Drill and blast

Drill and blast drives a tunnel one round at a time: a rig called a jumbo drills a pattern of holes into the rock face, crews charge the holes with explosive and fire them in a set order, and the broken rock, called muck, is loaded out before the next round.

5

Milestones achieved, from 1876 to 2025.

1

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1876

    Hoosac sets the modern cycle

    The Hoosac Tunnel runs 4.75 miles (7.6 km) through the Hoosac Mountain in Massachusetts on a rail route to Boston. By 1868 only a third of it had been dug, and the state handed the work to the Canadian engineers Walter and Francis Shanley. The American Society of Civil Engineers (ASCE) credits the job with four changes that mark the start of modern hard-rock tunneling: the center cut, in which angled holes near the middle of the face are fired first to open a V-shaped space that the surrounding rock breaks into; the newly invented Burleigh compressed-air drill; nitroglycerin, which ASCE calls ten times more powerful than the black powder used before, more than half a million pounds of it; and firing many charges at once from an electric battery. ASCE dates completion to 1876 and says nearly 200 lives were lost over two decades of work.

    asce.org

    Credit

    Walter and Francis Shanley; the Commonwealth of Massachusetts

  2. 1950s

    One driller per drill

    Atlas Copco says its "Swedish method" of rock drilling let one man run a drilling machine where several had been needed before. The company says it introduced the method in Canada in 1948, took half of that market within a few years, and owed its global success in the 1950s to it. One person per drill is now the ordinary way hand-held rock drilling is done.

    atlascopcogroup.com

    Credit

    Atlas Copco

  3. 1973

    Oil power replaces air

    A hydraulic rock drill strikes the drill steel with a piston driven by oil pressure from an electric pump, instead of by compressed air piped from a compressor. Atlas Copco told the trade journal E&MJ that it introduced its first, the COP 1038, for its centenary in 1973, and a former Tamrock engineer recalled that the Finnish maker brought out its own in 1974. Makers surveyed by E&MJ said hydraulic drifters strike 3,500 to 6,000 blows a minute against about 1,700 for an old pneumatic one, and E&MJ notes that electric-driven pumps also cut noise and improve the air underground.

    e-mj.com

    Credit

    Atlas Copco; Tamrock

  4. 1988

    Pilot tunnel under the strait

    The Seikan Tunnel carries trains 53.85 km between Honshu and Hokkaido in Japan, 23.3 km of it under the Tsugaru Strait, and its deepest point is 240 m below sea level, by the figures in the journal of the Japan Society of Civil Engineers (JSCE). Railway Technology reports that it was driven by drilling and blasting, with about 2,900 t of explosives. Years before the main tunnel, crews began inclined shafts in 1964 and a small pilot tunnel in 1967, to explore the rock under the sea and develop ways of digging it; JR Hokkaido, which runs the line, describes the whole job as a long fight against water seeping in from the rock. The pilot tunnel broke through in January 1983, the main tunnel in March 1985, and trains began running in March 1988. The main tunnel swerves in two places where, after abnormal inflows of water, the heading was backfilled and dug around.

    Lessonunder the sea, a small pilot tunnel driven well ahead of the main one finds bad ground before the large heading reaches it.

    jsce.or.jpjrhokkaido.co.jprailway-technology.com

    Credit

    Japan's public railway builders, now the Japan Railway Construction, Transport and Technology Agency (JRTT)

  5. 2025

    Twice the planned explosive

    Since the early 1970s the Norwegian University of Science and Technology (NTNU) has published models that predict the drilling, charging, time and cost of drill-and-blast tunnels; the version in use dates from 2007. Researchers at the Norwegian Geotechnical Institute (NGI) compared 353 rounds fired in recent Norwegian tunnels with it and found that contractors used more charged holes and more explosive per cubic meter of rock than the model predicts. Three road tunnels averaged roughly twice the model's specific charge, the kilograms of explosive per cubic meter of solid rock. The authors say specific charge has in some road projects doubled since the early 2000s, whatever the contractor, and point to bulk emulsion, a pumped explosive that is easier to over-use than cartridges, and to contracts that reward speed and low cost.

    Lessona planning model stays true only while someone checks it against the rounds actually fired.

    airdrive.eventsair.com

    Credit

    S. Gjengedal and P. D. Jakobsen (NGI), with H. Nilsen, at Eurock 2025

Watch for

  1. Battery loaders at the face

    Statens vegvesen, Norway's road agency, reports that a 40 t battery-electric wheel loader made by XCMG has loaded blasted rock since May 2026 in the 8 km Rismålsheia tunnel on the E6 road, and that the contractor Skanska's machine foreman says it performs like a diesel loader, if not better. Its 700 kWh battery charges overnight and during two meal breaks and seldom ends a 12-hour shift below 30%. On the E134 Røldal–Seljestad project the agency requires mucking and haulage with zero exhaust on one side of the 12 km Røldal tunnel, where Metrostav tested a 25 t Liugong 870HE Max. Skanska says its own risk assessment finds batteries add little fire risk compared with diesel.

