Block assembly

Yards join panels and parts into large three-dimensional sections called blocks, fit pipes and equipment into them, and then lift the blocks into place and weld them together into a hull, on a slipway, in a dry dock or on land.

7

Milestones achieved, from 1942 to 2024.

1

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1942

    A ship in five days

    US emergency yards built Liberty ships from sections welded in advance; prefabricated parts came by rail from across the country. At Kaiser's Permanente Metals No. 2 Yard in Richmond, California, the Robert E. Peary was launched 4 days, 15 hours and 30 minutes after her keel was laid in November 1942, by Project Liberty Ship's account. An average Liberty took 592,000 hours of labor.

    Lessonthe record was a planned showpiece, and the real gain was steady series building from sections made off the ship.

    ssjohnwbrown.orgusmm.ianewatts.org

    Credit

    Henry J. Kaiser's Permanente Metals Corporation

  2. 1956

    Block building moves to Japan

    In 1950 the American shipowner Daniel K. Ludwig leased Japan's former Kure naval dockyard, where his National Bulk Carriers built 42 ships, among them tankers of more than 100,000 dwt (deadweight tons, the weight a ship can carry). His agreement with the Japanese government required him to open the yard and its block and welding methods to competing Japanese shipbuilders, and historians Tomohei Chida and Peter Davies record that Japanese builders were given free access. Japan passed Britain as the world's largest shipbuilding nation by 1956. When the lease ended, Ishikawajima-Harima Heavy Industries (IHI) took over the yard.

    imarest.orgrbtus.com

    Credit

    National Bulk Carriers (Daniel K. Ludwig); Japanese shipbuilders, IHI among them

  3. 1974

    Yard and ships built together

    Chung Ju-yung of Hyundai broke ground for a shipyard on a beach at Ulsan, South Korea, in March 1972, after winning an order from Greek owners for two very large crude carriers. Hyundai built the yard and the two 260,000 dwt tankers at the same time and named both ships on the yard's completion in June 1974, by its own account. It had a technical agreement with A&P Appledore and Scott Lithgow of the UK, and in 1972 sent Korean staff to Scott Lithgow's Scottish yards to learn the work. Historians Tenold, Kang, Kim and Murphy describe Hyundai as the world's leading shipbuilder by the late 1980s.

    Lessonequipment and licenses could be bought, but the know-how of running a yard traveled with people.

    hd-hhi.comcambridge.org

    Credit

    Chung Ju-yung and Hyundai Heavy Industries; Scott Lithgow; A&P Appledore

  4. 1995

    The tallest tow

    Offshore platforms are assembled in sheltered water and towed to the field. Norwegian Contractors began building the concrete base of the Troll A gas platform at Hinnavågen, Stavanger, in summer 1991, and Aker Stord built its deck; both went to Vats on the Yrkesfjord, where the base was finished and the deck joined to it. On 10 May 1995 eight tugs began towing the 472 m structure at 1 to 2 knots, and on 17 May it was lowered to the seabed in 303 m of water. The Norwegian Petroleum Museum's history site for Equinor says the platform "is renowned for being the tallest structure ever moved by humans."

    equinor.industriminne.no

    Credit

    Norwegian Contractors and Aker Stord

  5. 2004

    Ships built on dry land

    Large ships are usually assembled in a dry dock, a basin that is flooded to float the finished hull out, and dock space limits how many hulls a yard can build at once. On 7 October 2004 Hyundai Heavy Industries launched a 105,000 dwt tanker for Novoship of Russia that had been assembled on land, using methods from its offshore platform work, and planned 16 more ships built this way by 2007. The Motorship called her "the first ship built on land."

    motorship.com

    Credit

    Hyundai Heavy Industries

  6. 2017

    Two cranes collide

    On 1 May 2017 a tower crane lifting a large load collided with a gantry crane at Samsung Heavy Industries' Geoje yard in South Korea. The accident hit a break area on the deck of a $500 million oil platform the yard was building for Total's Norwegian subsidiary; five people died at the scene, a sixth died later and more than 20 were injured. The head of the yard said it "arose due to signals not done properly between the crane operators and signalers," and police opened an investigation.

