Cleaning and releasing the site
This work removes or measures the radioactivity left in buildings, soil and groundwater, proves with a final survey that what remains is below a legal limit, and ends the license so the land can be used for anything.
6
Milestones achieved, from 1974 to 2011.
2
To watch for: announced, not yet confirmed outside.
3
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
1974
First site restored
Elk River, a small boiling water reactor in Minnesota owned by the US Atomic Energy Commission and rated at about 23 MW of electricity, stopped producing power on 31 January 1968. Crews took it apart and returned the site to its condition before the reactor was built; the final site survey is dated 23 July 1974. By the NRC's 1982 summary the project cost $6.15 million in 1973 dollars, and about 100 workers received a combined radiation dose of 75 rem (0.75 sievert). A 1992 paper calls it the first dismantlement of a power reactor in the United States.
Credit
US Atomic Energy Commission (owner); United Power Association (dismantling)
1995
A green field in Bavaria
Niederaichbach, a 100 MW prototype built by Siemens, was shut on 31 July 1974 after the equivalent of 18.3 days at full power. It sat sealed in safe storage from 1975 to 1981 and was dismantled from 1988 to 1993. After measurements showed the remaining buildings free of artificial radioactivity, it was released from Germany's Atomic Energy Act in 1994, which the Karlsruhe research center calls the first release of a plant of this size in Europe. On 17 August 1995 the site was handed back as a meadow. The project cost DM 268.8 million against an expected DM 280 million, and about 2,800 tonnes of steel and 33,000 m³ of crushed concrete were recycled.
Credit
Forschungszentrum Karlsruhe (now KIT); the NOELL and NIS consortium (dismantling)
1997
A dose limit for release
The NRC's license termination rule, in force from 20 August 1997, set one test for releasing land and buildings for any use: the leftover radioactivity must give an average member of the most exposed group no more than 0.25 millisievert (25 millirem) a year, and be reduced as low as reasonably achievable. Before the rule, reactors were released against surface contamination levels in the NRC's Regulatory Guide 1.86.
Credit
US Nuclear Regulatory Commission
1998
One survey manual, four agencies
In February 1998 the US Department of Defense, Department of Energy, Environmental Protection Agency and NRC announced MARSSIM, a shared manual for planning, taking, evaluating and documenting radiation surveys of soil and building surfaces. Its center is the final status survey, the last round of measurements that shows a site meets the release limit. A second revision came out in July 2026.
Credit
US Department of Defense, Department of Energy, Environmental Protection Agency and Nuclear Regulatory Commission
2004
Numbers for clearing material
The International Atomic Energy Agency published activity levels below which material from a nuclear site can be "cleared", meaning released from regulation and reused or sent to an ordinary landfill. They were set so that nobody would receive more than about 10 microsieverts a year; for cobalt-60 and cesium-137 the level is 0.1 becquerel per gram (a becquerel is one atom decaying per second). In Germany, GRS reports that about 97% of the material from a plant's controlled area, typically about 200,000 tonnes, can be cleared, leaving about 3% as radioactive waste. IAEA guides GSG-17 and GSG-18 have since replaced the 2004 guide.
Credit
International Atomic Energy Agency; GRS (German figures)
2011
Leaks become cleanup bills
In 2005 and 2006 the operators of several US plants reported that radioactive water, mostly carrying tritium, had leaked without being noticed, in some cases for years. The NRC's Decommissioning Planning rule, published on 17 June 2011 and in force from 17 December 2012, requires licensees to keep radioactivity out of soil and groundwater while they operate, to survey for it, and to keep those records for decommissioning. Its stated aim is to prevent "legacy sites", where an owner cannot finish the cleanup for technical or financial reasons.
Lessoncontamination missed while a plant runs becomes a cost when it closes.
Credit
US Nuclear Regulatory Commission
Watch for
Crystal River asks for release
Accelerated Decommissioning Partners (ADP), a joint venture of NorthStar and Orano that took over Florida's Crystal River 3 in October 2020, submitted a license termination plan to the NRC in October 2025, supplemented in December 2025 and February 2026, and separately asked to release 618 acres (250 hectares) of the site. Basement structures will be left in place. The NRC accepted the plan for review on 26 February 2026, issued a finding of no significant environmental impact for the land release in September 2025, and sent the Oak Ridge Institute for Science and Education to check the basements in January 2026, with a second survey planned for May 2026.
Achieved whenthe NRC approves the plan and releases the site, apart from the spent fuel storage area, for unrestricted use.
Claimed by
Accelerated Decommissioning Partners, October 2025 to February 2026
Release rules without ALARA
In July 2026 the NRC proposed removing the term "as low as reasonably achievable" (ALARA), the principle that doses should be cut further whenever that is reasonable, from its site release rules. The 25 millirem limit would stay. Owners would instead show that further cleanup is not justified given its own harms, such as traffic accidents from hauling waste, could take credit for contamination they avoided while dismantling, and would get an explicit option of a cost-benefit analysis for restricted release.
