Industries / Energy, water and waste / Pipelines and midstream / LNG
Boil-off and methane leaks
LNG boils slowly in every tank and ship, and this work decides what happens to that gas and measures how much methane, the main part of natural gas and a strong greenhouse gas, escapes along the way.
7
Milestones achieved, from 2008 to 2025.
1
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
2008
Boil-off made liquid again
Some cargo always boils off at sea; Lloyd's Register Foundation's heritage center puts the loss at 2% to 6% of the cargo on a typical 20-day voyage. Ships whose engines can burn gas use that boil-off as fuel, as Gaz de France's dual-fuel carriers did from 2006. The Q-Flex and Q-Max carriers built for Qatari LNG ran slow-speed diesel engines on fuel oil instead, so each carried a reliquefaction plant that cools the boil-off back into liquid and returns it to the tanks. In November 2008 Hamworthy said it was supplying the plants for all 31 Q-Flex ships, each of 216,000 m³, and that 20 had passed their first trials with cold gas; that year Qatargas's shipping project manager credited onboard reliquefaction with savings in operation and lower emissions, Oil & Gas Journal reported.
wartsila.comogj.comheritage.lrfoundation.org.ukrivieramm.com
Credit
Hamworthy Gas Systems (Moss RS reliquefaction process); Samsung Heavy Industries, Daewoo Shipbuilding & Marine Engineering and Hyundai Heavy Industries (builders)
2022
A carrier's methane measured
Researchers sailed on the GasLog Galveston, a carrier built in 2021, from the US to Belgium and back, and measured methane from its exhaust stacks, vents and leaks. Vents and leaks made up less than 0.1% of the ship's greenhouse gas emissions. Methane slip, the unburned methane in engine exhaust, averaged 3.8% of the gas the engines burned, equal to 0.1% of the LNG delivered, and the generator engines running at low load were the main source. The authors call these the first primary measurements of an LNG carrier's methane; Enagás, Cheniere and the Collaboratory to Advance Methane Science, an industry research group, paid for the study.
Lessongenerator engines, usually left out of estimates, caused most of the methane.
Credit
Paul Balcombe and Dalia A. Heggo (Queen Mary University of London) and Matthew Harrison (SLR International), in Environmental Science & Technology
2023
Lasers measure whole plants
The UK's National Physical Laboratory scanned three liquefaction plants and two import terminals with differential absorption lidar, a laser method that maps gas across a site from outside it. Methane losses averaged 0.070% of throughput at the liquefaction plants and 0.018% at the import terminals. The sites are kept anonymous, and the authors warn that their short campaigns should not be turned into yearly totals.
Credit
Fabrizio Innocenti and colleagues, National Physical Laboratory, in work funded through the Oil and Gas Methane Science Studies hosted by the UN Environment Programme
2024
Slip nearly twice the default
The FUMES project measured methane in the exhaust plumes of ships that burn LNG as fuel, in Europe and Australia, using drones, helicopters and sensors on board. In 18 ships with the most common LNG engine, a low-pressure four-stroke dual-fuel engine, slip averaged 6.4% of the fuel; EU rules assume 3.1% and the International Maritime Organization (IMO) 3.5%. The project also measured methane released while LNG cargoes were unloaded.
Lessonthe default values written into rules can sit far below what ships emit.
Credit
International Council on Clean Transportation (ICCT), Explicit ApS and the Netherlands Organisation for Applied Scientific Research (TNO)
2024
Europe reaches back to suppliers
The EU Methane Regulation, signed on 13 June 2024, requires leak detection surveys at LNG plants in the EU every four to eight months, depending on the survey type, and reaches back to gas bought abroad. Importers had to report what they know of their suppliers' methane controls by 5 May 2025. From 1 January 2027 new contracts may cover only gas whose producers measure and report methane to an equivalent standard; from 5 August 2028 importers report the methane intensity of the production behind their supply, and from 2030 it must be below limits still to be set.
Credit
European Parliament and Council of the European Union, Regulation (EU) 2024/1787
2024
Two footprints, two answers
In October 2024 Robert W. Howarth of Cornell University estimated that, counted over 20 years, the greenhouse gas footprint of US LNG is 33% larger than that of coal, with methane from production, pipelines, liquefaction and tankers the largest part. The US Department of Energy, which had paused new export approvals, released its own study in December 2024; in May 2025 it concluded that more exports would have "no discernable impact" on global greenhouse gas emissions.
Lessonestimates of LNG's climate effect turn on how much methane is assumed lost, a number few measurements pin down.
