Deciding the scope
Deciding the scope means choosing which jobs go into a turnaround, which can be done while the unit runs, and how long the unit can run before the next one.
4
Milestones achieved, from 1996 to 2016.
1
To watch for: announced, not yet confirmed outside.
1
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
1996
Inspection ranked by risk
In 1993 the American Petroleum Institute (API) started a project, sponsored by 23 companies including Amoco, Exxon, Shell, Chevron and Saudi Aramco, to rank equipment for inspection by the chance and the consequence of its failure. This is risk-based inspection (RBI). The group published its Base Resource Document in October 1996, and API released RP 580 on the method in 2002. RBI lists are now a main input to turnaround scope.
Credit
API and its sponsor group; history as told by Lynne Kaley of Pinnacle
1999
A job that should have waited
On 23 February 1999 workers at Tosco's Avon refinery in Martinez, California, replaced corroded naphtha piping 112 feet up a fractionator tower while the tower kept running above 500°F. The unit operator had argued for shutting down first, but a maintenance supervisor decided to go ahead. Naphtha sprayed out of the open pipe and ignited, killing four workers. The CSB, the US Chemical Safety Board, told the refinery to write a protocol for deciding when a job needs a shutdown.
LessonSome repairs belong in a shutdown, and the choice should not rest with one supervisor under time pressure.
Credit
CSB investigation, report March 2001
2000
The examiner sets the interval
The UK's Pressure Systems Safety Regulations came into force on 21 February 2000. A pressure system may not be run without a written scheme of examination, drawn up or certified by a competent person, that sets the nature and frequency of each examination. That scheme decides which vessels must be opened in a turnaround and how often.
Credit
UK government
2016
Scope growth measured
Shawn Hansen and Brett Schroeder of AP-Networks, from a database of more than 1,350 turnarounds, reported that the work list grows on average 19% between scope freeze, the date the list is meant to close, and the shutdown itself, against 7% for the best quarter of turnarounds.
Credit
AP-Networks (Asset Performance Networks)
Watch for
Open code for risk ranking
An unofficial Python package for the API RP 581 risk-based inspection calculations, published on GitHub in October 2026, says it has 509 calculations traced to 861 sections of the standard. Its author calls it "software-verified" and states that outside evaluation is out of the project's scope.
Achieved whenan inspection engineer outside the project runs the standard's worked examples, or a commercial RBI program's results, through it and publishes the match.
Claimed by
GitHub user lyullee, October 2026
Open
01
Run or wait, a casebook
A public casebook of at least 200 maintenance jobs taken from published accident reports, each coded for whether it was done on a running unit or in a shutdown, whether the equipment could be isolated and drained, and what happened. Then a written set of rules, and an AI model that applies them, that flags jobs which should wait for a shutdown.
The briefCredit · unclaimed
Open 01 · the brief
Run or wait, a casebook
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public casebook of at least 200 maintenance jobs taken from published accident reports, each coded for whether it was done on a running unit or in a shutdown, whether the equipment could be isolated and drained, and what happened. Then a written set of rules, and an AI model that applies them, that flags jobs which should wait for a shutdown.
Why it is still open
After Tosco in 1999 the CSB asked for a written protocol for shutdown decisions, but the protocols plants wrote are internal. A search found no public casebook or tool for this choice.
Built with what exists
CSB reports and the French accident database ARIA, both public; a spreadsheet; an AI model that reads long documents (see the Note "Seven more flagged").
First step
Code the 20 CSB investigations that mention work on a running unit, with the fields above, and ask one retired operator to check them.
Done looks like
200 coded cases published, and on 50 held-back cases the tool agrees with two experienced operators at least as often as the operators agree with each other.