Connecting new plants

Before a new power plant, wind or solar farm, or battery can plug into the grid, the grid owner studies its effect on nearby lines and decides what upgrades are needed and who pays, while the request waits in a line called an interconnection queue.

6

Milestones achieved, from 1996 to 2025.

2

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1996

    Grids opened to all generators

    FERC Order 888, issued on 24 April 1996, required every US utility that owns interstate transmission lines to file an "open access" tariff, offering others service on the same terms it gives itself. FERC's stated aim was to remove barriers to competition in wholesale power.

    govinfo.gov

    Credit

    US Federal Energy Regulatory Commission (FERC)

  2. 2003

    A standard way to connect

    FERC Order 2003, issued on 24 July 2003, required utilities to use standard procedures and a standard contract to connect any generator larger than 20 MW, starting from the procedures of ERCOT, the Texas grid operator. Requests took a place in line by date of arrival and were studied one by one.

    govinfo.gov

    Credit

    FERC; ERCOT

  3. 2013

    Texas builds lines before farms

    In 2008 the Public Utility Commission of Texas set up five Competitive Renewable Energy Zones and approved lines to carry 18,500 MW of wind power from them; all were energized by the end of 2013. EIA puts them at more than 3,500 miles and $7 billion, ERCOT at about 3,600 miles of 345 kV line and $6.8 billion, and EIA reports that wind power wasted for lack of line capacity fell steadily after 2011.

    eia.govercot.com

    Credit

    Public Utility Commission of Texas; ERCOT

  4. 2022

    Queues pass 2,000 GW

    At the end of 2022 US queues held more than 10,000 active requests totaling over 2,000 GW of generation and storage, more than four times the 2010 total, by Berkeley Lab's count as cited by FERC. FERC found that 68% of the 2,179 interconnection studies finished in 2022 were late, and that plants built in 2022 had waited about five years.

    Lessona cheap, first-come queue fills with speculative projects, and each withdrawal forces restudies that delay everyone behind it.

    govinfo.gov

    Credit

    Lawrence Berkeley National Laboratory's "Queued Up" team (Joseph Rand and colleagues); FERC

  5. 2023

    FERC switches to cluster studies

    FERC Order 2023, in force from 6 November 2023, replaced one-by-one studies with "first-ready, first-served" cluster studies of many requests at once, with larger deposits and withdrawal penalties for developers and penalties for late studies. Berkeley Lab counts about 2,061 GW still waiting at the end of 2025 and finds that only 13% of capacity that asked to connect from 2000 to 2020 had been built; the median plant built in 2025 waited 61 months, against 22 in 2008, though most of its data predate the reform.

    govinfo.govosti.gov

    Credit

    FERC; Berkeley Lab (tally)

  6. 2025

    Britain reorders its queue

    In April 2025 Ofgem, Britain's energy regulator, approved the system operator NESO's plan to end first-come, first-served connections, after 444 GW of new applications in 2023/24 and offered dates reaching into the 2040s. Projects now get a firm "Gate 2" date only if they are ready and fit the government's Clean Power 2030 plan. NESO published the reordered queue in December 2025, which Knight Frank reports as 283 GW of generation and storage, down from more than 700 GW.

    ofgem.gov.ukknightfrank.co.uk

    Credit

    NESO; Ofgem

Watch for

  1. Automated studies at MISO

    MISO, which runs the grid for much of the US Midwest, says Pearl Street Technologies' SUGAR software found more than 99% of the grid problems its existing software found in a benchmark and cuts the first study phase from months to days. MISO's own slides still show full study cycles taking 3 to 4 years against a target of about one.

    Achieved whenqueue data show MISO's full study cycles getting shorter, confirmed by an outside tally such as Berkeley Lab's.

    esig.energy

    Claimed by

    MISO and Pearl Street Technologies, October 2025

  2. Fast lane for needed plants

    MISO's Expedited Resource Addition Study takes up to 10 projects a quarter, to a cap of 68, until 31 August 2027, for plants that meet a reliability need, have state support and can run within three to six years. By March 2026 MISO had picked 27 GW of mostly gas and battery projects, E&E News reports.

    Achieved whenthese plants reach commercial operation on their promised dates, as recorded in queue data or an outside tally.

    utilitydive.comeenews.net

    Claimed by

    MISO, August 2025 to March 2026

Open

  1. 01

    Read interconnection studies automatically

    A tool that reads the PDF studies grid owners publish for each project waiting to connect, and pulls out the estimated cost of each grid upgrade with the page it came from.

    The brief
    Credit · unclaimed
  2. 02

    Europe's queues in one table

    A monthly table of grid connection queues across Europe, built from what each transmission and distribution company publishes, in one format, with a list of companies that publish nothing.

    The brief
    Credit · unclaimed

Open 01 · the brief

Read interconnection studies automatically

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A tool that reads the PDF studies grid owners publish for each project waiting to connect, and pulls out the estimated cost of each grid upgrade with the page it came from.

Why it is still open

For its February 2026 report on five utilities in the US West and Southeast, Berkeley Lab copied costs out of study PDFs by hand, about 20 minutes per project and 700 hours in all, and wrote that the lack of machine-readable cost data "poses an information barrier for prospective developers."

escholarship.org

Built with what exists

Berkeley Lab's posted project-level cost data as the answer key; the published study PDFs; vision-language models that read tables in scanned and digital documents; an agent that cites the page behind each number (see the Note "Findings that cite notes").

  1. First step

    Download 50 study PDFs from one of the five utilities, run a model on them, and compare its figures with Berkeley Lab's.

  2. Done looks like

    On the roughly 2,100 cost estimates in the Berkeley Lab sample, the tool's total matches the hand-copied figure within 5% for at least 95% of projects, with code and results public.

Open 02 · the brief

Europe's queues in one table

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A monthly table of grid connection queues across Europe, built from what each transmission and distribution company publishes, in one format, with a list of companies that publish nothing.

Why it is still open

Ember counted almost 700 GW of renewables waiting to connect, but only across eight countries that report queue data, and notes that many countries, including Germany and Italy, do not publish grid capacity data. Revised EU rules now require grid operators to publish available capacity, including capacity under connection request, monthly for transmission and quarterly for distribution companies, according to Ember.

ember-energy.orgember-energy.org

Built with what exists

Operators' capacity maps and queue lists; an agent that visits each site monthly, extracts the figures and cites the page (see the Note "Findings that cite notes"); a shared format modeled on Berkeley Lab's US queue data.

  1. First step

    List the EU's transmission operators and record which ones publish a queue or capacity map this month.

  2. Done looks like

    Every EU transmission operator and the 50 largest distribution companies checked each month for six months, with queued GW by technology where published, "not published" where not, and every figure linked to its source.