Blade repair and recycling
Blade repair keeps blades working once they are up, mostly by fixing the front edge that rain wears away, and blade recycling decides what happens to a blade when it comes down.
5
Milestones achieved, from 2018 to 2022.
3
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
2018
Eroded edges at Anholt
In April 2018 Siemens Gamesa began taking down and repairing the blades of its 3.6 MW turbines at Ørsted's 111-turbine Anholt offshore wind farm in Denmark, opened in September 2013, because rain had eroded their leading edges (the front edge that meets the air first). Crews fitted a protective shell and a kit to improve the blade's aerodynamics, and the 175-turbine London Array was next. Ørsted said the work would have no significant effect on its finances, partly because of warranty claims.
Lessonat sea, edge wear showed up within five years of opening and could mean taking blades down.
Credit
Ørsted; Siemens Gamesa
2018
A common rain test
In February 2018 DNV published a recommended practice, DNVGL-RP-0171, "Testing of rotor blade erosion protection systems." It names the test settings to control so that results from different rain erosion rigs can be compared. In the widely used "helicopter" setup, coated samples on a spinning rotor pass through a cloud of water drops at 126 to 160 m per second. Siemens Gamesa's 2021 white paper says there is no formal standard for such tests, but that this setup is "widely known and recognized" and is the one it uses.
Credit
DNV (then DNV GL)
2021
Blades fed to cement kilns
GE Renewable Energy signed a contract with Veolia to recycle blades from its US onshore turbines by co-processing: the blades are shredded at a Veolia plant in Missouri and fed to cement kilns, where 65% of the blade replaces raw materials such as sand and clay and 28% burns as fuel, by the companies' figures. Veolia said it had processed more than 100 blades, and Waste Management World called the contract the first of its kind in the US wind industry.
Credit
GE Renewable Energy; Veolia North America
2021
Industry asks for landfill ban
On 16 June 2021 WindEurope, the European wind trade body, asked the European Commission to ban landfilling of wind turbine blades across Europe from 2025, and committed the European wind industry to re-use, recycle or recover all decommissioned blades. It noted that Austria, Finland, Germany and the Netherlands already banned landfilling them, and expected about 25,000 tonnes of blades a year to reach end of life by 2025.
Credit
WindEurope; the Spanish Wind Energy Association (AEE)
2022
Recyclable blades at sea
On 1 August 2022 RWE reported that the first turbine at its Kaskasi offshore wind farm in the German North Sea was generating power with Siemens Gamesa's 81 m RecyclableBlades. These are made with a resin whose chemical structure lets it be separated from the fibers and other parts after the blade is retired. RWE called them "the world's first installed recyclable wind turbine blades."
Lessonwhether the resin separates as designed will be tested only when the blades come down.
Credit
Siemens Gamesa; RWE
Watch for
Robots patch blades in place
The ROMAIN project says a robot built by Aerones carried uncured patches, cut to fit the damage, up to a blade on a turbine, where a TECNALIA applicator shaped them to the blade, pressed them under vacuum and cured them with controlled heat. It was tested at EDP's La Cabaña wind farm in Albacete, Spain, and EDP staff checked the patches six months later and found them working. No count of repairs or time savings was given.
Achieved whena wind farm owner outside the project publishes the number, time and condition after a year of robot repairs set against manual ones.
Claimed by
TECNALIA for the ROMAIN consortium coordinated by EDP Renewables, May 2026
ENGIE tests a repair robot
ENGIE's research arm says it is testing Aerones' robots, which inspect and repair blade surfaces on the turbine, and that field trials showed they "can significantly reduce repair time," without giving figures. It says the method does not suit severe structural damage.
Achieved whenENGIE or another owner publishes measured repair times and repair quality from routine use.
Claimed by
ENGIE Research & Innovation, April 2026
Spain's blade recycling plant
Iberdrola España and FCC Ámbito opened EnergyLOOP in Cortes, Navarre, in June 2025, a plant of nearly 10 million euros designed to process up to 10,000 tonnes of waste a year and recover glass fibers and resins from blades for reuse in other industries.
Achieved whenthe tonnes actually processed in a year, and the share sold as material rather than burned or landfilled, are published and confirmed by a regulator or auditor.
Claimed by
Iberdrola and FCC, June 2025
Open
01
A ledger of blade recycling
A public table of every plant that takes wind turbine blades, worldwide, giving its method, its claimed capacity and the tonnes it actually processed each year, taken from company reports, permits, public waste returns and news, with every figure linked to its source and a note where no output is public.
The briefCredit · unclaimed02
Robot-laid edge protection tape
A robot arm that applies leading-edge protection tape, a tough polyurethane film stuck to the blade's front edge, to a section of a scrapped blade on the ground, trained from a few demonstrations by a technician and scored against that technician.
The briefCredit · unclaimed
Open 01 · the brief
A ledger of blade recycling
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public table of every plant that takes wind turbine blades, worldwide, giving its method, its claimed capacity and the tonnes it actually processed each year, taken from company reports, permits, public waste returns and news, with every figure linked to its source and a note where no output is public.
Why it is still open
IEA Wind's blade recycling task wrote in its 2025 report that "large scale solutions remain scarce" and that there is a "lack of reliable methods to assess future waste volumes." It is building a knowledge-hub database and a blade material passport, and neither is described as tracking what plants actually process. New plants announce what they are designed for, such as EnergyLOOP's 10,000 tonnes a year, not what they process. A search found waste forecasts (WindEurope, and a 2023 database of 104 turbine models used to predict China's blade waste) but no record of actual tonnes processed.
Built with what exists
Company and sustainability reports, permit registers and waste returns where they are public, trade press; a language-model agent that drafts each row and cites the sentence it came from (see the Note "Findings that cite notes"); two people who check every figure.
First step
List the plants named by WindEurope, IEA Wind and the trade press since 2021, and mark which of them publish any tonnage.
Done looks like
At least 50 plants on at least three continents, each with its method, capacity and either one year of reported throughput or a sourced statement that none is public, published under an open license and updated once a year.
Open 02 · the brief
Robot-laid edge protection tape
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A robot arm that applies leading-edge protection tape, a tough polyurethane film stuck to the blade's front edge, to a section of a scrapped blade on the ground, trained from a few demonstrations by a technician and scored against that technician.
Why it is still open
The repair robot with the longest published record applies liquid protection. Rope Robotics says its BR-8 robot sands, cleans and spreads liquid edge protection and had repaired over 150 blades by February 2023, and the ROMAIN project describes the manual alternative as technicians hanging from ropes applying liquid resins. A US patent application published in April 2026 (US 2026/0110287) claims a robotic device that dispenses, glues, presses and cures a pre-formed edge protector, but no product or test of it was found.
Built with what exists
A 3 m section of a scrapped blade from a recycler or repair shop; a collaborative robot arm with a roller tool; a commercial leading-edge tape; cameras; a robot model that learns a task from a handful of demonstrations (see the Note "Five demonstrations per task").
First step
Get a scrapped blade section and film a technician applying tape to it five times.
Done looks like
20 robot applications of at least 2 m of tape each on the curved leading edge, with trapped bubbles and wrinkles counted per meter, alignment measured and peel strength tested on matching panels, against 20 applications by a trained technician, filmed and published.