Credit
Robert W. Howarth, in Energy Science & Engineering; US Department of Energy
2025
US terminals measured
Researchers measured Cheniere's liquefaction terminals at Sabine Pass in Louisiana and Corpus Christi in Texas from the air and the ground over 16 months. Methane losses were 0.007% to 0.045% of the methane in the LNG produced, and total greenhouse gas emissions closely matched what the plants report to the US Greenhouse Gas Reporting Program. Cheniere staff were co-authors, and Cheniere was among the funders.
Credit
Yuanrui Zhu, Arvind P. Ravikumar and co-authors (University of Texas at Austin, Colorado School of Mines and Cheniere Energy), in Environmental Science & Technology Letters
Watch for
Variable compression cuts slip
Hanwha Engine says it has built the first variable compression ratio engine for an LNG carrier, a WinGD-designed 5X72DF-2.2 dual-fuel engine that adjusts its compression while it runs, and that it cuts methane slip by 30% to 50% compared with existing technology. The engine is for one of QatarEnergy's carriers being built at Samsung Heavy Industries.
Achieved whenan outside party measures slip on a carrier in service with this engine and compares it with the same engine type without variable compression, as was done on board the GasLog Galveston in 2022.
Claimed by
Hanwha Engine, August 2025
Open
01
Link flaring to ship loading
A night-by-night record for each LNG export plant of when satellites saw a flare, set beside the days a carrier was loading at the plant's jetty, and a test of whether plants flare more while ships load. Loading a ship makes extra boil-off at the jetty, gas that a plant can recover or burn; a 2024 paper is devoted to managing it.
The briefCredit · unclaimed02
Check each plant's methane figure
A public table of every LNG export plant showing the methane loss its operator reports, as a share of the gas it handles, beside every independent measurement of the same plant: aerial and laser surveys in published papers and satellite plume detections, each with its date and a link.
The briefCredit · unclaimed
Open 01 · the brief
Link flaring to ship loading
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A night-by-night record for each LNG export plant of when satellites saw a flare, set beside the days a carrier was loading at the plant's jetty, and a test of whether plants flare more while ships load. Loading a ship makes extra boil-off at the jetty, gas that a plant can recover or burn; a 2024 paper is devoted to managing it.
Why it is still open
The 2025 study of flaring at 48 export plants matched satellite flares to plants by distance and date but did not look at ship visits. A 2026 open dataset, LNG-T3, lists every carrier's loading and unloading events from 2020 to 2024, built from ship-tracking (AIS) signals and draught reports, but does not link them to flaring. One search found no study joining the two.
Built with what exists
VIIRS Nightfire flare detections from the Payne Institute at the Colorado School of Mines; the LNG-T3 dataset on Zenodo (doi 10.5281/zenodo.17273526); Python; an AI agent to write and rerun the data pipeline for each plant (see the Note "The jobs agents repeat").
First step
Download LNG-T3 and the Nightfire records for one plant, such as Sabine Pass, for 2023 and line up the dates.
Done looks like
For at least ten export plants over 2020 to 2024, a published table giving the share of nights with a flare when a carrier was at the berth and when none was, with a confidence interval for each plant, and the code so anyone can rerun it.
Open 02 · the brief
Check each plant's methane figure
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public table of every LNG export plant showing the methane loss its operator reports, as a share of the gas it handles, beside every independent measurement of the same plant: aerial and laser surveys in published papers and satellite plume detections, each with its date and a link.
Why it is still open
Independent measurements cover few plants. The National Physical Laboratory study keeps its five sites anonymous, and the University of Texas study covers two terminals of one company. SkyTruth's 2025 tally of satellite plumes at terminals warns that uneven satellite coverage means the counts do not rank plants. One search found no plant-by-plant comparison. From 5 August 2028 EU importers must report the methane intensity of the production behind their gas.
pmc.ncbi.nlm.nih.govpmc.ncbi.nlm.nih.govskytruth.orgeur-lex.europa.eu
Built with what exists
Operators' reports under the UN Environment Programme's OGMP 2.0 reporting framework and their sustainability reports; the US Greenhouse Gas Reporting Program; Carbon Mapper's free plume catalog and its API; Global Energy Monitor's gas infrastructure tracker for the list of plants; an AI model to pull figures from long reports, with a person checking each one (see the Note "Seven more flagged").
First step
List the operating export plants from Global Energy Monitor's tracker and find each operator's latest reported methane figure.
Done looks like
At least 25 operating export plants listed, every number linked to the page it came from; for every plant that has both kinds of number, the ratio of measured to reported; a second person checks 50 numbers and agrees on at least 48.