Coal and gas plants burn fuel to make steam or hot gas, which spins a turbine connected to a generator.

6

Milestones achieved, from 1882 to 2024.

2

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1882

    A central station opens

    Pearl Street Station in lower Manhattan began supplying about 85 customers and 400 lamps on 4 September 1882. Six "Jumbo" dynamos of about 100 kW each were driven by steam engines fed by four coal-fired boilers, and the station sold power to many buildings from one place. IEEE's plaque calls it "the forerunner of all central electric generating stations."

    ethw.org

    Credit

    Thomas Edison; Edison Electric Illuminating Company of New York

  2. 1884

    The steam turbine

    Charles Parsons built an experimental steam turbine generator in Newcastle upon Tyne in 1884 that ran at 18,000 revolutions per minute. A turbine is spun steadily by jets of steam instead of being pushed back and forth by pistons, which suits fast-running generators. The Science Museum, which holds the machine, calls it the forerunner of the turbo-generators that make most of the world's electricity today.

    collection.sciencemuseumgroup.org.uk

    Credit

    Charles Parsons; Clarke, Chapman, Parsons and Company

  3. 1939

    A gas turbine makes power

    Brown Boveri installed a 4 MW gas turbine in the municipal power station of Neuchâtel, Switzerland, in 1939. A gas turbine burns fuel in compressed air and is spun by the hot gas directly, with no boiler. This one turned 17.4% of its fuel's energy into electricity. ASME calls it the world's first successful electricity-generating gas turbine to go into commercial operation.

    asme.org

    Credit

    Brown Boveri; Aurel Stodola supervised its acceptance tests

  4. 1957

    Steam past the critical point

    Philo Unit 6 in Ohio, a 125 MW unit, began delivering power on 20 May 1957 with steam at 4,500 psi (31 MPa) and 1,150 °F (621 °C). At that pressure, above water's critical point, water turns to steam without boiling, and the plant gets more work from each unit of fuel. ASME calls it the world's first supercritical-pressure unit to operate commercially, with efficiency approaching 40% when the national average for fossil plants was 29.9%.

    asme.org

    Credit

    American Gas and Electric Company (now AEP); Babcock & Wilcox (boiler); General Electric (turbine-generator)

  5. 2017

    Kemper's coal gasifier stops

    Mississippi Power's 582 MW Kemper County plant was built to turn local lignite (soft brown coal) into gas and capture up to 65% of its carbon emissions. On 28 June 2017, with total costs above $7.5 billion including its mine and carbon dioxide pipeline, against an approved 2012 estimate of $2.4 billion that left those out, the company suspended the gasifier. The plant kept running on natural gas only, as state regulators had asked.

    Lessona first-of-a-kind plant can be overtaken by a cheaper fuel while it is still being built.

    powermag.com

    Credit

    Mississippi Power and Southern Company; Mississippi Public Service Commission

  6. 2024

    A gas plant efficiency record

    Guinness World Records verified on 21 May 2024 that Keadby 2, a gas plant run by SSE Thermal in North Lincolnshire, UK, reached 64.18% efficiency, the highest for a combined-cycle plant. A combined-cycle plant runs a gas turbine, then uses the turbine's hot exhaust to make steam for a second turbine. Guinness lists Siemens Energy as the record holder.

    guinnessworldrecords.com

    Credit

    SSE Thermal; Siemens Energy

Watch for

  1. Half hydrogen in a turbine

    Georgia Power and Mitsubishi Power say they ran one M501GAC gas turbine at Plant McDonough-Atkinson in Smyrna, Georgia, on blends of 5% to 50% hydrogen by volume, at partial and full load, over several weeks in May and June 2025. Burning hydrogen makes no carbon dioxide; the companies put the reduction at about 22% for the 50% blend. Mitsubishi Power calls it the first validation of a 50% blend on an advanced-class gas turbine. It reports no figures for nitrogen oxides, a pollutant that rises with hotter hydrogen flames, and names no independent tester.

    Achieved whena plant runs on such a blend in routine service, with emissions confirmed by a regulator or another outside party.

    power.mhi.com

    Claimed by

    Georgia Power and Mitsubishi Power, June 2025

  2. Hydrogen in an existing unit

    Kansai Electric Power retrofitted the roughly 480 MW Unit 5 gas turbine at its Himeji No. 2 station with a Mitsubishi Heavy Industries combustor and co-fired it with up to 30% hydrogen by volume; tests were largely complete by the end of September 2025. NEDO, the Japanese agency that funded it, reports stable combustion after tuning and calls up to 30% "technically feasible" in existing large gas turbines. It does not mention outside verification.

    Achieved whenhydrogen co-firing runs in commercial operation (Kansai targets around 2030) with results checked by an outside party.

    green-innovation.nedo.go.jp

    Claimed by

    Kansai Electric Power, through NEDO, tests completed September 2025

Open

  1. 01

    Measure how European plants flex

    An open table, for every coal, lignite and gas unit in Europe that reports its hourly output, of how low it can run steadily, how fast it ramps up and down, and how often it starts. These numbers decide how well a fossil fleet can fill in around wind and solar.

    The brief
    Credit · unclaimed
  2. 02

    Open pictures of turbine blades

    A public, labeled set of borescope images of gas-turbine blades from power plants, with damage such as cracks, burns and coating loss marked, and a baseline model that finds it. A borescope is a thin camera pushed inside a turbine so it can be inspected without taking it apart.

    The brief
    Credit · unclaimed

Open 01 · the brief

Measure how European plants flex

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

An open table, for every coal, lignite and gas unit in Europe that reports its hourly output, of how low it can run steadily, how fast it ramps up and down, and how often it starts. These numbers decide how well a fossil fleet can fill in around wind and solar.

Why it is still open

For the United States, Catalyst Cooperative's open PUDL project already estimates minimum stable load and ramp rates for each unit from EPA's hourly emissions data, but its method covers US units only. ENTSO-E, the body of European grid operators, publishes the hourly output of every generation unit of 100 MW or more. A search found no study or dataset that derives the same measures from it.

docs.catalyst.coopeepublicdownloads.entsoe.eu

Built with what exists

ENTSO-E Transparency Platform data (free account); PUDL's published method as the template; Python; a coding agent to write and test the data pipeline, with each step linked to the evidence behind it (see the Note "Findings that cite notes").

  1. First step

    Download one year of hourly output for German lignite and gas units and compute minimum stable output for ten of them.

  2. Done looks like

    Values for at least 300 units in at least five countries, published with code; the same code, run on 20 US units from EPA data, matches PUDL's published values within 5%.

Open 02 · the brief

Open pictures of turbine blades

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public, labeled set of borescope images of gas-turbine blades from power plants, with damage such as cracks, burns and coating loss marked, and a baseline model that finds it. A borescope is a thin camera pushed inside a turbine so it can be inspected without taking it apart.

Why it is still open

Researchers at Xi'an Jiaotong University write that "due to commercial rights and copyright issues, there is still a lack of open source aero-engine blade datasets," and that the few that exist are small or lack labels. A search found no public set for power-plant gas turbines.

arxiv.org

Built with what exists

Scrapped blades from turbine repair shops or scrap dealers, imaged on a bench with an industrial borescope; open image-segmentation models; vision-language models to suggest first-pass labels; two experienced turbine inspectors to set the final labels.

  1. First step

    Ask three turbine repair shops for scrapped blades, and image 20 to test the label scheme.

  2. Done looks like

    At least 2,000 images from at least 200 blades, labeled by two inspectors with their agreement reported, released under an open license with a baseline detection score.