Industries / Construction and property / Commercial and residential construction / Demolition
Surveys and planning
Before anything comes down, someone checks how the structure stands, decides the order in which it will be taken apart, tells the authorities and lists what it will release.
5
Milestones achieved, from 1971 to 2023.
1
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
1971
A survey before work
On 17 April 1971 the US Bureau of Labor Standards published safety rules for construction. Their demolition subpart required a competent person to survey the structure before work began, checking the framing, floors and walls and the chance of an unplanned collapse, and required the employer to keep written evidence of the survey. The same subpart required gas, electric, water and other service lines to be shut off or capped, and pipes and tanks that had held hazardous substances to be tested and purged. The rule survives almost word for word as 29 CFR 1926.850.
Credit
US Department of Labor, Bureau of Labor Standards
2013
Wall falls on a shop
On 5 June 2013 a four-story wall of 2136 Market Street in Philadelphia, a building being taken down by excavator, fell onto the one-story Salvation Army thrift shop next door while the shop was open. Six people in the shop died; a City Council committee counted 13 seriously injured, and the federal Occupational Safety and Health Review Commission's decision says twelve were injured. Photos from the two previous working days show the wall growing more freestanding as the machine worked, although US rules already forbade a wall section more than one story high to stand without lateral bracing, and OSHA, the federal safety regulator, cited the excavator operator's firm, S&R Contracting, for a willful violation. The council committee found that the city required neither an engineering survey nor a site safety plan for private demolitions. The city's Code Bulletin B-1302 of 12 June 2013 made contractors prove their qualifications and file a site safety plan for approval before work, sealed by a licensed engineer for commercial buildings over three stories, and required demolition one floor at a time from the top.
Lessona survey and a bracing rule that nobody checks before and during the work did not protect the people next door.
Credit
Philadelphia City Council Special Investigating Committee on Demolition Practices; Philadelphia Department of Licenses and Inspections; Occupational Safety and Health Review Commission
2015
Demolition plans in writing
From 6 April 2015, the UK's Construction (Design and Management) Regulations require demolition to be planned and carried out so as to prevent danger, or cut it as low as is reasonably practicable, and the arrangements to be written down before the work begins.
Credit
UK government (Construction (Design and Management) Regulations 2015, regulation 20)
2018
EU guidelines for audits
In May 2018 the European Commission published guidelines for a waste audit before demolition or renovation: a desk study of plans and records, a field survey, an inventory of materials and building elements, and advice on reuse, recycling and hazardous waste, done by a qualified auditor. The guidelines leave the building size above which an audit is needed to national authorities, and call the thresholds then in use "highly variable" across the EU.
Credit
European Commission
2023
France asks what is reusable
A French decree of May 2011 required a waste diagnostic before the demolition of large buildings, those over 1,000 m², and of buildings that had held hazardous substances. From 1 July 2023 it became the PEMD diagnostic (for products, equipment, materials and waste), which puts reuse first. The owner files it before applying for a permit, and files an after-works report within 90 days of finishing, on a platform run by CSTB, France's building research center. By the platform's own count, 838 diagnostics were filed on it in 2024 and 956 in 2025, against 26 and 148 after-works reports.
ecologie.gouv.frplateformepemd.developpement-durable.gouv.fraida.ineris.fr
Credit
French Ministry of Ecological Transition; CSTB, with funding from ADEME
Watch for
Audits from a phone video
Matthias Schuch trained two object detectors, YOLOv11 and Mask R-CNN, on expert-labeled walk-through videos of 11 older Vienna apartment buildings in need of renovation, to list reusable doors, windows, radiators, lamps, handrails and other items and estimate their value. He reports about 20 minutes of work per property against 450 for an expert, a 22.5-fold saving. Detection scores were low (AP50, a score from 0 to 1 for how well boxes match the labels, of 0.019 and 0.046), and the software valued each property's items at about €1,275 against the experts' €1,925.
Achieved whenanother group runs the method on buildings outside the training set and publishes its item counts and values against a professional audit of the same buildings.
Claimed by
Matthias Schuch, TU Wien diploma thesis, January 2026
Open
01
Collapses and the missing survey
A public table of every fatal US demolition accident in which part of a structure fell unexpectedly, built from OSHA's fatality inspections since 2011. Each row says what fell, at what stage of the job, and whether OSHA cited the survey rule (1926.850(a)) or the wall-bracing rule (1926.854(b)), with a link to the inspection.
The briefCredit · unclaimed02
Check France's audit numbers
For each French operation whose PEMD waste figures are public, set the declared tonnes of concrete, brick, metal and wood against an estimate made from the building's size and age in France's national building database (BDNB) and published material intensities, the kilograms of each material per square meter of floor. Publish the ratio for every operation, with the code.
The briefCredit · unclaimed
Open 01 · the brief
Collapses and the missing survey
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public table of every fatal US demolition accident in which part of a structure fell unexpectedly, built from OSHA's fatality inspections since 2011. Each row says what fell, at what stage of the job, and whether OSHA cited the survey rule (1926.850(a)) or the wall-bracing rule (1926.854(b)), with a link to the inspection.
Why it is still open
Engineering News-Record read OSHA's 2021 fatal demolition records one by one and found that they often involved premature collapses or loss of support. For Japan, Hiroki Takahashi of the National Institute of Occupational Safety and Health coded the 2010 to 2014 demolition deaths from government data and found falls (52%) and collapses (19%) the two largest causes. No table covering several years of US cases, with the standards OSHA cited, was found.
Built with what exists
OSHA's fatality inspection export, which covers federal inspections opened after April 2011 and state-plan inspections from about October 2014; OSHA's inspection pages for the standards cited; a model that answers fixed-choice questions in bulk, such as Google's Gemini Decision 1 (see the Note "A thousand questions, one pass"); Python.
First step
Export OSHA's fatality table, keep the rows that mention demolition, and code 30 by hand to settle the categories.
Done looks like
Every federal fatality inspection from 2012 to 2025 whose narrative mentions demolition coded, 100 rows coded separately by two people with their agreement with the model published, and the share of collapse deaths in which OSHA cited the survey rule stated.
Open 02 · the brief
Check France's audit numbers
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
For each French operation whose PEMD waste figures are public, set the declared tonnes of concrete, brick, metal and wood against an estimate made from the building's size and age in France's national building database (BDNB) and published material intensities, the kilograms of each material per square meter of floor. Publish the ratio for every operation, with the code.
Why it is still open
The PEMD platform's public data listed waste lots for only 29 operations in November 2026 (554 lots, 166 of them with no waste code; count made for this file), and only 148 after-works reports were filed on the platform in 2025. In Brazil, a 2026 study by Nagalli compared the plans and final reports of 118 demolitions in Curitiba and found that the facts known at the permit stage predicted waste per square meter little better than a single median rate. No check of France's audits against an independent estimate was found.
plateformepemd.developpement-durable.gouv.frplateformepemd.developpement-durable.gouv.frdoi.org
Built with what exists
The PEMD platform's public API (the "gisements" call with type "dechet"); BDNB, published by CSTB under France's open license; the material intensity database of Heeren and Fishman (2019); Python with GeoPandas.
First step
Download the public waste lots and try to match five operations to BDNB buildings from the commune and operation name, noting which matches are certain.
Done looks like
Every public operation matched to its BDNB building, the ratio of declared to estimated tonnes published for each material, and every operation off by more than a factor of two listed with a reason found or marked unexplained.