Industries / Construction and property / EPC contractors
Buying and expediting equipment
This is the work of buying a plant's equipment and bulk materials, chasing suppliers so that each item arrives on time (expediting), inspecting work in suppliers' factories, and collecting the documents each supplier owes.
5
Milestones achieved, from 1954 to 2025.
2
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
1954
One standard for pumps
The American Petroleum Institute (API) published the first edition of API Standard 610, for centrifugal pumps, in 1954. A shared standard lets a buyer order a pump to rules that every maker already knows, instead of writing its own. Users, engineering contractors and pump makers write it together, on a task force of 84 members by the latest count, and new editions have come about every five years; the 13th was released in June 2026. Simon Bradshaw of Trillium Flow Technologies, a pump maker, calls it the main standard for supplying centrifugal pumps to the oil and gas industry since 1954.
Credit
American Petroleum Institute and its API 610 task force
2013
Forged papers idle reactors
In May 2013 South Korea's nuclear regulator, the Nuclear Safety and Security Commission (NSSC), ordered Korea Hydro and Nuclear Power (KHNP) to stop two reactors and keep two more offline, because safety-related control cables had been installed with forged test documents. A Korean testing institute had sent part of the testing to a Canadian lab, and when some cables failed there, a staff member altered the result. By October the government had found 277 forged documents among 22,000 for parts at 20 reactors, and 2,010 among 218,000 for eight more units, five of them under construction; 100 people were indicted. Replacing the cable at the new Shin Kori 3 and 4 reactors delayed them by up to a year.
Lessona test certificate is evidence only if the buyer can trace it to the lab that ran the test.
world-nuclear-news.orgworld-nuclear-news.orgworld-nuclear-news.org
Credit
a failure; found by the NSSC after a tip-off
2016
Shared buying specifications
The International Association of Oil & Gas Producers (IOGP) started Joint Industry Programme 33 (JIP33) in 2016, with support from the World Economic Forum, in response to cost and schedule overruns of more than 40% across the industry. Until then each operator had asked suppliers to meet its own requirements, often hundreds of pages long and different even between one company's projects. Each JIP33 specification adds to an existing industry standard in four parts: technical requirements; a list of the documents and data the supplier must deliver, called the information requirements specification; the buyer's inspection and testing, called the quality requirements specification; and a data sheet for the project's choices. IOGP says 60 specifications are published, free to anyone, and that its 12 sponsoring operators, among them bp, Saudi Aramco, Shell and Petrobras, have committed to use them.
Credit
IOGP and its 12 sponsoring operators; Aker Solutions, which helps deliver the program
2022
Sanctions stop turbine deliveries
Baker Hughes was to supply 20 LM9000 gas turbines to Novatek's Arctic LNG 2 plant in northern Russia, seven of them for the first of three liquefaction trains. After Russia invaded Ukraine and Western sanctions followed, it delivered four, the last shipped to Novatek's Belokamenka yard near Murmansk on 25 May 2022, and left Russia. Technip and Saipem, which had key roles in the large bases the trains stand on, also left. In May 2023 High North News reported that Harbin Guanghan Gas Turbine, part of China Shipbuilding Industry Company, would supply turbines for the first two trains, and the Russian newspaper Kommersant described them as adaptations of a 1980s Ukrainian design.
Lessonan item that only one supplier makes, and that a government can embargo, can stop a plant whatever the contract says.
Credit
a failure; Novatek; Baker Hughes
2025
Paying for a factory slot
As orders for gas-fired power plants rose, driven in large part by data centers, makers of large gas turbines began taking money for a place in their production queue before a firm order. POWER magazine reported in April 2025 that reservation fees (non-refundable deposits) and production slot agreements, which fix a delivery window, had returned. Mitsubishi Power's Peter Sawicki said "We're back to the days of reservation fees", Southern Company's chief executive said it was paying them "to get in line", and Bobby Noble of EPRI, the utilities' research institute, put a new plant at 2029 or 2030. NRG Energy, which formed an alliance with GE Vernova and the contractor Kiewit, held slot reservations for two GE Vernova 7HA turbines, 1.2 GW due by 2029. GE Vernova said it had signed 9 GW of slot reservation agreements in 2024.
Lessonwhen a key item is scarce, the buyer commits money for it before the plant's design is fixed.
Credit
GE Vernova, Siemens Energy and Mitsubishi Power; buyers including NRG and Southern Company
Watch for
Twenty-four gigawatts a year
GE Vernova says it will raise its gas turbine manufacturing capacity to about 24 GW a year by 2028. In the first quarter of 2026 it shipped 4 GW of equipment and signed 21 GW of new agreements, 19 GW of them slot reservations, and its chief executive, Scott Strazik, said about 10 GW of capacity remained across 2029 and 2030 combined.
