Industries / Energy, water and waste / Power generation
Nuclear
Nuclear plants use the heat from splitting uranium atoms in a reactor to make steam for a turbine.
6
Milestones achieved, from 1951 to 2024.
2
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
In depth
The same ground is charted in more depth, as an industry of its own.
The road
AchievedWatch forOpen
Achieved
1951
First electricity from a reactor
On 20 December 1951 Experimental Breeder Reactor I, at what is now Idaho National Laboratory, lit a string of four light bulbs. In 1953 it showed it could make more nuclear fuel than it used, which is what "breeder" means. ASME calls it the world's first nuclear power plant.
Credit
Walter Zinn, Argonne National Laboratory
1954
Obninsk joins the grid
The IAEA says the world's first civilian nuclear power plant was commissioned on 26 June 1954 at Obninsk, then in the Soviet Union, with a net capacity of 5 MW. It also supported research, ran for 48 years and was unloaded in September 2002.
Credit
the Soviet nuclear program at Obninsk
1957
Shippingport powers Pittsburgh
On 18 December 1957 the Shippingport station in Pennsylvania began feeding the grid for the Pittsburgh area. ASME calls it the first US commercial central generating station to use nuclear energy.
Credit
Westinghouse, with the Atomic Energy Commission's Division of Naval Reactors (design); Duquesne Light Company (operator)
1979
Three Mile Island
On 28 March 1979 a relief valve at Three Mile Island Unit 2, near Middletown, Pennsylvania, stuck open while the control-room indicator showed it closed. Operators did not see that coolant was escaping, cut back emergency cooling, and the core partly melted. The NRC calls it the most serious accident in US commercial nuclear power history; off-site releases were very small and investigations found no detectable health effects.
Lessonan instrument that misleads operators can turn a routine fault into an accident.
Credit
US Nuclear Regulatory Commission (record)
2011
Fukushima Daiichi melts down
A massive earthquake on 11 March 2011 was followed by a tsunami that flooded the Fukushima Daiichi plant in Japan and cut all AC power to Units 1 to 5. The reactor cores in Units 1 to 3 overheated and their fuel melted, and more than 100,000 people were evacuated. The IAEA's 2015 report calls it the worst nuclear plant accident since Chernobyl in 1986 and names "a major factor": a widespread assumption in Japan that an accident of this size "was simply unthinkable."
Lessonplan for a natural disaster larger than any on record.
Credit
IAEA, report by the Director General
2024
Vogtle's late, costly reactors
Vogtle Unit 3 in Georgia began commercial operation in July 2023 and Unit 4, rated 1,114 MW, in April 2024. Both use Westinghouse's AP1000 design. EIA reports the pair were expected to cost about $14 billion and start in 2016 and 2017; Georgia Power now puts the total above $30 billion.
Lessonthe first builds of a new design cost far more and take far longer than planned.
Credit
Georgia Power and its co-owners; Westinghouse
Watch for
Four test reactors go critical
The US Department of Energy says four privately built advanced reactors reached criticality, a self-sustaining chain reaction, under its Reactor Pilot Program by 4 July 2026: Antares Nuclear's Mark-0, Valar Atomics' Ward 250 and Deployable Energy's Unity in June, and Aalo Atomics' Aalo-X on 4 July. The target of three came from a May 2025 executive order. DOE describes the Aalo-X run as a zero-power test, which makes no electricity.
Achieved whenone of these designs supplies electricity to a grid at its rated power, as recorded by its regulator or grid operator.
Claimed by
DOE and the four companies, July 2026
A closed plant restarts
Holtec International plans to return the 805 MW Palisades plant in Michigan, which last ran in 2022, to service. The American Nuclear Society reports it would be the first US nuclear plant to return to operation after permanent shutdown, and that an earlier target of grid connection by the end of February 2026 had passed. By September 2026 Holtec had begun loading fuel.
Achieved whenPalisades is connected to the grid and runs at full power, as recorded by the NRC.
Claimed by
Holtec International, July to September 2026
Open
01
Test open nuclear search models
An independent, repeatable test of Atomic Canyon's FERMI models on questions about public NRC documents, written and checked by people outside the company. FERMI models are retrieval models: they find the passages that answer a question, the first step of most AI document assistants.
The briefCredit · unclaimed02
Promised dates versus real ones
An open record of every advanced and small reactor project's announced dates for licensing, construction, first criticality and first power, set beside what actually happened, with each date linked to its source.
The briefCredit · unclaimed
Open 01 · the brief
Test open nuclear search models
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
An independent, repeatable test of Atomic Canyon's FERMI models on questions about public NRC documents, written and checked by people outside the company. FERMI models are retrieval models: they find the passages that answer a question, the first step of most AI document assistants.
Why it is still open
The models are free under the Apache 2.0 license, but their scores come from FermiBench, a benchmark the developer built itself "due to the absence of domain-specific benchmarks." A search found no outside evaluation.
Built with what exists
FERMI weights and Atomic Canyon's evaluation tooling, built on BEIR and pyserini; public documents from the NRC's ADAMS library; a language model to draft candidate questions; two people with nuclear engineering training to write and check the answers; one graphics card.
First step
Write 50 questions from 20 public NRC inspection reports and score one FERMI model on them.
Done looks like
500 questions, each tied to the pages that answer it, with FERMI and two general-purpose retrieval models scored by NDCG@10 (a standard score for how well the right passages rank near the top), and a second group re-running the test to within one point.
Open 02 · the brief
Promised dates versus real ones
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
An open record of every advanced and small reactor project's announced dates for licensing, construction, first criticality and first power, set beside what actually happened, with each date linked to its source.
Why it is still open
The Nuclear Energy Agency's SMR Dashboard rates 56 designs on six measures (licensing, siting, financing, supply chain, engagement and fuel), and its launch page says nothing about announced dates or slips. Recent targets have moved: Palisades missed an end-of-February 2026 grid date.
Built with what exists
NRC and Canadian Nuclear Safety Commission licensing records; utility filings; company press releases and archived web pages; a language-model agent that collects dated claims and cites each one (see the Note "Findings that cite notes"); two human checkers.
First step
Build the record for the four DOE pilot reactors and Palisades from their own announcements since 2024.
Done looks like
At least 40 projects, each with every public target date and its source, slips computed in months, a second person re-checking a random 20% of dates, updated each quarter.