Construction management
Construction management is running the site of a large plant: splitting the work into packages that crews can finish, housing and supplying thousands of workers, and measuring how much of their day goes into building.
6
Milestones achieved, from 1983 to 2025.
1
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
1983
Owners fund construction research
In October 1983, 28 charter member companies set up the Construction Industry Institute (CII) at the University of Texas at Austin. They were acting on a five-year Business Roundtable study, the Construction Industry Cost Effectiveness (CICE) Project, which had recommended a body to lead research on construction. CII's research teams, made up of owners, contractors and academics, later wrote the work-packaging model described below.
Credit
The Business Roundtable; CII's charter members; the University of Texas at Austin
2009
Strikes over posted workers
On 28 January 2009, contract workers at Total's Lindsey Oil Refinery in Lincolnshire, England, walked out over the hiring of Italian and Portuguese workers by IREM, an Italian subcontractor building a new desulfurization unit, and sympathy strikes spread to power plant sites across Britain. Talks run by Acas, the UK's conciliation service, ended the dispute on 5 February with about 100 new jobs on the site opened to UK workers. Acas's inquiry then found that Total, Jacobs Engineering and IREM had not broken EU law and had followed the industry's collective agreement.
LessonPay and hiring on a plant site can fall under EU law, a national agreement and local agreements at once, and Acas recommended a review of how they fit together and a larger role for the independent auditor of the National Agreement for the Engineering Construction Industry (NAECI).
Credit
Acas; Eurofound's account of the dispute
2011
Tool time has not risen
"Direct work", also called tool time, is the share of a craft worker's day spent installing material. Jie Gong, John Borcherding and Carlos Caldas analyzed time studies (work sampling and five-minute ratings) from 98 construction projects between 1972 and 2009 and found that direct work ratios and crew effectiveness had not improved over that period. The same year, Gouett, Haas, Goodrum and Caldas used 26 project data points from two large firms to show that repeated "activity analysis", measuring how workers spend their time and then removing the causes of waiting, raised direct-work rates.
Credit
Gong, Borcherding and Caldas; Gouett, Haas, Goodrum and Caldas
2013
Work packaging becomes a model
Workface planning, getting every material, tool, drawing and permit ready before a crew starts a task, grew out of large Alberta oil sands projects. CII's research team 272 began studying work packaging in 2009 and from 2011 worked jointly with the Construction Owners Association of Alberta (COAA). Its model, Advanced Work Packaging (AWP), reached version 3.1 in October 2013: the plant is divided into construction work areas, then construction work packages, then installation work packages handed to crews, and engineering and purchasing are planned around the order of building. A 2016 CII report on the team's case studies documented field productivity gains "on the order of 25%" and total installed cost about 10% lower.
LessonThe benefit figures came from case studies of firms that had adopted AWP, and in 2019 Yonas Halala and Aminah Robinson Fayek of the University of Alberta wrote that the lack of quantitative evidence for those benefits was a significant challenge to its adoption.
Credit
CII research team 272; COAA
2014
Workers counted on the island
Three LNG export plants were built side by side on Curtis Island, off Gladstone in Queensland, Australia, with workers flown or driven in and housed in camps. The Queensland Government Statistician's Office counted the non-resident workers on shift each June: on Curtis Island the count rose from 855 in June 2012 to a peak of 5,475 in June 2014, then fell to 1,095 by June 2016 as construction wound down and camps were closed or shrunk. Across the Gladstone region the non-resident population peaked at 6,655 in 2014.
LessonThe office noted that the plants' operating workforces would be small next to their construction workforces, so the camps built for the peak were taken down within two years of it.
Credit
Queensland Government Statistician's Office
2025
Outside data on work packaging
Vishal Porwal, William O'Brien and John Borcherding compared work-sampling data from 61 projects measured by a productivity consultant and 23 projects of a large EPC firm, all from 2015 to 2023. Projects that used AWP and workface planning had significantly higher direct-work rates, and rates that were easier to predict, than projects that did not.
