Industries / Mining and materials / Mining and quarrying / Uranium mining
Closing sites
Closing a uranium mine means reshaping and covering what mining left behind, treating the water that drains from it, and then watching over it for generations.
6
Milestones achieved, from 1980s to 2025.
2
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
1980s
Rum Jungle's first cleanup
Rum Jungle, a former uranium mine in Australia's Northern Territory, leaked acid and metals into the East Branch of the Finniss River. Major rehabilitation works in the mid-1980s cut the loads of acid and metals leaving the site by up to 70% and let the river's aquatic life largely recover. Metal levels in the river still fail today's water quality standards, and the land is not yet fit to hand back to its traditional owners, the Kungarakan and Warai peoples. Since 2009 the Northern Territory and Australian governments have planned a second rehabilitation that moves acid-forming waste rock to new storage, treats contaminated water and sends the diverted river back through the flooded main pit.
LessonWaste rock that has already weathered holds stored acid in minerals such as jarosite, so covering it slows the damage but does not end it.
Credit
Northern Territory and Australian governments (current program)
1991
Germany takes on Wismut
By an agreement with the Soviet Union on 16 May 1991, Germany took over the whole of SDAG Wismut, the Soviet-German company that had mined uranium in Saxony and Thuringia, with its environmental damage, and turned it into the federal company Wismut GmbH that December. Germany had allocated €7.4 billion to the cleanup by the end of 2025, by Wismut's account. Near Ronneburg, Wismut moved more than 125 million m³ of waste rock dumps into the old Lichtenberg open pit, finishing the last dump in early 2008, and showed the new landscape at the 2007 federal garden show.
LessonEven after the earthworks, water treatment and the upkeep of covers carry on with no end date, by Wismut's own account.
Credit
Federal Republic of Germany; Wismut GmbH
2014
Care fees fall short
When a US mill company hands a finished tailings site to DOE, it pays a one-time long-term surveillance charge, set in 1978 dollars with a minimum of $250,000 a site. DOE's Inspector General found that in fiscal years 2010 to 2012 the Office of Legacy Management spent $4.25 million on the six Title II sites it then managed, while the charges produced $148,000. The Congressional Research Service added in 2021 that the NRC had not revised the minimum charge since its rules were issued in 1985.
LessonA one-time fee set before anyone knew the cost of care leaves the rest of the bill to taxpayers.
Credit
DOE Office of Inspector General
2014
Money for Navajo mines
From 1944 to 1986 nearly 30 million tons of uranium ore were mined on Navajo lands, leaving 523 abandoned uranium mines, by EPA's count. After Tronox, a successor of the Kerr-McGee company, went bankrupt in 2009, the United States sued Anadarko, another successor, and won a $5 billion national settlement in 2014; EPA received almost $900 million of it to clean up more than 50 Kerr-McGee mines, 48 of them on or near the Navajo Nation. With a 2017 settlement for 93 mines and other agreements, more than $1.7 billion is now set aside, enough to start work at 253 of the 523 mines, by EPA's September 2025 fact sheet. EPA's own web page says 44 of the 46 priority mines are still in the assessment phase.
LessonCleanup money came decades after the mining, through lawsuits against successor companies, and assessment alone has taken years.
Credit
US Department of Justice and EPA; Navajo Nation
2022
Ranger outruns its deadline
The Ranger mine, surrounded by but separate from Kakadu National Park in Australia's Northern Territory, ended more than 35 years of mining and processing in January 2021. ERA had to return the land to a state like the surrounding park by January 2026. In February 2022 ERA put the cost at A$1.6 to 2.2 billion and the finish at late 2027 to late 2028, against A$973 million in its 2019 estimate. Parliament passed a law in November 2022 so that ERA could keep working past 2026, and a new authority took effect on 9 January 2026. At the end of 2025 ERA still expected to spend A$2.96 billion in nominal terms, by its own accounts.
LessonA closure estimate made while a mine is running can be badly short; Ranger's rose from A$973 million to as much as A$2.2 billion within three years.
world-nuclear-news.orgminingweekly.comannouncements.asx.com.au
Credit
ERA; Australian Parliament
2025
Four Central Asian sites finished
The Environmental Remediation Account for Central Asia, a fund set up in 2015 on the European Union's initiative and run by the EBRD, finished cleanup at Min-Kush and Shekaftar in Kyrgyzstan and at Charkesar and Yangiabad in Uzbekistan, four of the seven high-priority Soviet-era uranium sites in an IAEA master plan. The IAEA's January 2026 assessment records the four as remediated, as reported by The Times of Central Asia.
