Siting
Siting is choosing where a reactor goes and showing that the place suits it: the ground, water and weather, the people nearby, and the plans for an emergency.
5
Milestones achieved, from 2012 to 2023.
3
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
2012
A siting map in hectares
Oak Ridge National Laboratory built OR-SAGE, a tool that splits the lower 48 US states into 100 m by 100 m squares, just under 700 million of them, and tests each square against siting criteria such as population, land use and nearby hazards. A square that passes every test is a candidate area. Its first use was for nuclear plants, and the Electric Power Research Institute (EPRI) then backed its extension to other kinds of power plant.
Credit
Gary Mays and colleagues, Oak Ridge National Laboratory; EPRI
2019
Site approved before design
On 19 December 2019 the NRC issued early site permit ESP-006 to TVA for its Clinch River site near Oak Ridge, Tennessee, for two or more small modular reactors, valid until 2039. TVA applied in May 2016 without choosing a reactor design. A 2022 national laboratory report notes that the application's emergency planning calculations reached only 2 miles from the site. TVA's 2026 construction permit for a BWRX-300 there built on the conditions of this site permit.
Lessona site's safety and environmental questions can be settled before a design is picked.
Credit
Tennessee Valley Authority; US NRC
2020
A floating plant for Pevek
Akademik Lomonosov, a 140 m barge carrying two 35 MW reactors, was fully commissioned at Pevek in Chukotka, in Russia's Far East, on 22 May 2020. It had been supplying the isolated Chaun-Bilibino grid since 19 December 2019, covering 20% of its demand, and it also supplies heat. It is meant to become the region's main energy source when the old Bilibino nuclear plant closes. Construction began on 15 April 2007, by the World Nuclear Association's record.
Lessoneven a plant built as a vessel, away from its site, took 13 years from the start of construction to commercial operation.
Credit
Rosatom; its operating arm Rosenergoatom
2022
Coal sites screened for reactors
A study by Idaho, Argonne and Oak Ridge national laboratories screened US coal plant sites with public data and OR-SAGE, narrowing them to 157 retired and 237 operating candidates. It found that 80% of the sites it evaluated have the basic features to host an advanced reactor: 125 retired sites with room for 64.8 GWe and 190 operating sites with room for 198.5 GWe. Population was the main limit: 79% of the sites that scored worst in the first screen had more than 500 people per square mile within 4 miles. The study also estimated, for one hypothetical site, that reusing a coal plant's equipment could cut a reactor's construction cost by 15% to 35% compared with a new site.
Credit
Jason Hansen and colleagues at Idaho, Argonne and Oak Ridge national laboratories; DOE Office of Nuclear Energy
2023
Emergency zones sized by dose
Large US reactors plan for an emergency planning zone (EPZ) of about 10 miles (16 km), the area where protective steps such as evacuation are planned in advance. A final NRC rule of 16 November 2023, in force from 18 December 2023, lets small modular reactors and other new designs size the zone instead as the area where a person could receive more than 10 millisieverts (1 rem) in the 96 hours after a release. The NRC notes that several small reactors were already licensed with 5-mile zones, among them Fort St. Vrain, Big Rock Point and La Crosse.
Credit
US NRC
Watch for
Reactors nearer to towns
An NRC proposed rule of 16 July 2026 keeps the agency's preference for sites with few people nearby, but would let applicants place reactors in denser areas, including inside towns of more than about 25,000 people. An applicant would have to show that a site's benefits to society, such as reusing a retired fossil plant's equipment, outweigh the added risk. Comments closed on 31 August 2026, and the NRC says guidance for the assessment will follow.
Achieved whenthe final rule is in force and a permit is granted for a site justified by the new assessment.
