Liquefaction

Liquefaction cleans natural gas of water, carbon dioxide and heavier gases, then chills it to about minus 160 °C, where it turns to liquid and can be stored and shipped.

7

Milestones achieved, from 1941 to 2026.

2

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1941

    Gas liquefied for winter

    After a cold January 1940 left the eastern United States short of gas, the East Ohio Gas Company weighed a $2.5 million pipeline extension against a $750,000 plant to liquefy gas and store it, and built the plant in Cleveland between September 1940 and January 1941, according to a history by Theodore Lemoff of the National Fire Protection Association. Time reported in June 1940 that the plant would chill gas to 250 °F below zero, keep it as a liquid in insulated spheres, and warm it back into the mains in winter. This use is called peak shaving: a plant liquefies gas when demand is low and sends it out on the coldest days.

    share.ansi.orgtime.com

    Credit

    East Ohio Gas Company; its sister company Hope Natural Gas built a pilot plant in West Virginia in 1940

  2. 1969

    Cascade plant ships to Japan

    Phillips Petroleum completed its Kenai plant in Alaska in July 1969. It chilled gas to minus 259 °F (about minus 162 °C) in a cascade, a series of refrigeration loops, each with a different refrigerant and each reaching a colder temperature. The ship Polar Alaska carried its first cargo to a terminal in Tokyo Bay; ConocoPhillips dates the voyage to 26 October 1969, and JERA, successor to the Japanese buyer, says the cargo arrived in November. ConocoPhillips, the successor company, says its cascade process is now licensed for over 120 million tonnes a year, about 21% of installed capacity worldwide; that share is its own figure.

    conocophillips.com

    Credit

    Phillips Petroleum (now ConocoPhillips)

  3. 2009

    One train, 7.8 million tonnes

    A train is one complete liquefaction line, with its own compressors and main heat exchanger. Qatargas 2 started two trains of 7.8 million tonnes a year each at Ras Laffan, Qatar, which Oil & Gas Journal described in April 2009 as two of the world's largest; the project had been much delayed. They use Air Products' AP-X process, which Air Products said raised single-train output by about 50% over the previous generation. Air Products sold its LNG technology business to Honeywell in September 2024.

    ogj.comgasworld.comairproducts.com

    Credit

    Qatargas, Qatar Petroleum and ExxonMobil (owners); Air Products (process)

  4. 2013

    Plant costs quadruple

    Brian Songhurst of the Oxford Institute for Energy Studies found that the cost of liquefaction plants rose from about $300 to $1,200 per tonne of yearly capacity between 2000 and 2013, using Wood Mackenzie data on 36 projects. That was about twice the rise in other upstream oil and gas costs. Australian budgets rose most: Gorgon by 21% to A$52 billion, Queensland Curtis LNG by 36% and Ichthys by 30%, according to reports he cites.

    Lessonremote sites, high labor costs and few specialist contractors can multiply what a plant costs.

    oxfordenergy.org

    Credit

    Brian Songhurst, Oxford Institute for Energy Studies (analysis)

  5. 2019

    Prelude loses power

    Shell's Prelude, a 488 m floating liquefaction plant moored about 475 km north-northeast of Broome, Western Australia, shipped its first cargo in June 2019. An electrical trip in February 2020 stopped cargoes for almost a year. On 2 December 2021 the facility lost all power, and inspectors from NOPSEMA, Australia's offshore safety regulator, found that the operator "did not have a sufficient understanding of the risks of the power system." NOPSEMA ordered production to stay shut until Shell could show it could recover essential power safely.

    Lessonon a plant at sea, electric power is part of the safety system, not only a utility.

    marinelink.comoedigital.com

    Credit

    Shell (operator); NOPSEMA (regulator)

  6. 2022

    Factory-built trains

    Venture Global's Calcasieu Pass in Louisiana uses 18 mid-scale trains: smaller units of one standard design, built as modules and grouped in pairs called blocks. It loaded its first cargo on 1 March 2022, 30 months after the final investment decision, the shortest time for any US export plant, according to the US Energy Information Administration. The company declared commercial operation only on 15 April 2025, and sold cargoes on the spot market in between. In October 2025 an International Chamber of Commerce tribunal found it had breached its duty to BP to declare commercial operation in time; an earlier tribunal had ruled for Venture Global in a similar case brought by Shell.

    Lessona fast first cargo is not the same as delivering to the buyers who paid for the plant.

    eia.goveia.govgiignl-documents.s3.fr-par.scw.cloudpgjonline.com

    Credit

    Venture Global LNG

  7. 2026

    One site, one strait

    On 18 March 2026 Iranian missiles, fired in response to Israeli and US strikes, hit the Ras Laffan liquefaction complex in Qatar. QatarEnergy said the strikes damaged LNG Trains 4 and 6, removing 12.8 million tonnes a year of capacity, roughly 16% of Qatar's 2025 exports, and that repairs could take three to five years, as reported by GIIGNL, the association of LNG importers. Shipping through the Strait of Hormuz, the route for about 20% of world LNG flows, was also blocked; in September 2026 QatarEnergy's chief executive said normal operations would resume within weeks of the strait reopening.