    Achieved whenloading rates, energy use and air quality at the face over a full tunnel drive are measured and published by the owner or an independent party.

    vegvesen.no

    Claimed by

    Skanska Norge and Metrostav Norge, as reported by Statens vegvesen, September 2026

Open

  1. 01

    Twenty dummy rounds by robot

    A bench test of a robot that loads a rock face the way a charging crew does, with no explosive or detonator at any stage. A camera finds each drilled hole, and the arm pushes an inert dummy cartridge, a wooden or 3D-printed cylinder, to the bottom of the hole. The face is a scaled concrete or timber panel drilled to a published drill plan, with the holes at the plan's angles.

    The brief
    Credit · unclaimed
  2. 02

    Drill plans as open data

    An open, sourced table of drill-and-blast rounds: tunnel, country, year, cross-section, rock type and class, hole diameter and length, number of holes by kind (cut, stoping, contour, floor), explosive type, specific charge and advance per round, each value taken from a published paper, thesis, design drawing or contract document.

    The brief
    Credit · unclaimed

Open 01 · the brief

Twenty dummy rounds by robot

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A bench test of a robot that loads a rock face the way a charging crew does, with no explosive or detonator at any stage. A camera finds each drilled hole, and the arm pushes an inert dummy cartridge, a wooden or 3D-printed cylinder, to the bottom of the hole. The face is a scaled concrete or timber panel drilled to a published drill plan, with the holes at the plan's angles.

Why it is still open

MLIT notes that blasting work is mostly done by hand right at the face. ABB says its Robot Charger finished tests in late 2023 at Boliden's Garpenberg zinc mine in Sweden, finding holes by camera and filling them with pumped explosive; Obayashi and Keio University loaded real explosive by remote control from outside a road tunnel in Nagano, Japan, and fired it in a trial reported in December 2024. Both are the developers' own accounts. In a 2024 laboratory study, J. Yi and colleagues at Jianghan University in Wuhan had a camera-guided arm pick up emulsion cartridges and push them into holes in a simulated tunnel face, and reported 87.1% success in grasping and 79.2% in filling, at about 120 s a cartridge; they scored single cartridges, not whole rounds. Japan's road ministry, MLIT, catalogued 21 technologies for automating or remote-controlling tunnel blasting in April 2025 and said development lags because the work is complex; its March 2026 material, citing labor ministry data, puts 36% of accidents in mountain tunneling in the charging of explosives. No public, repeatable tally of a robot loading every hole of a round was found.

e-mj.comnewswitch.jpmlit.go.jpmlit.go.jpmlit.go.jppmc.ncbi.nlm.nih.gov

Built with what exists

LeRobot, Hugging Face's open robot-learning software, and its low-cost SO-101 arm (see the Note "No download"); an open robot model fine-tuned on a few dozen demonstrations (see the Notes "Open robot model weights" and "Five demonstrations per task"); a depth camera such as an Intel RealSense; OpenCV to find the holes; a drilled concrete paver or timber panel; wooden dowels as dummies. Robot models that learn a task from a few demonstrations are what make a small-team attempt possible.

  1. First step

    Drill 20 holes in a concrete paver at the angles of the cut holes in a published drill plan, film a person loading dowels into them, and time each hole.

  2. Done looks like

    Twenty filmed rounds on one 40-hole panel, each hole scored found or missed and dummy seated to depth or not (checked with a marked rod), with the time per hole, published beside the same twenty rounds loaded by a person.

Open 02 · the brief

Drill plans as open data

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

An open, sourced table of drill-and-blast rounds: tunnel, country, year, cross-section, rock type and class, hole diameter and length, number of holes by kind (cut, stoping, contour, floor), explosive type, specific charge and advance per round, each value taken from a published paper, thesis, design drawing or contract document.

Why it is still open

The large compilations stay with their authors. Cardu and Seccatore's 2016 analysis drew on a database of blast schemes from around 250 tunnels, 163 of them described fully enough to use, assembled by Mancini and colleagues in 1998, and NGI's 2025 study added 353 rounds to NTNU's database. Neither is published as data. The only tunnel drill-plan drawings found on GitHub are AutoCAD files from one Korean project, with no table extracted.

iris.polito.itairdrive.eventsair.comgithub.com

Built with what exists

Open-access papers and theses; ezdxf or LibreDWG to read CAD drawings; a vision-language model to read drill plans from scanned figures, with a second model checking each value against its source for a person to confirm (see the Note "Seven more flagged"); Python with pandas; a Creative Commons license.

  1. First step

    Extract 10 rounds from five open-access papers and the Korean drawing files, and publish them with column definitions.

  2. Done looks like

    At least 150 rounds from at least 30 tunnels in five or more countries, each value linked to its source page, a second person confirming 20 rounds picked at random, and a published chart of specific charge against cross-section that tests NGI's finding of a doubling since the early 2000s.