Industries / Energy, water and waste / Power generation / Hydroelectric
Refurbishing old plants
Refurbishing keeps plants built decades ago working: overhauling or replacing turbines and generators, adding turbines to dams built for other purposes, and renewing the licenses that let plants run.
5
Milestones achieved, from 1993 to 2025.
2
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
1993
More power from Hoover
When Hoover Dam's last generating unit went on line on 1 December 1961, the plant's installed capacity was 1,334,800 kW. The US Bureau of Reclamation replaced the original turbines in an uprating program between 1986 and 1993, and the plant's nameplate capacity is now about 2,080 MW from the same dam.
Credit
US Bureau of Reclamation
1995
Runners repaired in place
Turbine runners are pitted by cavitation, bubbles that form in fast, low-pressure water and collapse against the metal, and worn by sand in the water, and repair used to mean lifting the runner out. Hydro-Québec has used Scompi, a portable welding robot (a six-axis arm on a track) that fits between blades 25 cm apart, for repair work since 1995. In 2003 Invensys delivered one to the Liujiaxia station on the Yellow River in China to repair erosion damage on runners in place; taking a runner apart for repair there typically took nine months.
Credit
Hydro-Québec; Invensys (supplier of the Liujiaxia system)
2012
Counting dams without power
Oak Ridge National Laboratory analyzed 54,391 of the more than 80,000 US dams that make no electricity and estimated that adding turbines could add up to 12 GW, about 8 GW of it at just 100 dams, most of them Army Corps of Engineers navigation locks. It did not consider cost. By ORNL's 2026 market report, 43 such dams were fitted with turbines between 2010 and 2025, adding 595 MW. In 2026 a study by ORNL and Idaho National Laboratory, using more detailed streamflow data for 3,299 of the dams, put their technical potential at nearly 4 GW across more than 2,600 dams.
Lessonan estimate of what is physically possible is a ceiling, not a forecast of what will be built.
Credit
Boualem Hadjerioua, Yaxing Wei and Shih-Chieh Kao, ORNL
2021
Grand Coulee overhaul runs long
The US Bureau of Reclamation overhauled the three 805 MW units in Grand Coulee's largest powerhouse: G24 returned to service in April 2016, G23 in March 2019 and G22 on 30 September 2021. Heavy wear on the wicket gates, shafts, thrust bearing, rotor, outer head cover and embedded parts stretched the contract four years beyond plan, and Reclamation turned the overhaul of the next three, older units into a wider modernization that may include replacing whole units.
Lessonan old machine's condition is known only once it is taken apart, so overhaul plans need room for what is found.
Credit
US Bureau of Reclamation
2025
A relicensing peak
In the United States, 48% of hydropower capacity needs a license from the Federal Energy Regulatory Commission (FERC) to run; licenses typically last 30 to 50 years and must then be renewed. At the end of 2025, 200 projects with 18.5 GW, 18% of US installed capacity, were in relicensing, by ORNL's count. FERC issued 21 relicenses in 2025, the most since 2005, and for 165 relicenses issued from 2010 to 2025 the process took a median of six years from the owner's notice of intent.
Lessonrelicensing takes years, so an owner must start long before a license runs out.
Credit
ORNL, U.S. Hydropower Market Report
Watch for
Hoover's low-water turbines
Lake Mead has fallen, and below an elevation of 1,035 ft Hoover's older turbines are expected to suffer severe cavitation damage; Reclamation's modeling shows capacity at that level falling to 382 MW, from an earlier estimate of 1,302 MW. Reclamation says it will spend about $52 million to replace up to three older turbines with wide-head units that can run near 950 ft and restore at least 160 MW. Circle of Blue reports that five of the 17 units are already wide-head; Reclamation gave no installation date.
Achieved whenthe new units are running and Reclamation or the Western Area Power Administration reports their output with the lake below 1,035 ft.
