Scheduling is deciding which supply vessels to hire, which platforms each one visits and when, from which shore base, at what speed, and whether operators share them.

6

Milestones achieved, from 2000 to 2021.

1

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 2000

    Supply routes by optimization

    Optimization is the branch of math that searches for the cheapest plan that meets every constraint. Kjetil Fagerholt and Håkon Lindstad used it to choose the vessels and weekly schedules for platforms in the Norwegian Sea served from one onshore base, testing six scenarios for platform opening hours and visits per week. The recommended policy showed "potential savings of 7 million dollars," and they report that it was put into use.

    ideas.repec.org

    Credit

    Kjetil Fagerholt; Håkon Lindstad

  2. 2009

    Slower trips to save fuel

    Statoil had the 20 supply ships working for it sail round trips at 12 knots instead of the 15 they could make. On one trip from the Ågotnes base to the Statfjord, Kvitebjørn and Veslefrikk fields that cut more than 6 tonnes of CO2, or 1,900 tonnes a year, by Statoil's figures, and the run to Statfjord took nine hours instead of eight.

    Lessonslower sailing saves fuel only when the schedule leaves room for the extra hour.

    equinor.com

    Credit

    Statoil (project manager Ellen Karoline Norlund)

  3. 2012

    Fleet and routes planned together

    Elin Halvorsen-Weare and colleagues published a method that chooses both how many supply vessels to hire and the weekly voyages each one sails. By their account "Statoil has implemented a planning tool based on the voyage-based solution method and reports significant savings," with no figure given.

    ideas.repec.org

    Credit

    Elin E. Halvorsen-Weare, Kjetil Fagerholt, Lars Magne Nonås and Bjørn Egil Asbjørnslett; Statoil

  4. 2019

    Shared North Sea vessel pools

    The logistics company Peterson says it has run vessel sharing in the southern North Sea for more than 20 years and, from about 2017, a pool serving three operators in the central and northern North Sea. It says pooling can cut passage time by up to 50%, worth over £1 million per vessel per year, figures that are its own.

    oedigital.com

    Credit

    Peterson

  5. 2020

    Two operators, one vessel

    Wintershall Dea's Brage platform gave up a vessel of its own: the Energy Swan now sails a fixed route that also serves Equinor's Statfjord A, B and C and Veslefrikk platforms, with cargo gathered at one base at Mongstad. Neither company gave a figure for the savings.

    oedigital.com

    Credit

    Wintershall Dea Norge; Equinor; Golden Energy Offshore, the vessel's owner

  6. 2021

    Port work eats sleep

    On 25 June 2021 the supply vessel Elliot Cheramie struck an uncrewed platform 77 miles southwest of Port Fourchon, Louisiana, after its mate fell asleep on watch; he had been awake for 19 hours, most of them loading and unloading in port. Four people had minor injuries, and the damage cost $362,814. The NTSB found the owner had not kept to its own 12-hour work limit.

    Lessona sailing schedule that ignores the hours spent working cargo in port is not a safe one.

    ntsb.gov

    Credit

    US National Transportation Safety Board, report MIR-23-01

Watch for

  1. Vessel sharing in one plan

    Kabal, a vessel planning software company, says it has worked with Equinor since 2024 on sharing vessels between operators, and that Equinor, Vår Energi and OKEA now plan vessel schedules together "in one unified environment," with a smaller fleet and more frequent service. It gives no figures.

    Achieved whenan operator or an independent party publishes measured results, such as vessel days, fuel or CO2 saved.

    kabal.com

    Claimed by

    Kabal, March 2026

Open

  1. 01

    Measure what sharing saves

    A reconstruction, from ship-tracking records, of a year of supply voyages from one base such as Mongstad, showing which vessels sailed, which platforms they called at and for how long, and a plan for the same calls with every vessel shared, to show the vessel days sharing would save.

    The brief
    Credit · unclaimed
  2. 02

    Add weather to test problems

    A version of the public test problems for routing platform supply vessels with hourly waves and wind at each platform attached, and a script that scores how a plan holds up when weather stops cargo lifts.

    The brief
    Credit · unclaimed

Open 01 · the brief

Measure what sharing saves

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A reconstruction, from ship-tracking records, of a year of supply voyages from one base such as Mongstad, showing which vessels sailed, which platforms they called at and for how long, and a plan for the same calls with every vessel shared, to show the vessel days sharing would save.

Why it is still open

Sharing deals and software claims come without public numbers: the 2020 Brage agreement gave none, and neither does Kabal's 2026 claim. A SINTEF proof of concept maps supply-vessel tracks on data it does not publish, and an open project that reruns offshore logistics papers on Norwegian maps does not measure real voyages.

oedigital.comgithub.comgithub.com

Built with what exists

Norway's open AIS data, installation positions from Sodir, the PyVRP or Google OR-Tools route solvers, Python.

kystverket.no

  1. First step

    Pull one month of AIS tracks for vessels leaving Mongstad and split them into voyages.

  2. Done looks like

    A published table of one year of voyages from one base and a shared plan that serves the same calls, with the vessel days of each and the code to rerun both.

Open 02 · the brief

Add weather to test problems

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A version of the public test problems for routing platform supply vessels with hourly waves and wind at each platform attached, and a script that scores how a plan holds up when weather stops cargo lifts.

Why it is still open

The public problem set from Carnegie Mellon University, published with a 2024 paper by Silva, Wang, Filho and Gounaris, gives vessels, orders, fuel costs and time windows for platforms off south-east Brazil, but no weather.

gounaris.cheme.cmu.edu

Built with what exists

The Carnegie Mellon problems, Copernicus ERA5 hindcast waves and wind, PyVRP or Google OR-Tools, Python.

  1. First step

    Attach ERA5 wave heights to the six platforms of one problem and replay a good plan through one winter.

  2. Done looks like

    Every problem re-issued with ten years of hourly weather, and two planning methods scored on late deliveries and extra vessel hours across those years.