    Lessona large share of world supply at one site behind one sea lane can be lost at once.

    giignl-documents.s3.fr-par.scw.cloudogj.com

    Credit

    QatarEnergy (operator, damage figures); GIIGNL (report)

Watch for

  1. Lower emissions per tonne

    Petronas, a partner in LNG Canada at Kitimat, British Columbia, says the plant runs with greenhouse gas emissions per tonne about 35% lower than the best-performing LNG plants elsewhere and about 60% below the world average. It credits efficient gas turbines, methane leak detection and power from the mostly hydroelectric BC Hydro grid.

    Achieved whena full year of the plant's emissions, checked by an independent verifier, is published and compared with other plants on the same basis.

    petronas.com

    Claimed by

    Petronas, July 2025

  2. Arctic plant on grid power

    Equinor plans to run its Hammerfest LNG plant in northern Norway on power from the grid from 2030, after adding onshore compression from 2029. Norsk Petroleum, the Norwegian government's petroleum facts site, says an amended development plan for this was approved in 2023 to cut the plant's carbon dioxide emissions significantly.

    Achieved whenthe plant runs on grid power and its reported emissions, as published by the Norwegian authorities, fall accordingly.

    equinor.comnorskpetroleum.no

    Claimed by

    Equinor, on its website as read in November 2026

Open

  1. 01

    Record what plants really cost

    A public table of LNG export plants outside North America that reached a final investment decision since 2000. For each, give the cost and first-cargo date announced at the decision, and the final cost and actual first-cargo date, each figure linked to a public document. Then publish the median overrun and delay by region and by plant type: large onshore, mid-scale and floating.

    The brief
    Credit · unclaimed
  2. 02

    Count cargoes from floating plants

    A method that counts how often an LNG carrier is moored alongside each floating liquefaction plant, using free radar images from the European Union's Copernicus Sentinel-1 satellites, and turns those counts into an estimate of each plant's yearly output and downtime.

    The brief
    Credit · unclaimed

Open 01 · the brief

Record what plants really cost

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public table of LNG export plants outside North America that reached a final investment decision since 2000. For each, give the cost and first-cargo date announced at the decision, and the final cost and actual first-cargo date, each figure linked to a public document. Then publish the median overrun and delay by region and by plant type: large onshore, mid-scale and floating.

Why it is still open

Public Citizen's June 2026 analysis covered more than 20 export terminals in the United States, Canada and Mexico only, and found completed projects averaged 59% over their first cost estimates. The 2014 Oxford Institute study of plants worldwide drew on Wood Mackenzie's paid data and gives no row-by-row table. No public table for plants elsewhere was found.

citizen.orgoxfordenergy.org

Built with what exists

Company annual reports, investor presentations and regulator filings; AI models that read long documents and pull out figures (see the Note "The jobs agents repeat" and the Note "Seven more flagged"); a spreadsheet; a second person to check figures.

  1. First step

    Take the four Australian projects the Oxford study names (Gorgon, Queensland Curtis LNG, Pluto and Ichthys) and find each one's cost at the investment decision and at completion in the owners' annual reports.

  2. Done looks like

    At least 40 plants or expansions in Australia, the Middle East, Africa, Russia, Asia and Latin America; every figure linked to its source; a second person rechecks 50 figures and agrees on at least 95%; the table and the medians published under an open license.

Open 02 · the brief

Count cargoes from floating plants

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A method that counts how often an LNG carrier is moored alongside each floating liquefaction plant, using free radar images from the European Union's Copernicus Sentinel-1 satellites, and turns those counts into an estimate of each plant's yearly output and downtime.

Why it is still open

Kayrros, which sells satellite tracking of LNG plant outages, says floating plants are not covered, because their trains are cooled by seawater and give off no heat signal its method can detect. The open LNG-T3 dataset, which finds loadings from ship-tracking signals, records Prelude's cargoes for 2020 to 2024 but none from Malaysia's two floating plants and only one from Coral South off Mozambique, which began shipping in 2022. Searches of Crossref for satellite monitoring of floating LNG plants found no published method.

kayrros.comzenodo.org

Built with what exists

Sentinel-1 radar images from the Copernicus Data Space Ecosystem; the LNG-T3 dataset's ship list and loading records; open ship-detection models trained on Sentinel-1 images, such as those from the xView3 challenge; the list of floating plants and their capacities in GIIGNL's annual report; Python.

  1. First step

    Download every Sentinel-1 scene over Prelude for 2024 and mark by hand which ones show a carrier alongside.

  2. Done looks like

    For at least five floating plants and the years 2022 to 2025, yearly output estimated from carrier visits comes within 15% of the plant's published exports; the labeled images, code and yearly estimates published.