BRENNEN

Industries / Energy, water and waste / Electric transmission and distribution / Microgrids

Remote and island sites

Remote and island sites are places with no main grid to fall back on, where a local grid has to supply every hour of the year, usually starting from diesel generators.

7

Milestones achieved, from 1997 to 2021.

2

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1997

    Wind joins an Arctic town

    Kotzebue, Alaska, a town of about 3,300 that burned 1 to 1.5 million gallons of diesel a year for power, installed its first three 50-kilowatt wind turbines in 1997, and over the next decade grew to 925 kilowatts of wind. Unsteady wind and turbine faults caused short outages, so a zinc-bromide flow battery was added in 2010; it did not work, and a lithium-ion battery replaced it in 2015.

    LessonNREL's review says the failed battery had not been tested for the job or shipped properly, so remote storage needs proof before it goes north.

    osti.gov

    Credit

    Kotzebue Electric Association; NREL

  2. 2008

    An island wires itself

    On 1 February 2008 the Isle of Eigg in Scotland, whose homes had each run their own diesel generator, switched on an island-wide grid fed by hydro, wind and solar power, with batteries and two 64-kilowatt diesel generators as backup. Each home may draw at most 5 kilowatts at once and each business 10 kilowatts, which lets a small system serve everyone. The community puts the renewable share at about 95% since 2008; the Rocky Mountain Institute's 2015 casebook gives 87%.

    rmi.org

    Credit

    Isle of Eigg Heritage Trust (Eigg Electric)

  3. 2014

    El Hierro's wind and water

    In June 2014 El Hierro in Spain's Canary Islands opened Gorona del Viento, a plant that pairs 11.5 megawatts of wind turbines with pumped hydro storage: spare wind power pumps water uphill, and the water runs back through turbines when the wind drops. In 2025 it covered 1,049 hours, about 12% of the year, with renewable power alone and supplied 44% of the island's electricity; the island's diesel plant supplied the other 56%.

    Lessonthe Rocky Mountain Institute's 2015 casebook said El Hierro had "recently completed a shift to generating 100 percent" of its electricity from renewables, so an island's headline share needs a full year of meter readings behind it.

    goronadelviento.esgoronadelviento.esrmi.org

    Credit

    Gorona del Viento El Hierro S.A. (El Hierro island council, Endesa, Canary Islands government); IDAE, Spain's energy agency

  4. 2014

    Kodiak nears all renewable

    Kodiak Electric Association in Alaska added wind turbines to its Terror Lake hydropower plant in 2009 and 2012, batteries in 2012 and two 1-megawatt flywheels, spinning wheels that store energy for seconds, in 2014 to steady the grid and run an electric crane at the port. NREL reports that the island now gets 99% of its power from hydro and wind and runs its diesel generators about once a quarter to check they still start.

    Lessonthe upgrades were done in stages over 16 years, and NREL notes that earlier Kodiak projects failed for lack of engineering and project management.

    osti.gov

    Credit

    Kodiak Electric Association; Alaska's Renewable Energy Fund

  5. 2016

    Solar replaces a supply boat

    In November 2016 Ta'u in American Samoa, an island of 200 to 600 people whose diesel came by a boat that could be months late, switched off its diesel plant and ran on 1.41 megawatts of solar panels and 60 Tesla Powerpack batteries, enough to keep the island powered for up to three days without sun. National Geographic reported the $8 million cost, paid by the US Department of the Interior and the American Samoa Power Authority, and an expected saving of about 110,000 gallons of diesel a year.

    nationalgeographic.com

    Credit

    American Samoa Power Authority; SolarCity (Tesla)

  6. 2018

    When the main grid arrives

    A World Bank study of Cambodia, Sri Lanka and Indonesia found that most village mini-grids were abandoned once the national grid reached them: in Indonesia 9 connected to the grid and 150 were abandoned, and in Sri Lanka 3 connected and more than 100 were abandoned. Privately owned diesel mini-grids in Cambodia did better, many becoming local distributors that buy grid power and resell it.

    Lessonrules that say in advance what happens to a mini-grid when the grid arrives protect the investment; without them it is usually lost.

    openknowledge.worldbank.org

    Credit

    Bernard Tenenbaum, Chris Greacen and Dipti Vaghela (ESMAP, World Bank)

  7. 2021

    Wind powers a gold mine

    Gold Fields' Agnew mine in Western Australia, about 1,000 km from Perth, opened a microgrid of 18 megawatts of wind, 4 megawatts of solar and a 13-megawatt, 4-megawatt-hour battery, with 18 megawatts of gas and diesel engines as backup. ARENA calls it the first Australian mine to install wind turbines. The power company EDL built, owns and runs it and sells power to the mine; Gold Fields reports an expected 54% of annual energy from renewables and more than 85% in good weather.

    arena.gov.auarena.gov.au

    Credit

    Gold Fields; EDL; ARENA ($13.5 million)

Watch for

  1. Fifty million new connections

    The World Bank and the African Development Bank said on 16 June 2026 that their Mission 300 campaign had connected more than 50 million people to electricity in 40 African countries, on the way to 300 million by 2030, through the grid, mini-grids and solar home systems. The policy institute ODI checked the claim and found that much of it came from programmes started years earlier, and that Nigeria's mini-grid programme, DARES, had commissioned 67 isolated mini-grids and no grid-connected ones by June 2026.

