Industries / Construction and property / EPC contractors
Modules and fabrication
This is the work of building sections of a plant, called modules, in fabrication yards far from the site, shipping them, and setting and joining them at the site, along with shop-built sections of pipe (spools) and steel.
6
Milestones achieved, from 1975 to 2024.
1
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
1975
Prudhoe Bay arrives by barge
Atlantic Richfield (ARCO) built the central gas compression plant for Alaska's Prudhoe Bay oil field as modules in the Seattle-Tacoma area, each up to 1,000 tons, to be carried north on barges in the short late-summer season when the Arctic ice pack moves offshore; its 1975 schedule moved 22 of the plant's 31 modules, Oil & Gas Journal reported in November 1974. An ARCO engineer gave the reasons in 1982: lower labor rates, higher labor productivity and more skilled workers in the lower 48 states than on the North Slope. By 1994 ARCO counted 18 sealifts since 1975 and 777 production modules weighing more than 340,000 tons, and single modules had grown to 5,000 tons.
Lessonmoving work to where labor is cheaper and more productive can pay for shipping very large pieces.
Credit
Atlantic Richfield; Fluor Daniel, which fabricated the 1994 modules
2011
Modules too big for roads
Imperial Oil had equipment modules for its Kearl oil sands project in Alberta brought by barge to the Port of Lewiston, Idaho, about 30 of them by fall 2010, to be trucked over US Highway 12, a two-lane road through the Clearwater National Forest and a wild and scenic river corridor, in loads that filled both lanes. A test module left Lewiston on 12 April 2011, clipped a guy wire and brought down a power line. Opponents contested the permits, and in August 2011 Imperial and ExxonMobil said "lengthy permitting delays" had led them to cut the modules' size and weight and send them by four-lane interstate highways instead.
Lessonthe largest module a project can use is set by the route to the site and the people along it, not only by the yard and the crane.
Credit
a failure; Imperial Oil, ExxonMobil and their hauler, Mammoet; the Idaho Transportation Department
2014
Why modules succeed, ranked
James O'Connor, William O'Brien and Jin Ouk Choi of the University of Texas at Austin, working with CII Research Team 283 of the Construction Industry Institute, ranked 21 critical success factors for using more modules on industrial projects. The top five were the limits on module size and weight (the module envelope), team agreement on the project's main goals, enough owner planning, freezing scope and design on time, and counting the value of finishing early. The team also found that the industry had trouble meeting many of the factors, and urged teams to treat modules as the default approach. A 2024 study by Amrit Shahi and Choi, then at the University of Nevada, Las Vegas, drawing on CII Research Team 396, put site location, site attributes, site access and labor costs at the top of the factors in the decision to modularize.
Lessonthe choice to build in modules has to be made before the design is fixed, because the design depends on it.
Credit
O'Connor, O'Brien and Choi; CII Research Teams 283 and 396
2017
An Arctic plant from Asia
Yamal LNG, on Russia's Yamal Peninsula, was built from 142 modules and 365 pre-assembled pipe racks, more than 480,000 tonnes in all, made at 10 Asian yards, according to a case study by Technip, which led the contractor group with JGC and Chiyoda. A fleet of 20 ships carried them, including two ice-breaking module carriers, Audax and Pugnax, built in Guangzhou for the job. In January 2017 Audax set out along the Northern Sea Route in midwinter with three modules of about 6,000 tonnes each from the Qingdao yard of China Offshore Oil Engineering (COOEC). The first of the three trains started up in 2017.
Credit
Yamgaz (Technip, JGC and Chiyoda); COOEC; ZPMC Red Box Energy Services, the ships' operator
2023
Core and rack built together
LNG Canada's plant at Kitimat, British Columbia, arrived as 215 modules of varying sizes, the last from a yard in Zhuhai, China, in July 2023, according to Fluor, which built the plant with JGC. COOEC built 35 of them, 179,000 tons including all 19 core process modules, at its Qingdao yard from December 2019. COOEC says it built the core process modules and the pipe rack modules as integrated units, instead of building them separately and connecting them at the site.
Credit
JGC Fluor; COOEC; the COOEC-Fluor yard in Zhuhai
2024
Sanctions turn modules around
After the United States sanctioned Novatek's Arctic LNG 2 project, its modules came from a few Chinese yards on a few heavy-lift ships. On 24 June 2024, days after the US sanctioned another Chinese module yard, Penglai Jutal Offshore Engineering Heavy Industries, Wison New Energies said it would stop all Russian work and sell its yard in Zhoushan, which had built 12 large pipe rack modules weighing 145,000 tons for the project. In July a ship carrying two 14,000-ton Wison modules for the third train turned back toward China, a source at the yard told gCaptain. The US had also blocked Red Box, the operator of Audax and Pugnax. Reporters at High North News and gCaptain followed the modules on Planet satellite images.