    Lessonwhere several cranes share the air over a yard, the signals between operators and signalers are part of the lift plan.

    maritime-executive.com

    Credit

    reported by The Maritime Executive

  7. 2024

    Building before design is done

    The US Navy began building the lead Constellation-class frigate in August 2022, while its design was still incomplete. In May 2024 the GAO reported that the 3D design was still unfinished more than a year after construction began, that the ship's weight had grown, and that delivery was forecast 36 months late. GAO recommended that detail design be finished for each grand module (a group of blocks built and outfitted as one unit) before work on that module starts. In November 2025 the Navy cut the program from 20 ships to two.

    Lessonblocks cut and welded to an unfinished design get rebuilt, so the drawings have to be done before the steel is.

    gao.gov

    Credit

    US Government Accountability Office (report GAO-24-106546)

Watch for

  1. Philly from two to twenty

    Hanwha, the Korean owner of Philly Shipyard in Philadelphia, announced a $5 billion plan in August 2025 to add two docks and three quays and possibly a new block assembly hall, and to raise the yard's output "from less than two vessels to up to 20" a year. It gave no target year.

    Achieved whenpublic delivery records show Philly Shipyard delivering 20 ships in one year.

    navalnews.com

    Claimed by

    Hanwha, August 2025

Open

  1. 01

    An open block model

    A public, complete block breakdown of one reference ship. Take a hull form that is already published for research, such as the KRISO Container Ship (KCS), lay out its internal structure to classification rules, divide it into construction blocks, and publish each block's weight, center of gravity, weld-joint lengths and the order in which blocks can be erected, with baseline schedules, so that block-scheduling methods can be compared on the same ship.

    The brief
    Credit · unclaimed
  2. 02

    Block turnover loads, measured

    An open program that takes a block's 3D model, its lifting lugs (the steel eyes welded on for crane hooks) and the positions of two crane hooks, and computes the load on every lug and wire as the block is turned over in the air. Check it against load cells on scale-model blocks turned over by two small hoists.

    The brief
    Credit · unclaimed

Open 01 · the brief

An open block model

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public, complete block breakdown of one reference ship. Take a hull form that is already published for research, such as the KRISO Container Ship (KCS), lay out its internal structure to classification rules, divide it into construction blocks, and publish each block's weight, center of gravity, weld-joint lengths and the order in which blocks can be erected, with baseline schedules, so that block-scheduling methods can be compared on the same ship.

Why it is still open

Most published block-scheduling methods are tested as case studies on one yard's private data, as in a 2025 study of plane-block manufacturing by Lin and colleagues. The first open sets have appeared, such as a block scheduling set from Shanghai Jiao Tong University (March 2026) with each block's size, weight and processing time, adapted from a real yard; it is tied to no published hull, so nobody can check its blocks against the ship's structure or redo the division.

doi.orgdata.mendeley.com

Built with what exists

Free CAD (FreeCAD) or Rhino; Google's open-source OR-Tools for scheduling; Python; an AI coding agent to write the export scripts.

  1. First step

    Download the KCS hull lines and draw the block division of one midship cargo hold.

  2. Done looks like

    At least 100 blocks published under an open license, with block weights that sum to within 5 percent of a standard lightship-weight estimate for the hull, three baseline schedules, and a public leaderboard that others have submitted to.

Open 02 · the brief

Block turnover loads, measured

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

An open program that takes a block's 3D model, its lifting lugs (the steel eyes welded on for crane hooks) and the positions of two crane hooks, and computes the load on every lug and wire as the block is turned over in the air. Check it against load cells on scale-model blocks turned over by two small hoists.

Why it is still open

Lifts with more than one crane are among the riskiest jobs in a yard, as the 2017 collision at Samsung Heavy Industries' Geoje yard showed. Heavy lifts with several cranes have been simulated in research, for example by Ku and Ha (Ocean Engineering, 2014), but searches in November 2026 found no open tool whose predicted lug loads had been checked against measured ones.

maritime-executive.comdoi.org

Built with what exists

Project Chrono (an open multibody physics library) or a short Python statics script; FreeCAD for the block models; two small electric hoists; load cells with HX711 amplifiers and a Raspberry Pi to log them; plywood or thin steel scale blocks.

  1. First step

    Build one 1:20 plywood block with four lugs, hang it from two hand hoists through load cells, and log the loads through one turnover.

  2. Done looks like

    20 filmed turnovers of three different scale blocks, with predicted and measured lug loads published side by side and every predicted peak within 10 percent of the measured peak.