LessonCleanup moves only as fast as donors pay; the two priority sites in Tajikistan have studies done but lack the €42.9 million needed, by the revised plan's estimate.
Credit
EBRD; European Union and other donors; IAEA (master plan)
Watch for
Paying for Akouta's cleanup
Orano's Cominak mine at Akouta, Niger, stopped producing on 31 March 2021 after more than 75,000 tonnes of uranium, and Orano said remediation would take at least 10 years, followed by at least five years of monitoring. In May 2026 Niger's mines minister said that Orano holds Cominak's rehabilitation fund, about 125 billion CFA francs, in France, and that Niger will go to court to have the work done.
Achieved whena court or an independent audit settles who holds the fund, and an outside report confirms the state of the cleanup at Akouta.
Claimed by
Niger's Ministry of Mines, May 2026
Handing Moab to the county
A bill introduced in April 2025, the Moab UMTRA Project Transition Act (S. 1321), would have DOE give the former mill site at Moab to Grand County, Utah, at no cost once cleanup is complete. The Senate Energy and Natural Resources Committee passed it unanimously on 4 February 2026, and DOE aims to finish the cleanup in 2029.
Achieved whenthe bill becomes law and the deed passes to Grand County.
Claimed by
Senator John Curtis and Representative Mike Kennedy, February 2026
Open
01
Long-term care, site by site
A public ledger of what DOE spends each year to watch and maintain each uranium mill tailings site in its care, set beside the one-time surveillance charge each Title II company paid when its site was handed over, with every figure linked to its source document.
The briefCredit · unclaimed02
Measuring France's waste rock dumps
The volume, height and steepest slope of each waste rock dump that France's MIMAUSA inventory maps around its former uranium mines, measured from the national lidar terrain model, with a flag for dumps never reshaped since mining.
The briefCredit · unclaimed
Open 01 · the brief
Long-term care, site by site
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public ledger of what DOE spends each year to watch and maintain each uranium mill tailings site in its care, set beside the one-time surveillance charge each Title II company paid when its site was handed over, with every figure linked to its source document.
Why it is still open
DOE's Inspector General compared costs and charges only in total, for six sites over three years. The Congressional Research Service wrote in 2021 that information on Legacy Management's monitoring and maintenance costs by site and by year is limited. More sites are coming: DOE expects to add Durita, Colorado, in 2026 and up to 30 Title II sites in all.
Built with what exists
DOE budget requests and Legacy Management's yearly site management guide; USAspending.gov award data; the NRC's ADAMS document library for license terminations and surveillance charges; a records request to Legacy Management for site-level costs; a language model to pull figures from PDFs, with each figure checked by hand.
First step
Find the license-termination record and surveillance charge for one transferred Title II site, such as Bluewater, New Mexico, in ADAMS, and file the records request for its yearly costs.
Done looks like
For every Title II site DOE manages, the charge paid in today's dollars against DOE's yearly cost from 2010 to 2025, and the number of years of care each charge would cover at that cost; the same yearly costs for the Title I cells; all published with sources.
Open 02 · the brief
Measuring France's waste rock dumps
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
The volume, height and steepest slope of each waste rock dump that France's MIMAUSA inventory maps around its former uranium mines, measured from the national lidar terrain model, with a flag for dumps never reshaped since mining.
Why it is still open
French uranium mining ran from after the Second World War to 2001 at 250 sites and produced about 200 million tonnes of waste rock, the rock dug out to reach the ore, by the national radiation safety institute IRSN's count. IRSN's public MIMAUSA map, online since 2009, outlines 168 dumps and records each one's area, state, plant cover and use, 66 of them marked raw ("brut"), but gives no height, volume or slope. A search for this brief found deep learning applied to lidar over old mining districts, such as finding mine pits on Dartmoor in England, but no measurement of these dumps.
Built with what exists
MIMAUSA's dump and open pit outlines, published under France's open license; IGN's LiDAR HD terrain model, built from at least 10 laser pulses per square meter and free to reuse; QGIS, PDAL or WhiteboxTools; Python with rasterio and geopandas.
First step
Download the lidar terrain tiles under one mapped dump, cut them to the MIMAUSA outline in QGIS, and compute its volume above the surrounding ground.
Done looks like
A public table of all 168 mapped dumps with volume, height, steepest slope and lidar-measured area against MIMAUSA's area, with the code; volumes checked against any tonnages given in the regional environmental reviews of the same sites.