LessonThe result is a correlation across projects, not a controlled trial.
Credit
Porwal, O'Brien and Borcherding, in Frontiers in Built Environment, July 2025
Watch for
Packages drawn from the model
Doosan Enerbility of South Korea says it piloted AWP with AVEVA's WorkPacks software to standardize its construction work areas and packages, turn design models into construction-ready models and track progress in 4D (a 3D model linked to the schedule), linking drawings, materials, constraints and the schedule to allow "repeatable packaging at scale". The session description gives no measured results.
Achieved whenDoosan or an outside party publishes direct-work rates, rework or schedule results for projects packaged this way next to comparable projects that were not.
Claimed by
Changmin Choi of Doosan Enerbility, at AVEVA World in Milan, May 2026
Open
01
Work packages, drafted and scored
An open test for software that drafts installation work packages. It has three parts: a 3D model of one plant area, such as a pipe rack and the equipment beside it, with a few thousand tagged components, their quantities and their locations; a matching schedule; and the packages that three experienced workface planners make from them, each with its material, scaffolding and permit constraints. Any packager, rule-based or AI, is then scored against the planners.
The briefCredit · unclaimed02
Workforce forecasts against counts
A table that sets each workforce projection published for Queensland's resource regions against the count published later for the same year and place, and then a model that forecasts a plant site's peak workforce from public data, scored on the same counts.
The briefCredit · unclaimed
Open 01 · the brief
Work packages, drafted and scored
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
An open test for software that drafts installation work packages. It has three parts: a 3D model of one plant area, such as a pipe rack and the equipment beside it, with a few thousand tagged components, their quantities and their locations; a matching schedule; and the packages that three experienced workface planners make from them, each with its material, scaffolding and permit constraints. Any packager, rule-based or AI, is then scored against the planners.
Why it is still open
CII's report FR-391 of December 2023 still ranks the uses of AI in AWP as opportunities to be developed. The automatic methods found are a 2009 framework for generating work packages (Ibrahim and others, cited by Halala and Fayek), a 2023 simulation study on one Canadian project (Wollert) and vendor rule engines such as AVEVA WorkPacks, and none publishes a test set. GitHub searches for "workface planning" and "installation work package" in November 2026 returned no repositories.
Built with what exists
IfcOpenShell and FreeCAD, open-source tools that read and write IFC model files; MPXJ, an open-source library that reads Primavera P6 and Microsoft Project schedules; an AI model such as Claude Haiku 5.5 as one packager under test (see the Note "The jobs agents repeat").
First step
Model one pipe-rack bay in IfcOpenShell with tagged components, have one workface planner package it, and record how long it takes.
Done looks like
The model, schedule, the three planners' packages and a scoring script published under an open license, and at least two packagers scored on how often they put components in the same package as the planners and on how many constraints they miss. A packager counts as matching the planners when its agreement with each planner is at least as high as the planners' agreement with each other.
Open 02 · the brief
Workforce forecasts against counts
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A table that sets each workforce projection published for Queensland's resource regions against the count published later for the same year and place, and then a model that forecasts a plant site's peak workforce from public data, scored on the same counts.
Why it is still open
The Queensland Government Statistician's Office publishes both projection series, "based on information provided by industry regarding existing operations and future projects", and yearly counts of non-resident workers on shift, such as Curtis Island's peak of 5,475 in June 2014. No published comparison of the two was found, and the environmental impact statements that hold each project's own forecast could not be downloaded from the state's document server in November 2026.
Built with what exists
QGSO's report PDFs; pdfplumber or Camelot, open-source tools that read tables from PDFs; pandas; scikit-learn for the forecasting model.
First step
Download QGSO's Gladstone count and projection reports for each year it published them, and tabulate the Curtis Island figures.
Done looks like
Every projection and count pair in the published reports tabulated with page references; the error of the industry-based projections reported by how many years ahead they were made; and a model's two-year-ahead forecasts scored on the same pairs, with its error published next to the projections' error.