Rural build-out

Rural build-out is the physical work and money needed to run lines to places where homes are far apart, so each mile of cable serves only a few customers.

6

Milestones achieved, from 1949 to 2025.

2

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1949

    Loans for rural telephones

    On 28 October 1949 Congress amended the Rural Electrification Act so that the Rural Electrification Administration (REA), the federal agency already lending to build rural power lines, could also lend to furnish and improve rural telephone service. Only about 38% of US farmers had telephones in 1949, and about 80% by 1969, when 869 borrowers had taken over $1.6 billion in REA telephone loans at 2% interest, according to statements at a 1969 Senate hearing.

    rd.usda.govgovinfo.gov

    Credit

    the US Congress; the REA and the local telephone co-ops and companies that borrowed

  2. 2013

    Fiber dug by volunteers

    In Lancashire, England, residents formed Broadband for the Rural North (B4RN), a community benefit society launched in December 2011, sold shares to locals and dug trenches across fields with volunteers, with landowners giving access free. BBC News reported in February 2013 that B4RN put the cost of connecting a rural home at about £1,000, against up to £10,000 that BT and other companies estimated when digging along country roads, for a 500 Mbps service at £30 a month. B4RN says it now has more than 15,500 customers, and in 2026 it was laying fiber to over 600 properties in Lazonby, Cumbria, after villagers gathered sign-ups.

    bbc.co.ukb4rn.org.ukbbc.com

    Credit

    Barry Forde and the B4RN volunteers

  3. 2013

    Copper reused, then replaced

    A strategic review of Australia's National Broadband Network, released in December 2013, estimated the original plan of fiber to most premises at A$73 billion and recommended a "multi-technology mix" costed at A$41 billion, reusing existing copper phone lines and cable TV networks, with 44% of premises on fiber to the node (FTTN), where fiber runs to a street cabinet and old copper covers the last stretch. In September 2025 the ACCC, Australia's competition regulator, reported that FTTN lines on 50 and 100 Mbps plans made up 86% of the underperforming connections in its May 2025 tests. By the government's account, 1.5 million premises had been moved from copper to fiber by December 2025.

    LessonReusing copper lowered the first bill, but a decade later the same lines were being replaced with fiber.

    utilitymagazine.com.autheregister.comaccc.gov.au

    Credit

    NBN Co and the Australian Government; measured by the ACCC

  4. 2018

    One crew readies the pole

    Before a new line can go on a utility pole, the pole often needs make-ready work: moving the lines already on it, or replacing the pole. Under the old process each owner moved its own line in turn. On 2 August 2018 the FCC adopted one-touch make-ready, which lets the new attacher do all simple make-ready in the pole's communications space itself, with one crew, and cited estimates that this alone could add about 8.3 million premises passed with fiber. The rules govern poles in 30 states; the others and the District of Columbia regulate poles themselves.

    docs.fcc.gov

    Credit

    the FCC, on a recommendation of its Broadband Deployment Advisory Committee

  5. 2021

    A backbone few used

    Peru's Red Dorsal Nacional de Fibra Óptica, a 13,500 km fiber backbone with 322 nodes linking the capitals of the country's provinces, was concessioned in 2014 to Azteca Comunicaciones Perú as a public-private partnership, to sell capacity to the operators that serve customers. Those operators built their own fiber instead: a World Bank review found about 45,000 km laid by several operators by 2018, and Osiptel, the telecom regulator, judged that the 2013 plan had not allowed for competing fiber, 4G and mobile internet. Peru's Ministry of Transport and Communications (MTC) counted 3.2% of the backbone's capacity in use and state revenue covering 7.7% of its costs, ended the concession in July 2021, and took the network back in January 2022.

    LessonA backbone built for wholesale buyers found few once those buyers had built their own.

    dplnews.comdplnews.com

    Credit

    the MTC and Pronatel, its telecom program; Azteca Comunicaciones Perú; reported by DPL News

  6. 2025

    Fiber laid, villages offline

    India started BharatNet, first called the National Optical Fibre Network, in October 2011 to reach 250,000 gram panchayats (village councils) with fiber within three years. India's national auditor, the CAG, found that approval of the plan took 23 months and work began only in mid-2014. By November 2025 about 219,000 of a revised 226,000 gram panchayats were declared service-ready, but only 33.20% of those were working; fiber faults took 17 days on average to fix, and gram panchayats built under a private-led model were 90.11% working against 10.74% under the model led by state-owned companies.

