Removing fuel

Removing fuel means taking the used fuel out of the reactor and its cooling pool, including fuel that melted in an accident, and moving it into sealed casks that can stand on a pad outside.

7

Milestones achieved, from 1986 to 2024.

2

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1986

    Fuel moves to dry casks

    Used fuel first cools in a pool of water beside the reactor. In 1986 the US Nuclear Regulatory Commission (NRC) licensed the first US dry storage installation, at the Surry plant in Virginia. The casks are steel cylinders, welded or bolted shut, wrapped in concrete or more steel for shielding, and the fuel must have cooled in the pool for at least a year first. Moving fuel into casks is what lets a closed plant empty its pool and take the rest of the site apart. Idaho National Laboratory counts 4,169 canisters and casks of used commercial fuel in dry storage in the United States at the end of 2024.

    nrc.govcurie.pnnl.gov

    Credit

    US NRC (license); the Surry plant

  2. 1990

    Melted core removed

    After the 1979 accident at Three Mile Island Unit 2 in Pennsylvania, workers lifted off the reactor vessel's head in July 1984, began removing fuel in October 1985 and finished in January 1990, by the NRC's chronology. Shipments of core debris to Idaho National Laboratory began in July 1986. The NRC says 99% of the fuel was removed; the fuel left behind is estimated at less than 1,125 kg, about 1% of the original core, mostly fine sediment.

    Lessonmost of a melted core can be removed in about four years, while the last fines stay on site for decades.

    nrc.govnrc.gov

    Credit

    GPU (plant owner); US Department of Energy (took the debris)

  3. 2018

    A canister catches

    On 3 August 2018 at San Onofre in California, a loaded fuel canister being lowered into an underground storage vault caught on a metal ring inside the vault, as reported by the San Diego Union-Tribune. Had it slipped off, it could have dropped about 17 to 18 feet. Transfers were put on hold and the NRC sent a special inspection team.

    Lessonlowering a canister into its vault is a heavy-lift job that needs its own checks, not only the crane's.

    neimagazine.com

    Credit

    Southern California Edison (operator); US NRC (inspection)

  4. 2019

    Calder Hall defueled

    Sellafield finished removing 38,953 used fuel rods from the four reactors of Calder Hall in England, which opened in 1956, stopped generating in 2003, and is described by the UK government as "the world's first full-scale nuclear power station." Defueling began in 2011. The fuel cooled in a pond, had its metal casings removed and went to Sellafield's Magnox reprocessing plant.

    gov.uk

    Credit

    Sellafield Ltd; Nuclear Decommissioning Authority

  5. 2021

    Wrecked pools emptied

    At Fukushima Daiichi in Japan, TEPCO had removed 1,331 used fuel assemblies (bundles of fuel rods) from the Unit 4 pool by the end of 2014. At Unit 3, explosions in 2011 had dropped large pieces of equipment into the pool. After several years of clearing that debris, removal began on 15 April 2019 and ended on 28 February 2021 with all 566 assemblies out, using a crane run by a team about 500 meters away. TEPCO said "this was the first time such methods were attempted and there were various problems."

    Lessonin a wrecked building, clearing debris from the pool took longer than moving the fuel.

    world-nuclear-news.orgsmr.nucnet.org

    Credit

    TEPCO

  6. 2021

    Chernobyl fuel goes dry

    On 22 April 2021 Ukraine's nuclear regulator, SNRIU, licensed ISF-2, a dry store at Chernobyl, to take the plant's used fuel: more than 21,000 assemblies built up from 1977 to 2000, held in an older wet store, ISF-1, that was not designed for long-term storage. The project began in 1998 and stalled when the technology supplied by Areva was shown to be inadequate; Holtec International took it over in 2011. The facility cost €400 million, paid by many countries and the European Union.

    Lessona storage design has to fit the actual fuel it will hold; the first one here did not, and the project took 23 years.

    neimagazine.com

    Credit

    Holtec International (builder); SNRIU (license)

  7. 2024

    First grams of melted fuel

    On 7 November 2024 TEPCO pulled about 0.693 g of melted fuel, about 9 mm by 7 mm, out of Fukushima Daiichi Unit 2 with a telescopic device that extends like a collapsible fishing rod. A second grab on 22 April 2025 brought out about 0.187 g. Japan's Ministry of the Environment reports that the first sample is full of voids, breaks apart easily, and has a uranium-235 enrichment of about 1.9%. The first attempt was held up for 19 days in August and September 2024 because pipes were inserted in the wrong order, and again when the arm's camera stopped sending images. World Nuclear News reports an estimated 880 tonnes of fuel debris in Units 1 to 3.

