Supply and lead times

Supply is the work of getting transformers and switchgear built and delivered: the factories, the core steel and copper they are made from, the spare units kept for emergencies, and the time between an order and a delivery.

6

Milestones achieved, from 2012 to 2025.

2

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 2012

    A spare built to travel

    A large power transformer weighs about 100 to 400 tons and is usually designed for one site, so replacing one takes many months. The Recovery Transformer (RecX), a 345 kV to 138 kV prototype rated 200 MVA per phase, weighs about 125 tons. In an exercise it was moved, installed and switched on in less than a week, and by the Department of Energy's 2014 account it had been in service on CenterPoint Energy's grid since March 2012. The department reports it was designed to stand in for more than 90% of transformers in its voltage class.

    energy.gov

    Credit

    US Department of Homeland Security Science and Technology Directorate, with EPRI, ABB and CenterPoint Energy

  2. 2014

    The US counts its dependence

    A Department of Energy study found that in 2010 six US factories met about 15% of US demand for power transformers rated 60 MVA or more, and that the country relied on imports even more for the highest voltages. Lead times ran 5 to 12 months from US makers and 6 to 16 months from foreign ones, and up to five years in extreme cases. A large unit cost $2 million to $7.5 million at the factory, and copper and electrical steel made up more than half of the cost.

    energy.gov

    Credit

    US Department of Energy, Office of Electricity Delivery and Energy Reliability

  3. 2024

    Small transformers run short

    Distribution transformers are the small units on poles and pads that lower the voltage for homes and shops. Researchers at the National Renewable Energy Laboratory reported that utilities faced lead times of up to two years, four times the pre-2022 norm, and prices up as much as five to six times in two years. They named post-pandemic demand, short-staffed factories, and shortages of grain-oriented electrical steel, aluminum and copper.

    osti.gov

    Credit

    Killian McKenna, Sherin Ann Abraham and Wenbo Wang (NREL, now the National Laboratory of the Rockies)

  4. 2024

    Waits pass two years

    The President's National Infrastructure Advisory Council (NIAC) reported that lead times had grown, by Wood Mackenzie's figures, from about 50 weeks in 2021 to 120 weeks on average in 2024, with 80 to 210 weeks for the largest units. Transformer prices were 80% higher than before the pandemic on a Federal Reserve Bank of St. Louis price index. NIAC put US production at about 20% of large power transformer demand, set a goal of 50% by 2029, and recommended a virtual reserve with the federal government as buyer of last resort, and shared standard designs.

    cisa.govpublicpower.org

    Credit

    NIAC Transformer Production Subcommittee

  5. 2025

    Lead times level off

    A survey by Wood Mackenzie with American Clean Power found that in the second quarter of 2025 lead times eased a little but stayed at two to three years: 128 weeks on average for power transformers, down 10 weeks, and 143 weeks for generator step-up units. Switchgear averaged 44 weeks. It counted nearly $1.8 billion announced since 2023 for transformer factories serving North America. A transformer broker quoted by POWER magazine disputes the picture, saying a standard substation transformer can be delivered in 12 to 14 months once drawings are approved.

    powermag.compowermag.com

    Credit

    Wood Mackenzie and American Clean Power (survey); POWER magazine (dissent)

  6. 2025

    China ships a record

    By China's customs figures, its transformer exports rose 36% in 2025 to CNY 64.6 billion (USD 8.9 billion), and the average price per unit rose about a third to CNY 205,000. Cai Yiqing of the China Electricity Council told the business news service Yicai that China makes about 60% of the world's transformers.

    yicaiglobal.com

    Credit

    China's General Administration of Customs (data); Yicai (report)

Watch for

  1. The largest US transformer plant

    Hitachi Energy broke ground on 29 June 2026 on a $457 million expansion at South Boston, Virginia, which it calls the nation's largest facility for making large power transformers, with about 825 jobs.

    Achieved whenthe plant ships transformers and someone outside the company reports its yearly output.

    hitachienergy.com

    Claimed by

    Hitachi Energy, June 2026

  2. Fewer transformer designs

    US utilities buy distribution transformers in tens of thousands of distinct designs: DOE gave "at least 79,421" types in November 2024 and "almost 40,000" configurations in March 2026. A DOE working group of utilities and manufacturers published a common configuration matrix, says the approach could cut the number of types by up to 40%, and has a smaller group of volunteer utilities applying it to specific transformer requirements.

    Achieved whenutilities that buy to the matrix report shorter lead times or more units per design, checked by someone outside DOE and the working group.

    energy.govenergy.gov

    Claimed by

    US Department of Energy, Office of Electricity, March 2026

Open

  1. 01

    Test the common designs

    A public comparison of real distribution transformer specifications with DOE's common configuration matrix. For each utility specification posted with a public bid, code every attribute on the matrix's list, then report which designs already fit a common configuration and which features push the rest out.

    The brief
    Credit · unclaimed
  2. 02

    A public GOES mill map

    An open table of every mill that makes grain-oriented electrical steel (GOES), the steel used for transformer cores, with owner, country, capacity and output in tonnes per year from 2020, the grades made, and a source for every number, set beside trade data for the same steel.

    The brief
    Credit · unclaimed

Open 01 · the brief

Test the common designs

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public comparison of real distribution transformer specifications with DOE's common configuration matrix. For each utility specification posted with a public bid, code every attribute on the matrix's list, then report which designs already fit a common configuration and which features push the rest out.

Why it is still open

DOE has put the matrix and its spreadsheets online and says a volunteer group of utilities is only now trying it on specific orders; no measurement of how many existing specifications fit it has been published.

energy.govopenenergyhub.ornl.gov

Built with what exists

The attribute, configuration and interchangeability spreadsheets on Oak Ridge National Laboratory's Open Energy Hub; specifications that utilities and cooperatives post with public bids; a language model that fills in each attribute and cites the page it came from (see the Note "Findings that cite notes"); two engineers to review.

  1. First step

    Download the attribute and configuration spreadsheets and code five public specifications against them.

  2. Done looks like

    Specifications from at least 30 utilities coded against every attribute, with a second checker agreeing on at least 90% of fields, and the share of designs that fit a common configuration published along with the five attributes that most often push a design out.

Open 02 · the brief

A public GOES mill map

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

An open table of every mill that makes grain-oriented electrical steel (GOES), the steel used for transformer cores, with owner, country, capacity and output in tonnes per year from 2020, the grades made, and a source for every number, set beside trade data for the same steel.

Why it is still open

Published figures for the largest producer disagree by a factor of four. Fastmarkets, citing the China Society of Metals, gives China's 2023 GOES output as 2.65 million tonnes, while a Fastmarkets article five months later quotes an analyst giving 620,000 tonnes, or 56% of world output. A search for a producer-by-producer list found only paid market reports.

fastmarkets.comfastmarkets.com

Built with what exists

Steelmakers' annual reports and press releases; US International Trade Commission investigation reports on GOES; UN Comtrade trade data for HS codes 7225.11 and 7226.11 (grain-oriented silicon electrical steel); a language model that extracts figures and cites the page (see the Note "Findings that cite notes").

  1. First step

    List the mills named in the 2013 USITC report on GOES imports and in the five largest producers' 2025 annual reports.

  2. Done looks like

    Every GOES mill named in at least two sources, with capacity for 2020 to 2025 and a source for each figure, the world total compared with Comtrade trade flows, and disagreements listed side by side rather than averaged, checked by a second person.