Cutting up reactors

Cutting up a reactor means taking its most radioactive parts, the steel pressure vessel that held the fuel and the internals, the metal structures inside it, out of the building, either in one piece or cut into pieces small enough to pack and ship.

7

Milestones achieved, from 1989 to 2025.

1

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1989

    A vessel shipped whole

    The US Department of Energy took apart the 72 MW Shippingport plant in Pennsylvania between September 1985 and July 1989. It lifted out the reactor pressure vessel, which held 99% of the plant's radioactivity, in one piece and sent it by barge to its Hanford site in Washington for burial. The vessel weighed about 153 tons and stood about 26 feet high, according to the US General Accounting Office. The GAO noted that commercial reactors are much larger and would "probably have to" cut their vessels up, so Shippingport taught the industry little about cutting.

    Lessonthe easiest way to handle a small, clean vessel tells you little about a large, highly radioactive one.

    gao.gov

    Credit

    US Department of Energy

  2. 1996

    Seven cutting methods tried

    The Japan Atomic Energy Research Institute (JAERI) took apart its Japan Power Demonstration Reactor (JPDR), which JAERI says made Japan's first nuclear electricity in 1963, in a project that began in 1981. It cut the reactor internals with a remote plasma arc torch under water, cut the pressure vessel into blocks with an arc saw (a spinning disc that cuts with an electric arc), cut pipes with disc cutters and shaped explosives, and broke up the concrete shield around the reactor with mechanical cutters, a water jet and controlled blasting. All dismantling was finished without accidents by the end of March 1996. It produced 24,400 tons of waste, of which 3,770 tons were radioactive, and JAERI kept the hours worked, worker doses and waste figures in a database for later projects.

    rdreview.jaea.go.jpjaea.go.jp

    Credit

    Japan Atomic Energy Research Institute (now the Japan Atomic Energy Agency)

  3. 1999

    A reactor goes upriver

    Portland General Electric shipped the reactor vessel of its Trojan plant in Oregon with the internals still inside, filled with low-density concrete so nothing could move. The NRC had to grant one-time exemptions from its package test rules, because larger impact limiters (the crush pads bolted to each end) would have made the package too tall to pass under the lowest clearance on the route and added dose to the workers fitting them. The NRC put the package's maximum weight at 925 metric tons; the Associated Press called it a 1,000-ton vessel. Two tugs pushed it 270 miles up the Columbia River in about 36 hours, arriving on 8 August 1999, and a 320-wheel trailer carried it to the Hanford burial site.

    Lessonshipping a vessel whole avoids cutting it, but only where a route exists for a package that size, and only with a one-off approval.

    govinfo.govspokesman.com

    Credit

    Portland General Electric; US Nuclear Regulatory Commission (approval)

  4. 2018

    Laser cutting reaches the core

    A snake-arm robot is a long, bendable arm made of many short links that can thread through a small hole. In 2016 Sellafield used LaserSnake2, a snake-arm robot carrying a laser cutting head, to cut up a 5-tonne steel vessel in a radioactive part of its first reprocessing plant, the first such use on a UK nuclear site, according to the Nuclear Decommissioning Authority (NDA). In 2018 Magnox passed a LaserSnake through a narrow hole in the 3 m concrete shield of the Dragon reactor in Dorset and cut free a 400 mm vessel attached to the core, with less than 3 hours of cutting. Magnox said it believed this was the first time a laser had been used directly on a reactor core, and that the work saved at least £200,000 and four weeks.

    Lessonthe team built two mock-ups and rehearsed on them before making the real cuts.

    gov.ukgov.uk

    Credit

    OC Robotics and TWI (developers); Magnox and Sellafield Ltd (users); NDA (funding)

  5. 2024

    A reactor in four packages

    At Crystal River 3 in Florida, Orano cut and packed the reactor pressure vessel and internals in under two years, finishing in December 2023, using a patented method it calls "optimized segmentation." In October 2024 it reported that the whole dismantled reactor had gone to the Waste Control Specialists disposal site in Andrews County, Texas, in only four large packages, each shipped more than 1,800 miles by barge and trailer. In December 2023, at Fort Calhoun in Nebraska, the plant's owner reported cutting its reactor vessel into 43 pieces of 6,000 to 40,000 pounds with an oxy-propane torch over two months.

    ans.organs.orgoppdthewire.com

    Credit

    Orano, with NorthStar, in the Advanced Decommissioning Partners venture

  6. 2025

    Four Swedish vessels cut up

    A consortium of Nukem Technologies and Uniper Nuclear Services finished taking apart the fourth and last of the reactor pressure vessels it was hired in 2020 to dismantle in Sweden, two at Barsebäck and two at Oskarshamn, all boiling water reactors. It cut the last vessel in place with flame cutting, and Uniper packed the pieces into containers, NucNet reported in February 2025.

    nucnet.organs.org

    Credit

    Nukem Technologies Engineering Services and Uniper Nuclear Services

  7. 2025

    One supplier, seven years

    In May 2025 Japan Atomic Power moved the finish of decommissioning at Tsuruga-1, Japan's first commercial light water reactor, back seven years, from fiscal 2040 to fiscal 2047. The maker hired to take apart part of the containment, the suppression chamber, had withdrawn, and the replacement needed time to develop the cutting equipment. Reactor dismantling had been due to start in fiscal 2026.