    Achieved whena country-by-country, project-level count is published that outsiders can recompute, and it supports the figure.

    worldbank.orgodi.org

    Claimed by

    World Bank Group and African Development Bank Group, June 2026

  2. Island resorts cut diesel

    Three resorts in Fiji's Yasawa islands installed 760 kilowatts of rooftop solar and 1.6 megawatt-hours of batteries between September 2025 and June 2026. The installer says energy costs fell 35% in the first six months and expects a 50% cut in diesel costs for 2026.

    Achieved whena full year of fuel purchase records is published, or checked by someone outside the companies, and shows the cut.

    pv-magazine.com

    Claimed by

    Future Energy (New Zealand) and SolaX Power Australia, June 2026

Open

  1. 01

    Revisit the 2015 island casebook

    A ten-year follow-up of the island and remote grids in the Rocky Mountain Institute's 2015 casebook (Bonaire, Kodiak, El Hierro, the Falkland Islands, King Island, Marble Bar and Nullagine, Coral Bay, Eigg, Necker Island and Mawson Station in Antarctica), plus Ta'u. For each site and year: renewable share, diesel burned and major outages, set beside what was promised when it opened.

    The brief
    Credit · unclaimed
  2. 02

    List Nigeria's mini-grid sites

    A public list of the mini-grids counted by Nigeria's World Bank-funded programmes: site name, place, capacity, date commissioned and the document each comes from, with a check on satellite or aerial images that solar panels are present at each site.

    The brief
    Credit · unclaimed

Open 01 · the brief

Revisit the 2015 island casebook

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A ten-year follow-up of the island and remote grids in the Rocky Mountain Institute's 2015 casebook (Bonaire, Kodiak, El Hierro, the Falkland Islands, King Island, Marble Bar and Nullagine, Coral Bay, Eigg, Necker Island and Mawson Station in Antarctica), plus Ta'u. For each site and year: renewable share, diesel burned and major outages, set beside what was promised when it opened.

Why it is still open

The casebook gave one snapshot per site in 2015. Public reporting on Ta'u stops near its opening in 2016. Gorona del Viento publishes yearly figures for El Hierro, which show 44% renewable in 2025. An IEA PVPS report of September 2026 by P. Blechinger, H. Hecker, A. Linke and M. Müller compared 11 islands, most with renewable shares of 80% to 100%, but it draws on papers, case studies and five interviews to sort 111 factors behind success, and its summary gives no measured share year by year against what each island was promised.

rmi.orgnationalgeographic.comgoronadelviento.esiea-pvps.orgpv-magazine.com

Built with what exists

Utility annual reports and regulator filings; Gorona del Viento's quarterly spreadsheets; NREL's 2023 Arctic case study; Python and a spreadsheet; an extraction model that cites pages (Note: "The jobs agents repeat").

  1. First step

    Turn Gorona del Viento's 2018 to 2025 annual reports into a yearly table of renewable share and fully renewable hours.

  2. Done looks like

    11 sites with at least five years of figures each, every figure linked; a short note per site on the gap between the promised and the measured renewable share.

Open 02 · the brief

List Nigeria's mini-grid sites

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public list of the mini-grids counted by Nigeria's World Bank-funded programmes: site name, place, capacity, date commissioned and the document each comes from, with a check on satellite or aerial images that solar panels are present at each site.

Why it is still open

The World Bank's March 2026 status report for DARES gives only totals, 64 isolated mini-grids commissioned against a target of 1,170. Nigeria's Rural Electrification Agency said in December 2025 that it had deployed more than 200 mini-grids that year under an earlier project. ODI wrote in June 2026 that the Mission 300 figures cannot be recomputed from published records. The World Bank's DRE Atlas (June 2025) maps Nigerian settlements that could host a mini-grid and gives each one's distance to the nearest existing mini-grid, but warns that "public mini-grid data can be outdated / inaccurate"; no public list of commissioned sites was found.

documents1.worldbank.orgnairametrics.comodi.orggep-source-archive.s3.us-east-1.amazonaws.com

Built with what exists

World Bank status reports; Rural Electrification Agency press releases; free high-resolution imagery in Google Earth and Esri's World Imagery Wayback; Python; an extraction model (Note: "The jobs agents repeat").

  1. First step

    Gather the World Bank status reports for DARES and the Nigeria Electrification Project and the agency's 2025 and 2026 press releases into one table.

  2. Done looks like

    Every mini-grid the agency has announced as commissioned, listed with coordinates and a source; 50 chosen at random checked on imagery, with a published tally of panels found and not found.