Achieved whena final rule is published and takes effect.
Claimed by
US Nuclear Regulatory Commission, July 2026
Open
01
Test an AI site history
An AI agent that reads a closed plant's public records, such as event reports, yearly effluent and groundwater reports and inspection reports, and lists every known spill, leak and contaminated area with its date and place. This list is the first step of a MARSSIM survey, called the historical site assessment. Score the agent against the historical site assessments that owners filed with their license termination plans.
The briefCredit · unclaimed02
Robot survey against people
A small wheeled robot that scans floors for beta and gamma radiation along a planned path, logs every reading with its position, and is tested side by side with trained human surveyors on the same floors.
The briefCredit · unclaimed03
Final survey results as data
A public table of the final status survey results for each released US reactor site: every survey unit, its class, area and number of measurements, its release limit expressed as a concentration (the derived concentration guideline level, DCGL), and the highest and average readings. Then report how close released sites came to the limit.
The briefCredit · unclaimed
Open 01 · the brief
Test an AI site history
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
An AI agent that reads a closed plant's public records, such as event reports, yearly effluent and groundwater reports and inspection reports, and lists every known spill, leak and contaminated area with its date and place. This list is the first step of a MARSSIM survey, called the historical site assessment. Score the agent against the historical site assessments that owners filed with their license termination plans.
Why it is still open
Assystem says its AI system turned 20,913 archive documents from a French reactor into a searchable inventory with 23,134 extracted tables, but it published no accuracy test. A Korean project with Yonsei University and KEPCO Engineering & Construction, run from 2021 to 2023, built a language model that reads reports and classifies the places where past incidents happened, for site characterization; its public summary gives no score against an owner's filed assessment. The NRC warned in 2002 that old records should not be the only source for a historical site assessment, so any tool has to show what it misses. No published test of an AI model against filed assessments was found.
Built with what exists
NRC ADAMS public documents; OCR for scanned pages, such as Tesseract; a long-context AI model that cites the page behind each finding (see the Note "Findings that cite notes"); MARSSIM Revision 2 as the checklist.
First step
Pull Zion's license termination plan from ADAMS and list the events in its historical site assessment by hand, as the answer key.
Done looks like
On five released US reactor sites, the agent finds at least 90% of the events listed in each filed assessment; a person checks and counts every extra event it reports; the event lists, scores and prompts are published.
Open 02 · the brief
Robot survey against people
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A small wheeled robot that scans floors for beta and gamma radiation along a planned path, logs every reading with its position, and is tested side by side with trained human surveyors on the same floors.
Why it is still open
The University of Manchester's CARMA II robot surveys floors for alpha, beta and gamma radiation and was tried at Sellafield, but its 2023 paper reports no detection limits and no measured comparison with human surveyors or with MARSSIM, and its avoidance tests used simulated sources. Los Alamos National Laboratory has released open code for an autonomous robot that surveys large floor areas for alpha radiation, and Pryor and colleagues described a team of survey robots for working nuclear facilities in 2024, with no measured comparison in their summary. No scored test of a robot against human surveyors was found.
Built with what exists
A Clearpath Jackal or similar rover; a handheld beta and gamma probe of the kind surveyors already use; ROS and TU Darmstadt's MIT-licensed hector_radiation_mapping package on GitHub (tu-darmstadt-ros-pkg); a robot that maps an indoor space and drives itself to saved spots (see the Note "A camera on patrol"); test patches of potassium chloride salt substitute, which is slightly radioactive from natural potassium-40, so no licensed material is needed.
First step
Mount the probe on a rover and record count rates over a 1 kg bag of potassium chloride at three heights and three speeds.
Done looks like
On a test floor with 20 patches hidden by someone else, 20 robot runs and 20 human runs, with a published tally of patches found, false alarms and minutes per 100 square meters.
Open 03 · the brief
Final survey results as data
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public table of the final status survey results for each released US reactor site: every survey unit, its class, area and number of measurements, its release limit expressed as a concentration (the derived concentration guideline level, DCGL), and the highest and average readings. Then report how close released sites came to the limit.
Why it is still open
The NRC has published lessons from reviewing license termination plans in words, not numbers, and no compiled table of survey results across sites was found. The results sit in each site's reports in the NRC's ADAMS library.
Built with what exists
NRC ADAMS; PDF table tools and OCR; an AI model that copies table rows and records the page (see the Note "The jobs agents repeat"); a second person to check.
First step
Download the final status survey reports for Zion, whose land the NRC released in November 2023, and transcribe one survey area by hand to set the format.
Done looks like
Survey-unit tables for at least five released reactor sites, each row linked to its source page; a 100-row recheck with at least 98% agreement; a published summary of how many units had a highest reading above half the limit.