BRENNEN

Industries / Construction and property / Commercial and residential construction / Modular and prefab building

Finance and scheduling

Finance and scheduling is the work of paying for a factory and its output before the building exists, and of planning factory and site work so that they run at the same time.

6

Milestones achieved, from 1950 to 2026.

1

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1950

    Lustron's loans called in

    Lustron, set up in 1947 by the inventor Carl Strandlund, made houses of enameled steel in a former aircraft plant in Columbus, Ohio, and shipped each house on one flatbed trailer. Mass production began on 25 February 1949 and reached 26 houses a day that August, against a stated goal of 45,000 houses for 1949. Loans from the federal Reconstruction Finance Corporation (RFC) reached $37.5 million; the RFC declared the company in default in January 1950 and filed to foreclose on 22 February 1950, after about 2,680 houses had been built.

    LessonA plant financed for tens of thousands of houses a year made 1,250 in its first twelve months, and the debt came due before output caught up.

    encyclopediaofarkansas.net

    Credit

    Carl Strandlund; the RFC

  2. 2005

    Auditors weigh factory housing

    At the request of the Office of the Deputy Prime Minister and the Housing Corporation, the UK National Audit Office (NAO) examined modern methods of construction (MMC), the British term for factory-based building. Its report of 22 November 2005 found that MMC could cut time on site by up to half and build up to four times as many homes with the same on-site labor, but that its average costs were then higher than those of traditional building.

    nao.org.uk

    Credit

    National Audit Office

  3. 2021

    Philanthropy pays the factory

    833 Bryant Street, supportive housing in San Francisco for people leaving homelessness, was paid for at first with flexible money from Tipping Point Community, a philanthropy, and the San Francisco Housing Accelerator Fund, with Mercy Housing as developer; its units were built at Factory_OS in Vallejo while site work went on. The Terner Center for Housing Innovation at UC Berkeley found in February 2021 that it was on track to finish in 33 months at $382,917 a unit, 30 percent faster and 25 percent cheaper per unit than projects built in a similar way.

    LessonThe early money moved fast because its backers accepted the risk that some of it would not come back once public funding took over.

    ternercenter.berkeley.edu

    Credit

    Tipping Point Community; San Francisco Housing Accelerator Fund; Mercy Housing; Factory_OS

  4. 2021

    Katerra goes bankrupt

    Katerra, founded in 2015, set out to design, manufacture and build in one company, with its own factories. It filed for Chapter 11 bankruptcy in Houston on 7 June 2021. Its chief transformation officer stated in the filing that it had raised close to $3 billion in equity in six years without making a profit, with large losses on maximum-price guarantees and discounts given to early customers; its lender Greensill Capital had collapsed in March, and SoftBank Vision Fund, its largest investor, declined to invest more in May.

    LessonFixed prices promised to win early work turned into losses when costs overran.

    enr.com

    Credit

    Katerra; SoftBank Vision Fund

  5. 2024

    Lords find UK modular failing

    After ilke Homes and House by Urban Splash collapsed and Legal & General closed its modular housing factory in 2023, the House of Lords Built Environment Committee reported in January 2024 that the government's approach to MMC was "in disarray": millions of pounds of public money had gone in without a strategy or measurable goals, and "Category 1 (modular) MMC has been failing financially". It named caution among warranty providers and insurers, and unclear building regulations, as barriers.

    theconstructionindex.co.ukpinsentmasons.com

    Credit

    House of Lords Built Environment Committee, chaired by Lord Moylan

  6. 2026

    US modular share shrinks

    The US Census Bureau's Survey of Construction records how new houses are built. Its figures for 2025, published on 1 July 2026, show 14,000 of the 1,005,000 single-family houses completed were modular, about 1%, down from 4% in 1997 and 1998; the Northeast had the highest share, 5%. Manufactured homes built to the federal HUD code are counted in a separate survey and are not included.

    census.gov

    Credit

    US Census Bureau

Watch for

  1. A house factory goes public

    Boxabl, which makes a small factory-built house it calls the Casita, became a Nasdaq company on 17 July 2026 by merging with FG Merger II Corp., at a value of $3.5 billion set by the merger terms. It reports a backlog of 679 Casitas worth $45.0 million at 30 September 2026, against 36 Casitas delivered and $2.6 million of revenue in the first nine months of 2026; in the same filing it states "substantial doubt" about its ability to continue as a going concern, with an accumulated deficit of $811.3 million.

    Achieved whenaudited annual results show the backlog being delivered and revenue above the cost of goods sold.

    sec.gov

    Claimed by

    Boxabl, November 2026

Open

  1. 01

    Permit-to-occupancy times compared

    A comparison of how long modular and site-built apartment buildings take from first building permit to certificate of occupancy, built from city open data and matched by size, height and year.

    The brief
    Credit · unclaimed
  2. 02

    A ledger of house factories

    A public, sourced table of factories that make modules or wall panels for housing worldwide since 2000: opening date, owner, capacity, money raised, homes delivered, status and, for those that closed, the stated reasons.

    The brief
    Credit · unclaimed

Open 01 · the brief

Permit-to-occupancy times compared

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A comparison of how long modular and site-built apartment buildings take from first building permit to certificate of occupancy, built from city open data and matched by size, height and year.

Why it is still open

The Terner Center found in 2022 that at least four affordable projects built off site since 2018 claimed 10 to 30 percent shorter schedules, that cost results were mixed, and that detailed comparisons are difficult. A search for this brief found no study that checks such claims against public permit records.

ternercenter.berkeley.edu

Built with what exists

NYC Open Data's "DOB Certificate Of Occupancy" and "DOB NOW: Certificate of Occupancy" datasets and job filings, read through the Socrata API; New York City's modular-unit certification process (Buildings Bulletin 2014-003) and manufacturers' project lists to find modular jobs; Python with pandas.

  1. First step

    List 30 completed modular apartment buildings in New York City from public sources and find their job numbers in the DOB datasets.

  2. Done looks like

    At least 30 modular and 90 matched site-built multifamily buildings, with the median days from permit to certificate of occupancy for each group and confidence intervals, and the code and data published.

Open 02 · the brief

A ledger of house factories

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public, sourced table of factories that make modules or wall panels for housing worldwide since 2000: opening date, owner, capacity, money raised, homes delivered, status and, for those that closed, the stated reasons.

Why it is still open

Failures are told as stories, not data. A December 2025 essay lists Katerra, Veev, Entekra, Blu Homes, Factory_OS and Revolution Precrafted as a "graveyard" without a table, and accounts disagree even on whether Factory_OS has closed: its successor, Harbinger Production, told officials in February 2026 that it might lay off all 280 workers while saying it was not planning to shut. A search for this brief found no database of factory closures.

onebuild.substack.comvallejosun.com

Built with what exists

Company filings on SEC EDGAR and UK Companies House; court dockets; trade press; a shared spreadsheet; a language model to pull fields out of articles, with a person checking each row (see the Note "Seven more flagged").

  1. First step

    Enter ten well-documented cases, among them Lustron, Katerra, Veev, ilke Homes, Legal & General Modular Homes and Factory_OS, each with sources.

  2. Done looks like

    At least 100 factories in at least five countries, each field with a source, and the share that closed within five years of opening, by country and by type of factory.