Claimed by
US Bureau of Reclamation, May 2026
Itaipu's 14-year control upgrade
Itaipu Binacional, which runs the 20-unit Itaipu plant on the Brazil–Paraguay border, says the first unit will stop in 2026 to begin replacing control and protection systems, at about two units a year until 2036, with about US$670 million contracted. It says the turbines, rotors and stators will stay because they are in excellent condition and far from the end of their life.
Achieved whena modernized unit is back in service with its new control system, reported by Itaipu and confirmed by Brazil's grid operator or another outside party.
Claimed by
Itaipu Binacional, to Canal Solar, January 2026
Open
01
Where 12 GW went
A row for each of the 100 dams that ORNL ranked highest in 2012 for adding power, giving what has happened since (built, under construction, licensed, permit expired or surrendered, or never proposed) and the reason given in public filings.
The briefCredit · unclaimed02
Checking upgrade gains
For 20 US plants refurbished since 2005 with a published gain in capacity or efficiency, a check of that gain against public records: the energy made per unit of water passed, before and after the work, from monthly generation and river-flow data, with the head taken into account.
The briefCredit · unclaimed
Open 01 · the brief
Where 12 GW went
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A row for each of the 100 dams that ORNL ranked highest in 2012 for adding power, giving what has happened since (built, under construction, licensed, permit expired or surrendered, or never proposed) and the reason given in public filings.
Why it is still open
The 2012 report names its top 100 dams in an appendix. ORNL's 2026 market report counts these projects only in total: 43 retrofits with 595 MW since 2010, and 92 projects in the development pipeline, many waiting on a second permit from the Army Corps of Engineers. ORNL's 2022 study of development opportunities reviewed recent retrofits for what they share, and its 2026 reassessment recalculated the potential at 3,299 dams; neither follows the 2012 list dam by dam. A search found stories about single projects but no follow-up of the 2012 list.
Built with what exists
Appendix A of the 2012 report; FERC's eLibrary docket search; ORNL's development pipeline data on OSTI; a model that reads long filings and pulls out dates and reasons, such as Meta's Muse Ember (see the Note "The jobs agents repeat"); a spreadsheet.
First step
Type Appendix A into a spreadsheet and look up the first ten dams in FERC's eLibrary.
Done looks like
All 100 dams with their status as of 2026, every status linked to a filing, stated reasons sorted into a few kinds (cost, permits, Corps review, financing, not stated), capacity totaled by outcome, and a second person agreeing with at least 18 of 20 random rows.
Open 02 · the brief
Checking upgrade gains
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
For 20 US plants refurbished since 2005 with a published gain in capacity or efficiency, a check of that gain against public records: the energy made per unit of water passed, before and after the work, from monthly generation and river-flow data, with the head taken into account.
Why it is still open
Gains are measured at handover by owners and contractors. At Chief Joseph Dam the Corps of Engineers sought a guaranteed 94% efficiency after tests found 88% to 89%, and an article by the contractor's public affairs leader reports 95.6% from a third-party test near completion. US owners spent an average of $646 million a year on refurbishments and upgrades in 2023–2025, 80% of it on turbine-generator work, by ORNL's count. Reports to the Department of Energy by single owners, such as Alabama Power's on four units it upgraded at three Coosa River plants from 2010 to 2014, cover one owner's own work. A 2026 conference abstract on planning turbine upgrades says "a rigorous method to determine when and how turbines should be upgraded" is missing. A search found no public check of claimed gains against years of reported generation.
renewableenergyworld.comosti.govosti.govmeetingorganizer.copernicus.org
Built with what exists
The US Energy Information Administration's Form 923 monthly plant generation; USGS daily streamflow from a gauge below each dam, or Reclamation and Corps release records; published reservoir and tailwater elevations; Python with pandas and statsmodels.
First step
Collect owners' and contractors' press releases that state a gain, and pick five of those plants that have a USGS gauge just below the dam.
Done looks like
20 plants, each with the claimed gain set beside the measured change in energy per unit of water and its uncertainty, using at least five years before and after the work; method and code published; results reported whether or not they match the claims.