Industries / Mining and materials / Cement and concrete
Cutting emissions
Cutting emissions is the work of lowering the carbon dioxide released in making cement, most of which comes from heating limestone, and of measuring, reporting and pricing what remains.
5
Milestones achieved, from 2005 to 2026.
2
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
2005
Permits to emit
From 1 January 2005 the European Union's emissions trading system required every cement-clinker kiln making more than 500 t a day to hold a permit and hand in one allowance for each tonne of CO2 it emitted. Member states gave at least 95% of allowances free in 2005–2007 and at least 90% in 2008–2012.
LessonFree allowances outran what kilns needed. By the calculations of the consultancy CE Delft, as reported by Carbon Market Watch, cement companies in 20 European countries made €5 billion in windfall profits from the system in 2008–2015, €2.7 billion of it from selling surplus free allowances.
Credit
The European Parliament and Council, Directive 2003/87/EC
2021
Credits for CO2 in concrete
CarbonCure injects captured CO2 into fresh concrete, where it turns into calcium carbonate, and producers use the gain in strength to cut some cement. Verra, which runs a carbon-credit registry, lists its methodology VM0043 for CO2 use in concrete production, developed by CarbonCure and assessed by First Environment and Ruby Canyon Environmental, with the date 5 April 2021. CarbonCure says its producers had made 10 million truckloads of concrete with the process by November 2025, a company figure.
Credit
CarbonCure Technologies; Verra
2025
China prices cement carbon
On 26 March 2025 China's Ministry of Ecology and Environment published a work plan adding steel, cement and aluminium smelting to the national emissions trading market, which had covered only power. The addition brings about 1,500 more companies and about 3 billion t of CO2-equivalent a year into the market. For cement, only CO2 counts. Allowances for 2024 emissions were given free, with a surrender deadline of 31 December 2025, and later years are allocated by benchmarks of carbon per tonne of product, not by a fixed cap.
Credit
Ministry of Ecology and Environment of China
2025
Capture at a cement plant
Heidelberg Materials opened Brevik CCS at its cement plant in Norway on 18 June 2025, designed to capture about 400,000 t of CO2 a year, half the plant's emissions. The company calls it the cement industry's first industrial-scale carbon capture plant. In August 2025 Northern Lights, owned by Equinor, Shell and TotalEnergies, piped the first shipped CO2 100 km to the Aurora reservoir, 2,600 m below the North Sea seabed. Northern Lights reports storing 40,000 t in 2025 and issuing Heidelberg Materials its first storage certificate.
LessonThe ramp-up took longer than planned. A company spokesperson told Cleanthinking in October 2026 that the hardest problems lay where the new capture plant joins the running cement works.
Credit
Heidelberg Materials; Northern Lights; the Norwegian state's Longship project
2026
Carbon priced at the border
The EU's Carbon Border Adjustment Mechanism (CBAM) charges importers for the carbon emitted in making certain goods abroad, as the EU phases out free allowances at home. After reporting-only years from 2023 to 2025, it entered its definitive regime on 1 January 2026: importers of cement, iron and steel, aluminium, fertilisers, electricity and hydrogen must be authorised, report embedded emissions, and buy and surrender CBAM certificates priced from EU allowance auctions.
Credit
European Commission
Watch for
Brevik near full capacity
Heidelberg Materials told the German site Cleanthinking that Brevik CCS was running at nearly full capacity, capturing more than 50 t of CO2 an hour in recent operating periods. Cleanthinking notes that this rate over every hour of a year would be about 440,000 t, an upper bound since the plant stopped for winter repairs. The company says it will give the total captured since opening only in its 2026 annual and sustainability report.
Achieved whenthe 2026 report gives captured tonnes near the 400,000 t design figure and Northern Lights' stored volumes match.
Claimed by
Heidelberg Materials, October 2026
Electrochemical cement for data centres
Sublime Systems makes cement by an electrochemical process that, by its account, avoids the usual sources of carbon emissions in cement-making. It says accredited third-party labs have found its cement complies with ASTM standards. On 12 November 2026 it announced a multi-year agreement under which Meta buys environmental attribute certificates, tradable records of the lower emissions, for at least 180,000 t of Sublime cement, to be verified by an accredited third party. The cement will come from first commercial plants that are still in development.
Achieved whena commercial Sublime plant is running and an outside verifier confirms its tonnes and their emissions.
Claimed by
Sublime Systems and Meta, November 2026
Open
01
A ledger of captured carbon
A public table of every cement plant that captures CO2, listing design capacity next to captured, shipped and stored tonnes per year, each figure linked to a company report, a storage operator's report or a regulator's record, and updated as each new report appears.
The briefCredit · unclaimed02
Measure CO2 kept in concrete
An outside measurement of how much injected CO2 stays bound in ready-mix concrete, using carbon analysers on samples from several plants that inject CO2, each paired with a control sample made without it.
The briefCredit · unclaimed
Open 01 · the brief
A ledger of captured carbon
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public table of every cement plant that captures CO2, listing design capacity next to captured, shipped and stored tonnes per year, each figure linked to a company report, a storage operator's report or a regulator's record, and updated as each new report appears.
Why it is still open
Heidelberg Materials does not publish in-year capture volumes for Brevik and will give its first total in the 2026 annual report. Northern Lights reports stored tonnes, 40,000 t in 2025, for its whole operation rather than per customer.
Built with what exists
Company annual and sustainability reports; Northern Lights reports and storage certificates; facility emission records from the Norwegian Environment Agency (norskeutslipp.no) and the EU emissions trading registry; Python and a public spreadsheet.
First step
Read the Northern Lights 2025 annual report and Heidelberg Materials' 2025 report, and fill in the first row for Brevik with sources.
Done looks like
Brevik's 2025 and 2026 design, captured and stored figures side by side with a source for each, plus every other cement capture plant that reports figures, posted within a month of each new report.
Open 02 · the brief
Measure CO2 kept in concrete
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
An outside measurement of how much injected CO2 stays bound in ready-mix concrete, using carbon analysers on samples from several plants that inject CO2, each paired with a control sample made without it.
Why it is still open
The Verra methodology lets producers skip testing and assume that 60% of the injected CO2 is mineralized. That default rests on one case study by CarbonCure's Sean Monkman (2018): eight batches of masonry concrete at one producer, with measurements precise to about ±20% by weight of cement. The methodology itself says such tests show "quite a range of results".
Built with what exists
A combustion carbon analyser such as the Eltra CS-800 used in the case study, or a LECO unit; thermogravimetric analysis, which weighs a sample as it is heated to see how much carbonate it holds; the sampling steps in Appendix IV of VM0043.
First step
Write a sampling plan from VM0043's Appendix IV and ask a university lab with a carbon analyser to run 20 control samples to learn its repeatability.
Done looks like
At least 100 paired samples from at least five plants and ten mix designs, with the share of injected CO2 found in each and its uncertainty, published with the raw readings.