Claimed by
US NRC, July 2026
Reactors inside a chemical works
Dow's Long Mott plant at its Seadrift chemical site in Texas would supply the site with power and steam from four Xe-100 reactors, each 80 MWe (200 MW thermal). X-energy says the design's fuel is expected to support an emergency planning zone of 400 m, against 10 miles for conventional reactors. Dow has not decided to build and expects to consider a preliminary investment decision in 2027.
Achieved whenthe NRC approves a zone of about that size in an operating licence and the plant delivers power and steam to the Seadrift works.
Claimed by
X-energy and Dow, November 2026
Microreactor on an air base
On 10 June 2025 the Defense Logistics Agency, for the Department of the Air Force, again named Oklo's Aurora reactor for Eielson Air Force Base in Alaska, under a 30-year fixed-price agreement to buy its electricity and heat. The programme aims to have at least one licensed microreactor running at a base by 31 December 2027. A first notice of intent in August 2023 was rescinded the next month after a bid protest.
Achieved whenthe NRC licenses the Eielson reactor and it delivers electricity and heat to the base.
Claimed by
the Department of the Air Force and the Defense Logistics Agency, June 2025
Open
01
Emergency zones as filed
A public table of the emergency planning zone each small reactor applicant has proposed or been granted, worldwide: the radius, the dose basis, the method used, the regulator's decision and the page of the filing it comes from.
The briefCredit · unclaimed02
People around every planned site
A public table of every announced small reactor site worldwide, giving the number of people within 4 and 20 miles (6.4 and 32 km) and the distance to the nearest town of 25,000 or more, with each site's coordinates tied to a public filing or announcement.
The briefCredit · unclaimed
Open 01 · the brief
Emergency zones as filed
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public table of the emergency planning zone each small reactor applicant has proposed or been granted, worldwide: the radius, the dose basis, the method used, the regulator's decision and the page of the filing it comes from.
Why it is still open
Since the NRC's 2023 rule, each applicant sizes its own zone by dose, so the figures sit in separate filings. NuScale's method, accepted in 2022, could limit a zone to the site boundary at a "wide range of potential plant sites"; TVA's Clinch River calculations reached 2 miles; X-energy expects 400 m for Long Mott. A search found no table that sets these side by side.
federalregister.govworld-nuclear-news.orgosti.govworld-nuclear-news.org
Built with what exists
the Federal Register API; NRC, CNSC and ONR filings; a language model that pulls each zone size with its page reference, in the way the Note "Findings that cite notes" describes; Python; two people to check.
First step
Fill the rows for the four US construction permits (Hermes, Kemmerer, Clinch River, Long Mott) and Darlington.
Done looks like
At least 20 applications in at least three countries, each with a zone radius, dose criterion, status and cited page, and a second person re-checking a random 20% of rows.
Open 02 · the brief
People around every planned site
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public table of every announced small reactor site worldwide, giving the number of people within 4 and 20 miles (6.4 and 32 km) and the distance to the nearest town of 25,000 or more, with each site's coordinates tied to a public filing or announcement.
Why it is still open
The Nuclear Energy Agency's SMR Dashboard rates projects on six measures, siting among them, as progress scores rather than distances or head counts. The NRC's July 2026 proposal would allow denser sites under an assessment whose guidance "will be developed". The 2022 national laboratory study counted people around coal plants, not around announced reactor sites; it cites NRC guidance that discourages sites with more than 500 people per square mile within 20 miles. A University of Michigan team published open data and models scoring more than 30,000 possible US sites, coal plants and brownfields, not the sites companies have announced.
Built with what exists
the European Commission's Global Human Settlement Layer population grid (GHS-POP) and WorldPop, both free; GeoNames for towns; NRC, CNSC and ONR filings and company announcements for coordinates; Python with rasterio.
First step
Do the count for the four sites that already hold a construction permit or licence: Clinch River, Kemmerer, Long Mott and Darlington.
Done looks like
at least 50 announced sites in at least 10 countries, each with populations at 4 and 20 miles from both datasets agreeing within 15%, and a second person checking every site's coordinates against its source.