Drilling is making a hole from the surface to the target rock, sometimes several kilometres down and then sideways, and keeping that hole open and on course.
7
Milestones achieved, from 1859 to 1982.
1
To watch for: announced, not yet confirmed outside.
1
Open deliverables. Nobody has shipped them.
In depth
The same ground is charted in more depth, as an industry of its own.
The road
AchievedWatch forOpen
Achieved
1859
Pipe to hold the hole
At Titusville, Edwin Drake and his driller William "Uncle Billy" Smith drove an iron "drive pipe" down through loose ground so the hole could not cave in, then drilled about three feet a day through rock to reach oil at 69.5 feet. Drake did not patent the idea.
Credit
Edwin Drake, William Smith
1901
Rotary drilling breaks through
At Spindletop near Beaumont, Texas, Anthony Lucas hired drillers Al and Curt Hamill, who used a rotary bit (one that turns to grind the rock instead of pounding it). On 10 January 1901, at 1,139 feet, the well blew out oil at an estimated 100,000 barrels a day and was capped nine days later, according to Lamar University's Spindletop museum.
Lessondeeper drilling found high-pressure oil that crews could not yet control.
Credit
Anthony Lucas, Al and Curt Hamill
1909
A bit that crushes rock
Howard Hughes Sr. was granted a patent on 10 August 1909 for a two-cone roller bit. The older fishtail bit scraped rock; the Hughes bit's rolling cones chipped and crushed it, which let rotary rigs drill through hard rock to deeper oil. ASME named it an engineering landmark in 2009.
Credit
Howard Hughes Sr., Walter Sharp (Sharp-Hughes Tool)
1976
Diamond cutters
General Electric first tested a polycrystalline diamond compact (PDC) bit, which shears rock with man-made diamond cutters, on an Exxon well on King Ranch, Texas, in July 1973. Three cutters failed at their brazed joints. GE launched its Stratapax cutters commercially in December 1976, and a Baker Hughes author estimated in 2015 that PDC bits drilled more than 90% of footage.
Lessonthe diamond worked first; fixing it to the bit was the harder problem.
Credit
General Electric
1978
Data from the hole's bottom
Measurement while drilling (MWD) sends readings from sensors near the bit to the surface while drilling goes on. Teleco introduced the first commercial MWD tool that sent direction data as pressure pulses in the drilling mud in 1978, at about 0.4 bits per second, according to a 2008 Oil & Gas Journal article by Baker Hughes engineers.
Credit
Teleco Oilfield Services
1980
Lake Peigneur drains
Early on 20 November 1980, a rig drilling for Texaco from a platform in Lake Peigneur, Louisiana, pierced the salt mine below. The lake drained into the mine and a crater pulled down barges and rigs. The mine owner said the rig's position had been triangulated wrongly, and Texaco was ultimately found at fault and ordered to pay $45 million, according to 64 Parishes.
Lessonknow exactly where the bit is and what lies under it.
Credit
Texaco and contractor Wilson Brothers
1982
Drilling sideways
After test wells at Lacq, France, from May 1980, Elf Aquitaine drilled Rospo Mare 6 off Italy in January 1982 with 370 m of horizontal hole. It cost 2.1 times a vertical well and produced 3,000 barrels a day, over 20 times a nearby vertical well, according to engineers Jacques Bosio and Michael Economides.
Credit
Elf Aquitaine
Watch for
Self-steering well offshore
ExxonMobil, working with Halliburton, Sekal and Noble, says it completed "the industry's first fully closed-loop automated geological well placement with complete rig automation" in the Stabroek Block off Guyana. Software read the rock, steered the bit and ran the rig, with no driller intervention on the controls during the reservoir section. No figures were released.
Achieved whendrilling rate and position-in-reservoir results are published and confirmed by someone outside the project, or the system is used routinely on later wells.
Claimed by
ExxonMobil and Halliburton, March 2026
Open
01
Label Volve's drilling problems
A public set of drilling problems (stuck pipe, lost drilling mud, kicks, equipment failures) taken from the Volve field's daily drilling reports and lined up with the time-stamped sensor data from the same wells.
The briefCredit · unclaimed
Open 01 · the brief
Label Volve's drilling problems
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public set of drilling problems (stuck pipe, lost drilling mud, kicks, equipment failures) taken from the Volve field's daily drilling reports and lined up with the time-stamped sensor data from the same wells.
Why it is still open
The public collection of 1,759 Volve daily drilling reports on Hugging Face was built for text summarization and has no event labels. A 2024 study built stuck-pipe time series from Volve sensor data but does not describe labels drawn from the reports.
Built with what exists
Volve data from Equinor; a language model that proposes each label and links it to the sentence that supports it (Note: "Findings that cite notes" covers an agent that links each finding to its evidence); two human checkers; Python.
First step
Register for the Volve data, take the daily reports for one well, and have a language model list every problem event with its time and source sentence.
Done looks like
At least 300 events labelled with start and end times, each linked to its report sentence, with agreement between two human checkers reported as Cohen's kappa, published within the Equinor Open Data Licence terms.