Achieved whenGE Vernova's annual report shows about 24 GW of gas turbines shipped in one year.
Claimed by
GE Vernova, April 2026
JIP33 in machine-readable form
IOGP says it is piloting versions of the JIP33 specifications in ReqIF, an open file format for passing requirements between software tools, and that they will be offered through its online bookstore; today the library is a set of PDF files.
Achieved whenReqIF files for the specifications are published and a contractor or supplier outside IOGP reports loading them into its requirements software.
Claimed by
IOGP, 2026
Open
01
Check supplier packages against JIP33
A public test of AI document reviewers on a job an EPC contractor's engineers and document controllers do for every order: checking that a supplier's documents meet the buyer's specification. Take five JIP33 specifications, such as S-615 for centrifugal pumps and S-562 for ball valves. For each, write 20 made-up supplier packages (data sheets, drawing lists, inspection and test plans, certificate lists) that follow the specification's information and quality requirements, and plant known gaps in them: a missing deliverable, a document sent "for information" that must be sent "for acceptance", a missing hold or witness point for the chosen risk level, a data sheet value outside the buyer's selection. Publish the packages, the answer key and a scoring script.
The briefCredit · unclaimed02
Remote witnessing, measured
A controlled comparison of factory witness inspection done in person and over live video. Set up a pump skid at a training center, switched off, drained and not under pressure, with 30 planted nonconformances (items that break the order's requirements) drawn from a witness-test checklist: wrong nameplate data, missing tags, a gap in the coupling guard, voids under the baseplate, the wrong flange rating stamped, paint defects, a missing document. Have 20 experienced inspectors check it, half in person and half through a helmet camera and phone video, then swap modes on a second skid with a different set of faults.
The briefCredit · unclaimed
Open 01 · the brief
Check supplier packages against JIP33
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public test of AI document reviewers on a job an EPC contractor's engineers and document controllers do for every order: checking that a supplier's documents meet the buyer's specification. Take five JIP33 specifications, such as S-615 for centrifugal pumps and S-562 for ball valves. For each, write 20 made-up supplier packages (data sheets, drawing lists, inspection and test plans, certificate lists) that follow the specification's information and quality requirements, and plant known gaps in them: a missing deliverable, a document sent "for information" that must be sent "for acceptance", a missing hold or witness point for the chosen risk level, a data sheet value outside the buyer's selection. Publish the packages, the answer key and a scoring script.
Why it is still open
Software firms say their tools do this work. Wrench AI sells a Technical Reviewer that checks "vendor submissions against the standards that govern your project", and an open prototype, RFQ Deviation Analyzer, flags deviations in requests for quotation with AI models run on the user's own computer. Neither publishes miss or false-alarm rates, and searches of GitHub and arXiv found no test set built on JIP33.
Built with what exists
The JIP33 specifications (free PDFs from IOGP); Python with PyMuPDF to read PDFs; AI models such as Claude Haiku 5.5 or Meta's Muse Ember (see the Note "The jobs agents repeat") and open models run through Ollama; a spreadsheet for the answer key.
First step
Download S-615's four documents and list every required deliverable and every inspection point in one spreadsheet, which becomes the template for the answer key.
Done looks like
100 packages, each with 5 to 15 planted gaps confirmed by two engineers; published recall and false-alarm rates for at least three reviewers; and a list of the gap types every reviewer missed.
Open 02 · the brief
Remote witnessing, measured
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A controlled comparison of factory witness inspection done in person and over live video. Set up a pump skid at a training center, switched off, drained and not under pressure, with 30 planted nonconformances (items that break the order's requirements) drawn from a witness-test checklist: wrong nameplate data, missing tags, a gap in the coupling guard, voids under the baseplate, the wrong flange rating stamped, paint defects, a missing document. Have 20 experienced inspectors check it, half in person and half through a helmet camera and phone video, then swap modes on a second skid with a different set of faults.
Why it is still open
The one published study found, in ISPE's Pharmaceutical Engineering in 2022, was qualitative: five automation projects and seven interviews, with no detection rates. Nick Ganatra of FMC Technologies and the consultant R. C. Patel argued at the 2012 Pump Symposium that a witness on site can catch problems that the written acceptance criteria do not name, but measured nothing. No measured comparison was found.
Built with what exists
A training pump skid; a RealWear Navigator headset or phones; Microsoft Teams or Zoom; a scoring sheet; Python or R for the statistics.
First step
Write the 30-item fault list from published API 610 witness-test practice and ask a technical college with a pump lab to host the skid.
Done looks like
Detection rates for each mode, with 95% confidence intervals, over at least 600 inspector-item checks, and a table of the fault types that video missed more often.