Industries / Industrial equipment and services / Industrial services / Turnaround management
Planning and scheduling
Planning turns the work list into job packages, with crafts, hours, scaffolds, cranes, parts and permits. Scheduling fits them into the shortest safe shutdown.
4
Milestones achieved, from 1959 to 2016.
1
To watch for: announced, not yet confirmed outside.
1
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
1959
A library of shutdown schedules
At DuPont's Louisville Works, which had many shutdowns a year, planners found that most jobs recur every time. They computed a library of typical schedules with the critical path method and took the closest one before each shutdown. The average shutdown fell from 125 hours to 93, and the authors expected 78 once critical jobs were worked faster.
Credit
James E. Kelley Jr. and Morgan R. Walker, for DuPont and Remington Rand
1999
The first textbook
Butterworth-Heinemann published Tom Lenahan's Turnaround Management in July 1999, written from his years with ICI and with Eutech Engineering Services. It sets the work in order: strategy, confirming the scope, pre-shutdown work, contractor packages, the plan, the team, site logistics, cost, safety, quality, running the turnaround and closing it.
Credit
Tom Lenahan
2012
Overruns put in numbers
Gordon Lawrence of AP-Networks, with execution data on more than 750 turnarounds from almost 40 firms, found that turnarounds overrun their estimates by 16% on average, from 27% under to 43% over. Teams set aside about 9 to 10% for unknown work and used 13 to 20%. He split the unknowns into forgotten work, emerging work, discovery work (defects found only when equipment is opened) and true contingency, and argued that only the last cannot be estimated line by line.
LessonWork found after opening is predictable enough to plan for.
Credit
Gordon Lawrence, AP-Networks
2016
Two in three miss
AP-Networks reported that more than two-thirds of turnarounds in its database exceeded planned cost and schedule by 10% or had a trip after startup, and 40% overran cost or schedule by more than 30%.
Credit
Shawn Hansen and Brett Schroeder, AP-Networks
Watch for
Short turnarounds and AI planners
Chevron vice chairman Mark Nelson said that more than 80% of Chevron's US refinery turnarounds over the last two years were completed with "first-quartile duration", without naming the benchmark or peer group. On the same call its chief financial officer, Eimear Bonner, said "human agent teams" were helping with turnaround and refinery planning.
Achieved whena named benchmarking firm, or a filing, publishes the duration figures and the peer set they are measured against.
Claimed by
Chevron, 30 October 2026
Open
01
A public turnaround record
A public table of refinery and chemical plant turnarounds, each with the planned start and length as announced and the actual dates as later reported, and with every figure linked to the filing, press release or trade report it came from.
The briefCredit · unclaimed
Open 01 · the brief
A public turnaround record
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public table of refinery and chemical plant turnarounds, each with the planned start and length as announced and the actual dates as later reported, and with every figure linked to the filing, press release or trade report it came from.
Why it is still open
The large turnaround databases belong to benchmarking firms such as AP-Networks and are not public. An October 2026 review of US refiners' results found that public disclosure cannot tell genuine longer runs from deferred maintenance, and that no company reports a turnaround spending line.
Built with what exists
SEC EDGAR full-text search; company news releases and earnings call transcripts; Python; an AI model that reads long documents and pulls out dates (see the Note "Seven more flagged").
First step
Collect every turnaround start and finish that Chevron, ExxonMobil, Valero and Marathon named in 2025 and 2026 earnings calls and releases.
Done looks like
At least 300 turnarounds from 2015 to 2026 with planned and actual dates, a published median overrun, and 50 rows checked by a second person with at least 95% agreement.