    Lessona simple assembly mistake can stop a remote job for weeks.

    fukushima-mirai.env.go.jpjaif.or.jpwnn.world-nuclear.org

    Credit

    TEPCO (retrieval); Japan Atomic Energy Agency and Nippon Nuclear Fuel Development (analysis labs named by JAIF)

Watch for

  1. Unit 2 pool emptying

    TEPCO has begun removing the 615 assemblies (587 used, 28 unused) from the pool of Fukushima Daiichi Unit 2, one by one by remote crane into a transport cask that goes by trailer to a shared pool on site, and plans to finish by its fiscal year 2028, which ends in March 2029. Work on the Unit 1 pool is to begin in 2027 or 2028.

    Achieved whenall 615 assemblies are in the shared pool, as confirmed by Japan's Nuclear Regulation Authority or the IAEA.

    nucnet.org

    Claimed by

    TEPCO, June 2026

  2. Debris removal by the tonne

    TEPCO says preparing Unit 3 for full-scale removal of melted fuel will take 12 to 15 years, so the work will start in 2037 at the earliest instead of the early 2030s, while it keeps its target of finishing decommissioning in 30 to 40 years.

    Achieved whenTEPCO removes melted fuel from Unit 3 in bulk, with amounts reported by Japan's Nuclear Regulation Authority.

    wnn.world-nuclear.org

    Claimed by

    TEPCO, July 2025

Open

  1. 01

    Count casks from aerial photos

    A year-by-year count of dry storage casks at nuclear plant sites in countries that publish no per-site figures, made by finding casks in published aerial and satellite photos, and joined with the official per-site figures where they exist into one open world table. Use only published imagery; no drone flights near plants.

    The brief
    Credit · unclaimed
  2. 02

    Time to empty the pool

    A public table of every power reactor closed since 1990, giving the date it stopped, the dates its core and its pool were emptied, and the dates its owner had planned for each, every date linked to a public document; then the median time from shutdown to an empty pool, by country and by decommissioning strategy.

    The brief
    Credit · unclaimed

Open 01 · the brief

Count casks from aerial photos

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A year-by-year count of dry storage casks at nuclear plant sites in countries that publish no per-site figures, made by finding casks in published aerial and satellite photos, and joined with the official per-site figures where they exist into one open world table. Use only published imagery; no drone flights near plants.

Why it is still open

Some countries publish per-site figures, each in its own units. Idaho National Laboratory's December 2025 inventory report lists the casks loaded at each US site, from a Department of Energy fuel survey through 2022 and from StoreFUEL data for 2023 and 2024. Canada's Nuclear Waste Management Organization lists the fuel bundles in wet and in dry storage at each reactor site, as of June 2024. No table joining such figures across countries was found, and a search for cask counts made from imagery found only work on imaging the inside of casks with cosmic rays.

curie.pnnl.govnwmo.ca

Built with what exists

USDA NAIP aerial photos (free, US) to calibrate against the INL counts; national open aerial photo services in Europe, such as France's IGN, Spain's PNOA and the Netherlands' PDOK; Google Earth Pro's historical imagery for checks by eye; an object-detection model such as Ultralytics YOLO or Meta's Segment Anything, fine-tuned on one graphics card (see the Note "One GPU to fine-tune"); QGIS.

  1. First step

    Pick five closed US plants, take their counts from the INL report, and count casks by hand on the latest NAIP photo of each.

  2. Done looks like

    Counts at 20 US sites that match the INL table within one cask for the same year, to prove the method; then counts at 40 or more sites in at least 8 other countries, each with its image date and source; a second person recounts 10 sites by hand and agrees within one cask; the world table published under an open license.

Open 02 · the brief

Time to empty the pool

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public table of every power reactor closed since 1990, giving the date it stopped, the dates its core and its pool were emptied, and the dates its owner had planned for each, every date linked to a public document; then the median time from shutdown to an empty pool, by country and by decommissioning strategy.

Why it is still open

The World Nuclear Industry Status Report marks which closed reactors are defueled, which it defines as both the core and the pools emptied, and gives some dates in its country notes, but its 2026 edition publishes counts by stage, not a table of dates or of planned against actual times. Plans sit in each plant's own documents: in 2013 Dominion said the pool at Kewaunee in Wisconsin would be emptied into dry casks by 2020. No table across plants was found.

worldnuclearreport.organs.org

Built with what exists

NRC decommissioning pages and post-shutdown reports; national regulator and operator reports; the WNISR country notes; an AI model that reads long documents and pulls out dated facts with their sources (see the Note "The jobs agents repeat"); a spreadsheet; a second person to check dates.

  1. First step

    Fill the rows for the US reactors closed since 2013, starting from each plant's page on the NRC's list of reactors in decommissioning.

  2. Done looks like

    At least 60 closed reactors in at least 8 countries, every date linked to its source; a second person rechecks 50 dates and agrees on at least 95%; medians published with the table under an open license.