Grid control and balancing
Grid control is the work of control rooms that match the power going into the grid with the power being used, second by second, keep frequency and voltage within safe limits, stop a local fault from spreading, and restart the system after a blackout.
7
Milestones achieved, from 1933 to 2025.
2
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
1933
Britain finishes a national grid
The Electricity (Supply) Act 1926 created the Central Electricity Board to link selected power stations through one high-voltage network. The last tower went up in September 1933, completing about 4,000 miles of line at 132 kV on 26,265 towers, and by 1 April 1934 power was traded over the grid in six areas, according to Grace's Guide, a British industrial-history archive.
Credit
Central Electricity Board
1965
Northeast blackout creates NERC
On 9 November 1965 about 30 million people in the northeastern US and southeastern Ontario lost power, some for as long as 13 hours, by NERC's account. In 1968 the industry formed the National Electric Reliability Council (NERC) to set shared rules for planning and running the connected grid, though for decades it could not enforce them.
Lessongrids that are tied together need shared operating rules, because a failure at one utility can black out its neighbors.
Credit
North American electric utilities; the Federal Power Commission
1995
Satellite-timed grid measurements
A phasor measurement unit (PMU) measures the size and timing of the voltage and current waves on a line and stamps each reading with time from GPS satellites, so readings from substations hundreds of miles apart can be lined up. Arun Phadke's group at Virginia Tech built the first complete GPS-synchronized units around 1990, and IEEE issued the first standard for them, IEEE 1344, in 1995, according to Phadke and Bi (2018).
Credit
Arun Phadke, James Thorp, Virgilio Centeno; IEEE
2003
Blackout makes rules mandatory
On 14 August 2003 a blackout cut power to an estimated 50 million people and 61,800 MW of load in eight US states and Ontario. The US-Canada task force found that FirstEnergy in Ohio did not see its system failing after its alarm software failed, that trees under its lines had tripped three 345 kV lines, and that regional bodies gave no effective help. Its top recommendation, mandatory reliability rules, came with the US Energy Policy Act of 2005, and NERC's standards became enforceable on 18 June 2007.
Lessonoperators need tools that show them the state of the grid, and a backup for when those tools fail.
Credit
U.S.-Canada Power System Outage Task Force
2015
Hackers switch off substations
On 23 December 2015 attackers broke into three regional power distribution companies in Ukraine, used the companies' own remote-control software to open circuit breakers, and cut power to about 225,000 customers, by the US Cybersecurity and Infrastructure Security Agency's count. They also wiped computers and disabled devices to slow recovery.
Lessonthe remote access that lets staff run substations from afar also lets intruders do it.
Credit
US Cybersecurity and Infrastructure Security Agency (investigation)
2017
A battery steadies frequency
Frequency is the rate at which alternating current changes direction, and it falls when demand outruns supply. The 100 MW Hornsdale Power Reserve in South Australia, a lithium-ion battery, began selling frequency correction in late 2017. The engineering firm Aurecon found it took nearly 10% of the national market for raising frequency in early 2018, and models its response time at 100 milliseconds against 6 seconds for the fastest existing service.
Credit
Neoen (owner); Tesla (supplier); Government of South Australia
2025
Iberia blacks out on overvoltage
At 12:33 on 28 April 2025 the grids of mainland Spain and Portugal collapsed within seconds, which ENTSO-E's expert panel called the most severe blackout in Europe in more than 20 years. Voltage rose fast, plants tripped on overvoltage protection, and the panel found that voltage-control devices were switched by hand, that wind and solar plants did not respond to voltage swings, and that some protection was set below required limits. Power took about 12 hours to restore in Portugal and 16 in Spain.
Lessonvoltage control must be fast and automatic, and wind and solar plants must take part in it.
Credit
ENTSO-E expert panel led by Klaus Kaschnitz (APG) and Richard Balog (MAVIR), final report 20 March 2026
Watch for
AI autopilot for reserve power
Swissgrid, Switzerland's grid operator, says its Optimizer Autopilot decides how much control energy (reserve power held ready to correct imbalances) is needed and activates the cheapest offers fully automatically, and that it went live between January and May 2025. Swissgrid credits it "partly" for a 22% fall in secondary control energy activations in the first ten months of 2025, but publishes no performance figures.
Achieved whensomeone outside Swissgrid, such as the Swiss regulator ElCom, publishes a measured result.
Claimed by
Swissgrid, January and February 2026
AI helper for outage requests
The California ISO is piloting OATI's "Genie" AI assistant on requests to take equipment out for maintenance: it flags anything unusual, lists the affected lines and areas, and suggests next steps, while operators keep the decision. CAISO gave no figures on time saved.
Achieved whenCAISO or an outside reviewer publishes measured results from routine use.
Claimed by
California ISO, July 2025
Open
01
Test AI forecasts against operators
A public, running comparison of next-day electricity demand forecasts from open AI forecasting models with the forecast the grid operator itself published, scored on the same hours.
The briefCredit · unclaimed02
Check Swissgrid's balancing AI
An outside measurement of what Swissgrid's automated control-energy tool changed: how much reserve power was activated and what it cost, before and after it went live in 2025, with weather and market changes accounted for.
The briefCredit · unclaimed
Open 01 · the brief
Test AI forecasts against operators
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public, running comparison of next-day electricity demand forecasts from open AI forecasting models with the forecast the grid operator itself published, scored on the same hours.
Why it is still open
A February 2026 study tested four open forecasting models on Texas grid (ERCOT) demand against Prophet, SARIMA and a naive seasonal guess, not against ERCOT's own forecast, and its limits section does not mention one.
Built with what exists
ERCOT's public Seven-Day Load Forecast, posted hourly; the open-source gridstatus Python library, which fetches demand and forecasts from nine North American grid operators; forecasting models trained on many kinds of time series, such as Amazon's Chronos-2 (released October 2025, Apache-2.0 license) and Google's TimesFM 2.5; public weather forecasts.
First step
Collect one month of ERCOT's day-ahead forecasts and actual demand, and score a seasonal-naive baseline and Chronos-2 against them.
Done looks like
Twelve months of forecasts made each morning at the hour ERCOT publishes its own, scored by mean absolute percentage error by hour and season beside ERCOT's error, with code public and a second person reproducing the scores.
Open 02 · the brief
Check Swissgrid's balancing AI
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
An outside measurement of what Swissgrid's automated control-energy tool changed: how much reserve power was activated and what it cost, before and after it went live in 2025, with weather and market changes accounted for.
Why it is still open
Swissgrid gives no figures for the tool, and credits it only "partly" for the 22% fall in activations, without saying how it separated the tool's effect from other causes.
Built with what exists
Swissgrid's public 15-minute data on activated reserves, imbalance and prices, with yearly files back to 2009; public weather data; Python statistics libraries.
First step
Download the 2023 to 2025 quarter-hour activation data and plot monthly totals around January to May 2025.
Done looks like
A published estimate, with a confidence range, of the change in activations and in cost per MWh that can be put down to the tool, with code that a second person reruns to the same result, sent to Swissgrid and ElCom.