Lessona module program built far from the site rests on a handful of yards and ships, and sanctions can remove any of them.
Credit
a failure; Novatek; Wison New Energies; the US Treasury's Office of Foreign Assets Control
Watch for
Modules built near the site
Glenfarne chose Kiewit Offshore Services to build the liquefaction, pretreatment and pipe rack modules for its Texas LNG export plant at Kiewit's yard in Ingleside, Texas, instead of overseas. Its chief executive, Brendan Duval, said US fabrication "avoids tariffs, geopolitical risks, heavy-lift shipping, Panama Canal transit, and helps ensure quality control". Work starts on a notice to proceed, and a final investment decision was planned for the second quarter of 2026.
Achieved whenthe modules are built at Ingleside and set at Brownsville, and an outside party, such as the lenders' engineer or a filing with US regulators, compares their cost and schedule with the plan.
Claimed by
Glenfarne, March 2026
Open
01
An open module-yard model
A discrete-event simulation (a model that steps through each job, crane lift and ship sailing in time order) of a module fabrication yard: bays, cranes, crews, weather, skidways, the load-out quay and ship availability. Release it as open code and calibrate it with public module programs: COOEC's 35 LNG Canada modules from December 2019 to March 2023, Yamal's 142 modules and 365 racks from 10 yards, ARCO's yearly sealifts. Then use it on questions the public record raises, such as how much later a program finishes if one of three yards drops out halfway, as Wison did on Arctic LNG 2, or if one heavy-lift ship is lost.
The briefCredit · unclaimed02
Modular or stick-built, tested
An open scoring tool that turns the published modularization factors, O'Connor, O'Brien and Choi's 21 success factors and the top ten decision factors from CII Research Team 396, into a questionnaire and a score. Back-test it on 20 plants whose build method and problems are on the public record, both modular (Prudhoe Bay, Kearl, Yamal, LNG Canada) and stick-built (built piece by piece at the site), and check whether the risks it flags match what went wrong, such as Kearl's road limits.
The briefCredit · unclaimed
Open 01 · the brief
An open module-yard model
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A discrete-event simulation (a model that steps through each job, crane lift and ship sailing in time order) of a module fabrication yard: bays, cranes, crews, weather, skidways, the load-out quay and ship availability. Release it as open code and calibrate it with public module programs: COOEC's 35 LNG Canada modules from December 2019 to March 2023, Yamal's 142 modules and 365 racks from 10 yards, ARCO's yearly sealifts. Then use it on questions the public record raises, such as how much later a program finishes if one of three yards drops out halfway, as Wison did on Arctic LNG 2, or if one heavy-lift ship is lost.
Why it is still open
Yard simulations exist but belong to one firm. Hosein Taghaddos, Simaan AbouRizk and Yasser Mohamed of the University of Alberta, with R. Hermann of the contractor PCL, built a simulation-based scheduler for a module assembly yard that they say was "implemented successfully in the industry", and Di Hu and Mohamed (2014) set out a modeling method for fabrication shops; neither released a model others can run, and a GitHub search for "module yard" found only unrelated software.
Built with what exists
SimPy (an open Python library for discrete-event simulation); public module counts, weights and dates from company releases and trade press; ERA5 weather data from Copernicus for wind and rain stoppages.
First step
Put the dated module milestones for LNG Canada and Yamal from company releases into one table, with a source for each date.
Done looks like
Using only published inputs, the model reproduces the span from first to last module shipment for two programs within 15%, and its code, inputs and a table of what-if results are public.
Open 02 · the brief
Modular or stick-built, tested
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
An open scoring tool that turns the published modularization factors, O'Connor, O'Brien and Choi's 21 success factors and the top ten decision factors from CII Research Team 396, into a questionnaire and a score. Back-test it on 20 plants whose build method and problems are on the public record, both modular (Prudhoe Bay, Kearl, Yamal, LNG Canada) and stick-built (built piece by piece at the site), and check whether the risks it flags match what went wrong, such as Kearl's road limits.
Why it is still open
Amrit Shahi and Jin Ouk Choi write that many heavy industrial projects have not gained from modularization "due to poor and late decisions", and the decision models they reviewed were the business cases of individual companies. CII's Research Team 283 set out a business case process for members, to be applied "at the earliest opportunity", but no published test of such a score against finished plants was found. A GitHub search for "modularization" found only software-architecture projects.
Built with what exists
Python or a spreadsheet; the two papers' factor lists; public project records; an AI model to pull project facts from sources, each fact checked by hand.
First step
Code the 21 success factors and the ten decision factors into one question list, and score Kearl as the first test case.
Done looks like
20 projects scored, with sources; for each project with documented problems, a record of whether the tool flagged them in advance; published hit and miss counts.