Fuel work makes the enriched uranium and the finished fuel pieces a small reactor burns, and keeps a steady supply of both.

6

Milestones achieved, from 1960s to 2026.

2

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1960s

    Fuel in coated beads

    TRISO fuel packs uranium into kernels about the size of a poppy seed, each wrapped in layers of carbon and ceramic that hold in the radioactive products of fission. The beads are pressed into cylinders or into billiard-ball-sized "pebbles" for gas- or salt-cooled reactors. The US Department of Energy (DOE) says TRISO was first developed in the United States and the United Kingdom in the 1960s. A 2026 Oak Ridge National Laboratory (ORNL) report names Germany's AVR pebble-bed reactor at Jülich, run from the 1960s to the 1980s, as a "significant milestone" that showed the fuel performing well.

    energy.govosti.gov

    Credit

    US and UK developers (DOE); the AVR program at Jülich (ORNL)

  2. 2009

    Beads pass record burnup

    DOE's Advanced Gas Reactor (AGR) program, started in 2002, tested an improved TRISO with uranium oxycarbide kernels. Burnup is the share of the original uranium atoms that have been split. In 2009 the fuel reached 19% maximum burnup in a three-year test at Idaho National Laboratory (INL), which DOE calls an international record and nearly double a German mark from the 1980s, then survived more than 300 hours at up to 1,800 °C with little damage. The Electric Power Research Institute (EPRI) put the AGR-1 and AGR-2 results to the Nuclear Regulatory Commission (NRC), whose final safety evaluation repeated the conclusion that particles inside the measured range "can be relied on to provide satisfactory performance". ORNL notes that this range is much narrower than the program's own fabrication specifications.

    Lessona fuel counts as proven only for the properties actually tested, so every plant must make it to that recipe.

    energy.govosti.gov

    Credit

    INL and ORNL under DOE's AGR program; EPRI; NRC

  3. 2022

    The only supplier is lost

    In December 2022 TerraPower said its Natrium demonstration reactor at Kemmerer, Wyoming, a 345 MWe sodium-cooled design, would start at least two years after its 2028 target. Its first core was to use HALEU, high-assay low-enriched uranium, enriched to between 5% and 20% uranium-235. Chief executive Chris Levesque said Russia's invasion of Ukraine had removed "the only commercial source of HALEU fuel", and that no new enrichment plant had started construction.

    Lessona reactor whose fuel has one supplier takes on that supplier's risks in its own schedule.

    world-nuclear-news.organs.org

    Credit

    TerraPower (announcement); World Nuclear News (report)

  4. 2023

    First HALEU from Ohio

    Centrus Energy started a cascade of 16 centrifuges at DOE's enrichment plant in Piketon, Ohio, and by 7 November 2023 had made 20 kg of HALEU, which DOE called the first production of its kind in the US in more than 70 years. The Government Accountability Office (GAO) reports that Centrus completed 900 kg in June 2025 and that DOE extended the contract for another 900 kg by 30 June 2026. DOE puts the cost of both contracts, from 2019 to June 2026, at about $475 million.

    energy.govfiles.gao.gov

    Credit

    Centrus Energy, through its subsidiary American Centrifuge Operating; DOE

  5. 2024

    Russian uranium banned

    Public Law 118-62, signed on 13 May 2024, bars imports of unused low-enriched uranium made in Russia or by Russian entities. DOE may grant waivers, but every waiver ends by 1 January 2028, and the ban runs until 31 December 2040. Utility Dive reports that its passage released $2.7 billion already authorized for US fuel production, including HALEU.

    congress.govutilitydive.com

    Credit

    US Congress

  6. 2026

    Stockpiles fill the gap

    With no commercial HALEU on sale in the US, DOE offers developers material from government stocks, including the National Nuclear Security Administration's, some of it made by downblending, mixing weapons-grade uranium down to a lower enrichment. DOE received requests from 15 companies and in April and August 2025 made conditional commitments to eight. In January 2026 Standard Nuclear reported its first shipment, to make TRISO fuel for a Radiant Industries microreactor. GAO reports that DOE expects about 21.2 tonnes of uranium as HALEU to be available for demonstrations by the end of 2028, and that DOE officials said demand will likely exceed it before commercial HALEU exists.

    energy.govfiles.gao.gov

    Credit

    DOE's HALEU Availability Program; National Nuclear Security Administration; Standard Nuclear

Watch for

  1. A licensed HALEU fuel plant

    The NRC issued licence SNM-7007 to TRISO-X, a subsidiary of X-energy, on 13 February 2026, covering TRISO fuel plants TX-1 and TX-2 in Oak Ridge, Tennessee, for 40 years. The American Nuclear Society reports they are the first new fuel fabrication plants licensed by the NRC in more than 50 years. TX-1 is under construction and TX-2 is in design, and the NRC must inspect TX-1 before it may receive HALEU.

