads long documents, such as Claude (see the Note "Seven more flagged", on a Claude-based reviewer of drug-making records).

  1. First step

    Write 50 packages for one made-up steel wall module, plant 15 errors, and score a first reviewer.

  2. Done looks like

    1,000 made-up packages with 300 planted errors of ten kinds, released openly; the reviewer finds at least 95% of planted errors with no more than one false flag per 20 packages, scored by someone outside the team.