    LessonPaying for cable laid, not for service kept running, left most of the network dark.

    cag.gov.inpolicyedge.in

    Credit

    Bharat Broadband Network (now merged into BSNL) and the Department of Telecommunications; audited by the CAG

Watch for

  1. Australia's last copper nodes

    The government says more than 99% of the roughly 600,000 premises still served by fiber to the node will be upgraded to full fiber by December 2030, funded by up to A$3 billion of new government equity and more than A$800 million from NBN Co, and that more than half of them are in regional areas.

    Achieved whenNBN Co's published premises counts and an ACCC report show the node network retired and those premises able to order fiber.

    minister.infrastructure.gov.auinfrastructure.gov.au

    Claimed by

    the Australian Government (Ministers Anika Wells and Katy Gallagher), September 2026

  2. BharatNet to every village

    The Amended BharatNet Program, approved in August 2023, aims to connect households in 640,000 villages within 36 months of contracts being signed. BSNL signed contracts for 12 of its 16 packages between February and June 2025, and the other 4 were still in tender in November 2025, the CAG reports.

    Achieved whenan audit or public data show households connected in those villages, with uptime reported village by village.

    cag.gov.in

    Claimed by

    BSNL and India's Department of Telecommunications, contracts signed February to June 2025

Open

  1. 01

    A make-ready clock

    A public table, updated each quarter, of how long pole owners take to ready poles for new broadband lines: applications received, poles involved, and days from application to completed make-ready, by pole owner and state, each figure linked to the filing it came from.

    The brief
    Credit · unclaimed
  2. 02

    Village links, checked in person

    A recurring public field check of BharatNet at village council offices. Each quarter, volunteers visit, with each council's permission, a fixed sample of gram panchayats listed as service-ready, record whether the fiber link and the Wi-Fi access point work, run a speed test and photograph the equipment, and the results are published beside the official counts.

    The brief
    Credit · unclaimed

Open 01 · the brief

A make-ready clock

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public table, updated each quarter, of how long pole owners take to ready poles for new broadband lines: applications received, poles involved, and days from application to completed make-ready, by pole owner and state, each figure linked to the filing it came from.

Why it is still open

A Congressional Research Service report of June 2026 says some states report timelines of up to five years in total for pole surveys and make-ready. New York requires every pole owner and attacher to report its requests and their processing times each year, and Kentucky's Public Service Commission has reported to its legislature every quarter since September 2024 on pole attachment backlogs, but a search in November 2026 found no dataset that puts such reports side by side.

everycrsreport.comnysenate.govapps.legislature.ky.gov

Built with what exists

State utility commission filings, starting with New York and Kentucky; the FCC's Electronic Comment Filing System for pole docket filings; a language model to pull dates and counts from PDF filings (see the Note "The jobs agents repeat"); SQLite and a spreadsheet.

  1. First step

    Put New York's latest annual pole reports and Kentucky's second-quarter 2026 report into one shared table layout.

  2. Done looks like

    At least eight states and 40 pole owners over four quarters, with median days per owner, every figure linked to its filing, and 50 figures rechecked by a second person.

Open 02 · the brief

Village links, checked in person

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A recurring public field check of BharatNet at village council offices. Each quarter, volunteers visit, with each council's permission, a fixed sample of gram panchayats listed as service-ready, record whether the fiber link and the Wi-Fi access point work, run a speed test and photograph the equipment, and the results are published beside the official counts.

Why it is still open

The CAG found only 33.20% of service-ready gram panchayats working in November 2025 and recommended real-time dashboards for uptime and service quality, which implies none is public. Earlier checks were one-off: a LIRNEasia and IIT Delhi survey in early 2016 found that 32 of 1,329 institutional users in two pilot areas used BharatNet. A search in November 2026 found no recurring public check.

cag.gov.inlirneasia.net

Built with what exists

KoboToolbox forms with GPS and photos; the Ookla Speedtest app or M-Lab's browser speed test; Python to tally results.

  1. First step

    Pick 20 service-ready gram panchayats in one district, test the form, and run the first round of visits.

  2. Done looks like

    200 service-ready gram panchayats in five states visited four times over a year, with the share working on each visit, speed results and photos published under an open license and set against the CAG's 33.20%.