    Achieved whenTX-1 passes the NRC's final inspections and ships finished fuel to a reactor site.

    ans.orggovinfo.gov

    Claimed by

    TRISO-X and X-energy, February 2026

  2. Enrichment at commercial scale

    GAO reports that in January 2026 DOE awarded task orders of $900 million each to Centrus and General Matter to build HALEU enrichment capacity, and that Urenco expects to make 10 tonnes of HALEU a year at a UK plant in the early 2030s. GAO also notes that China is the only country besides Russia with plant to make HALEU at scale. On 29 October 2026 Centrus shipped the first centrifuge built for its Piketon expansion from its factory in Oak Ridge.

    Achieved whena licensed plant outside Russia and China delivers HALEU to reactor developers at a sustained rate of tonnes a year, as reported by the NRC, DOE or GAO.

    files.gao.govans.org

    Claimed by

    DOE, Centrus and General Matter, January to October 2026

Open

  1. 01

    Map fuel needs against supply

    A public ledger that lists, for every small reactor and microreactor project with a public filing, the HALEU its first core and its yearly reloads need, in kilograms of uranium, and sets the total year by year against each announced source: DOE stockpiles, Centrus, General Matter, Urenco and Orano. Every figure links to its source.

    The brief
    Credit · unclaimed
  2. 02

    Chart designs against tested fuel

    A chart and table that place each TRISO-fuelled small reactor and microreactor design with public data against the conditions DOE's AGR tests covered: burnup, peak fuel temperature, fast-neutron dose and time spent in the core. Designs that fall outside the tested range are flagged.

    The brief
    Credit · unclaimed

Open 01 · the brief

Map fuel needs against supply

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public ledger that lists, for every small reactor and microreactor project with a public filing, the HALEU its first core and its yearly reloads need, in kilograms of uranium, and sets the total year by year against each announced source: DOE stockpiles, Centrus, General Matter, Urenco and Orano. Every figure links to its source.

Why it is still open

GAO found in August 2026 that published HALEU demand estimates "vary widely", from the Nuclear Energy Institute's 700 tonnes needed in total by 2030 (a 2021 survey) to DOE's 50 tonnes a year by 2035, and that DOE's own supply may fall short. DOE's allocation page names the companies selected in each round but gives no quantities. The national laboratories' 2021 estimate models a net-zero scenario with four stand-in designs (AP1000, NuScale, Natrium and Xe-100), not named projects. A search found market-research reports priced in dollars, not tonnes, and no project-by-project ledger.

files.gao.govenergy.govinldigitallibrary.inl.gov

Built with what exists

NRC and Canadian Nuclear Safety Commission filings; DOE and GAO reports; company announcements; a language-model agent that pulls each figure with its page reference; Python; two people who check every figure.

  1. First step

    Build the rows for the eight companies DOE selected in 2025, from their own public filings.

  2. Done looks like

    At least 25 projects, each with first-core and yearly HALEU needs and a cited source; a yearly balance of need against announced supply for 2026 to 2035; a second person re-checking a random 20% of entries.

Open 02 · the brief

Chart designs against tested fuel

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A chart and table that place each TRISO-fuelled small reactor and microreactor design with public data against the conditions DOE's AGR tests covered: burnup, peak fuel temperature, fast-neutron dose and time spent in the core. Designs that fall outside the tested range are flagged.

Why it is still open

A 2026 ORNL report says that, read strictly, the AGR results qualify fuel only within the properties as actually made, and proposes a further irradiation to widen that range. A 2026 INL modelling study warns that SMRs and microreactors that keep fuel in the core longer may expose it to more time at temperature than AGR explored, and recommends experiments to check its predictions. Both work from AGR's own test space, and a search of DOE's OSTI library found no comparison of named designs.

osti.govosti.gov

Built with what exists

AGR results on OSTI (AGR-5/6/7, for example, reached 5.66% to 15.26% burnup and a peak fuel temperature of 1,536 °C over 360.9 full-power days); public NRC applications; Python and matplotlib; review by two fuel engineers who do not work for a reactor vendor.

osti.gov

  1. First step

    Tabulate the tested ranges from the AGR-1, AGR-2 and AGR-5/6/7 reports, then add the first design from its public NRC application.

  2. Done looks like

    At least ten designs plotted on all four measures, each point cited to a public document, with every point outside the tested range named and the data published.