    Lessonwhen a cutting job depends on equipment only one maker builds, losing that maker can move the finish date by years.

    jaif.or.jp

    Credit

    Japan Atomic Power Company (record); Japan Atomic Industrial Forum (report)

Watch for

  1. Japan's first commercial vessels

    Chubu Electric lifted the vessel lid of Hamaoka 2 in March 2025, which World Nuclear News called the first commercial power reactor in Japan to enter dismantling, and lifted the lid of Hamaoka 1 on 7 October 2025. Chubu says it will cut the pressure vessels and containment with large devices such as band saws, store the waste in the building until a disposal site is chosen, and finish the reactor area by fiscal 2035. In October 2025 Japan's Nuclear Reprocessing and Decommissioning Facilitation Organization (NuRO) started a pilot project with the ten power companies to settle methods for cutting up reactors, using Hamaoka 1 and 2 as the test plants.

    Achieved whenboth vessels and their internals have been cut up and removed, as confirmed by Japan's Nuclear Regulation Authority.

    world-nuclear-news.orgjaif.or.jp

    Claimed by

    Chubu Electric and NuRO, October 2025

Open

  1. 01

    Shared test for cut plans

    A public test case and open-source planner for cutting up and packing a reactor vessel and internals. The test case is a 3D model of a generic pressurized water reactor vessel built from published dimensions, an assumed map of how radioactive each part is, a set of standard waste container sizes, and a scoring script that counts cut length, pieces and containers. The planner proposes cut lines and a packing plan and is scored against simple baselines, such as a uniform grid of cuts.

    The brief
    Credit · unclaimed
  2. 02

    Teach a robot cut paths

    A test of whether open robot models, trained from a few dozen demonstrations, can trace cut paths on containers of unknown shape. Use the low-cost mock-up published in 2026, in which a robot arm holds an ultraviolet torch that marks the light-sensitive faces of a box in place of a laser, so nothing is actually cut and no laser is used.

    The brief
    Credit · unclaimed

Open 01 · the brief

Shared test for cut plans

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public test case and open-source planner for cutting up and packing a reactor vessel and internals. The test case is a 3D model of a generic pressurized water reactor vessel built from published dimensions, an assumed map of how radioactive each part is, a set of standard waste container sizes, and a scoring script that counts cut length, pieces and containers. The planner proposes cut lines and a packing plan and is scored against simple baselines, such as a uniform grid of cuts.

Why it is still open

Published methods are each tested on one plant's own model. A 2022 study packed the cut pieces of South Korea's Kori-1 vessel into 24 containers against 42 in the earlier plan, and cites a 2019 method that plans cuts with genetic algorithms; neither offers a shared test geometry. Orano's optimized segmentation is a patented in-house process. No public test case was found in this session.

koreascience.or.krans.org

Built with what exists

FreeCAD or OpenSCAD for the model; Python with trimesh for geometry; Google OR-Tools for the packing search; public dimensions such as those in the Trojan package notice and Fort Calhoun's report (32 feet tall, 14 feet wide, 7- to 10-inch walls).

  1. First step

    Model a generic vessel from the Fort Calhoun and Trojan dimensions and post it with the scoring script.

  2. Done looks like

    The test case, scoring script and planner are published under an open license; the planner beats the uniform-grid baseline by at least 20% in containers used, with every piece under a stated weight limit; at least one other team submits a scored plan.

Open 02 · the brief

Teach a robot cut paths

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A test of whether open robot models, trained from a few dozen demonstrations, can trace cut paths on containers of unknown shape. Use the low-cost mock-up published in 2026, in which a robot arm holds an ultraviolet torch that marks the light-sensitive faces of a box in place of a laser, so nothing is actually cut and no laser is used.

Why it is still open

The mock-up's authors steered the torch with a model-based controller along given paths and reported a mean error of 2.4 mm to 3.9 mm. A 2019 Birmingham paper planned rough cut paths over unknown surfaces from a depth camera. In real work, LaserSnake was "controlled from a distance by specialist operators." No published test of a policy learned from demonstrations on such a mock-up was found.

arxiv.orgarxiv.orggov.uk

Built with what exists

a six-axis arm such as a UR5e or a low-cost SO-101; a UV LED torch and UV-sensitive paper; two depth cameras; LeRobot's open training code with an open robot model such as Runway's Praxis-1 (see the Note "Open robot model weights") or NVIDIA's GR00T 2 (see the Note "Five demonstrations per task").

  1. First step

    Rebuild the mock-up from the paper and record 30 teleoperated demonstrations on one box shape.

  2. Done looks like

    20 filmed attempts on five box shapes not seen in training, each trace photographed and compared with the drawn cut line, and a published tally of attempts within 5 mm mean error, with videos, data and code.