Installation puts a lining into a furnace, ladle, converter or kiln and keeps it working: laying brick, spraying or gunning a damp mix onto worn spots, heating a new lining dry without cracking it, and tearing out the old one when it is spent.

7

Milestones achieved, from 1975 to 2025.

2

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1975

    Measure the wall, then gun

    Gunning blows a damp refractory mix through a nozzle onto worn spots of a lining, often while the vessel is still hot. Tsunemi Ochiai and Teruyuki Nishitani of Nippon Steel first filed in June 1975 for a method that bounced microwaves off the hot lining of ladles, converters and other vessels, found the damaged areas from the reflections and steered the gunning nozzle to them. Kurosaki Refractories filed in December 1977 for a TV camera mounted on the spray pipe, because without one "an operator has to look into the inside of the furnace throughout the lining operation." By the account of Terry Pavlack and Charles Messina in 1997, "more aggressive gunning systems" spread through steel plants in the 1980s.

    patents.google.compatents.google.comapp.abmproceedings.com.br

    Credit

    Tsunemi Ochiai and Teruyuki Nishitani (Nippon Steel); Masayuki Fujita, Sueki Kubo and Yasuo Nakamura (Kurosaki Refractories)

  2. 1976

    Old linings torn out remotely

    At the Rönnskär metal works near Skellefteå, Sweden, workers in the 1970s crawled into hot lead furnaces to chip out slag and brick by hand, by Brokk's account. The brothers Lars and Per-Martin Holmgren built a remote-controlled machine from the parts of other machines; Brokk dates its start to 1976, calls it the industry's first remote-controlled demolition system, and says the first prototype halved the time of the job. A 2005 Oak Ridge National Laboratory report for the US Department of Energy notes that in the largest aluminum melting furnaces, built-up material is "sometimes" removed "using large robotic devices."

    brokk.comosti.gov

    Credit

    Lars and Per-Martin Holmgren; Brokk AB

  3. 1990s

    Machines lift the converter bricks

    A converter, or basic oxygen furnace, is the pear-shaped vessel in which oxygen blown into molten iron turns it into steel; its brick lining wears out and must be rebuilt. From 1986 to 1993 Paul Wurth of Luxembourg patented machines that lower a working platform into a converter, raise bricks from pallets and set them with a robot arm. In February 2023 the German steelmaker HKM (Hüttenwerke Krupp Mannesmann) ordered a relining machine from Primetals Technologies to replace a 30-year-old one at its Duisburg plant. In the new machine two magazine lifts carry bricks from a depalletizing station into the converter and a manipulator unloads them onto a roller table, so that "personnel working inside the converter vessel will no longer need to lift the bricks"; people still set them in place.

    patents.google.compatents.google.comprimetals.com

    Credit

    Paul Wurth (Edouard Legille, Corneille Melan and others); Primetals Technologies; HKM

  4. 1990s

    Slag coats the converter

    Slag splashing blows nitrogen through the oxygen lance after the steel is tapped, throwing the leftover slag onto the converter walls, where it freezes into a layer that wears away in place of the brick. Terry Pavlack and Charles Messina wrote in 1997 that Praxair developed it in the mid-1970s at National Steel's Great Lakes Division and was issued a patent in 1983, but that it saw little use through the 1980s because brick had improved and gunning had become more aggressive. John Stubbles, reviewing US steel for the Department of Energy in 2000, wrote that "in the 1990s, slag splashing dramatically extended lining lives and vessel availability." In 2009 Guo and Yang reported 15,000 heats (batches of steel) from one lining of a 50-tonne converter at a plant they call Long-steel.

    LessonBetter brick and gunning in the 1980s kept a cheap way of protecting the lining on the shelf for a decade.

    app.abmproceedings.com.brosti.govdoi.org

    Credit

    National Steel and Praxair

  5. 2003

    Steam pressure inside castables

    A castable is a refractory concrete, mixed with water and poured, pumped or sprayed into place. When a new lining is first heated, that water turns to steam inside it; in dense castables the steam can build pressure faster than it escapes and blow pieces off, which the trade calls explosive spalling. In 2003 Murilo Innocentini, Victor Pandolfelli and colleagues at the Federal University of São Carlos in Brazil measured how high-alumina castables lose water under different heating schedules and separated evaporation from boiling, as a basis for schedules that dry a lining faster with less risk. A 2022 review by the same group calls drying "the most critical process" of a dense refractory's first heating and says schedules are still "usually based on empirical knowledge", so plants often heat slowly and lose production time.

    doi.orgarxiv.org

    Credit

    Murilo D. M. Innocentini, Marcela F. S. Miranda, F. A. Cardoso and Victor C. Pandolfelli (Federal University of São Carlos)

  6. 2005

    Linings sprayed like concrete

    Shotcreting sprays a pumped castable through a nozzle, as builders spray concrete, so a lining can be put in without forms or bricklayers. A 2005 report by James Hemrick and colleagues at Oak Ridge National Laboratory for the US Department of Energy credits it with large cuts in downtime, and says that in steel ladles "it has been possible to successively repair the original lining such that complete relining is no longer necessary."

    osti.gov

    Credit

    James G. Hemrick and colleagues (Oak Ridge National Laboratory)

  7. 2025

    Long cure, then spalling

    Researchers at Vilnius Gediminas Technical University in Lithuania began from a biomass boiler whose castable lining spalled on its first heating after curing for a long time beforehand. They cured conventional and low-cement castables for 120 hours in moist air at 10, 20 and 35 °C and found a significant risk of explosive spalling in the low-cement castable cured at 10 °C, then used polypropylene fibers, up to 0.10% by weight, to check that their test could tell safer mixes apart.

    LessonThe days between installation and first heat-up, and how cold and damp they are, belong in the drying plan.

    doi.org

    Credit

    Andrius Kudžma, Valentin Antonovič, Rimvydas Stonys and Viktor Gribniak

Watch for

  1. A robot that relines ladles

    FBR, the Australian company behind the Hadrian X block-laying robot, says its Firehawk robot places insulating sand and refractory bricks in steel ladles of 10 to 350 tonnes with no workers inside, holds its accuracy across a 10 m reach by correcting for deflection and vibration, and can finish a reline "in as little as a day". Its page says deliveries are "starting soon" and names no customer.

    Achieved whena steelmaker reports Firehawk relines in service, with relining time and lining life set beside hand-laid ladles.

    fbr.com.auyoutube.com

    Claimed by

    FBR, February 2026

  2. Scans that write gunning recipes

    Calderys says its laser measurement and gunning system scans the lining of an electric arc furnace or steel ladle in service, turns the measured wear into "robot-ready gunning recipes", and extends lining life by 15 to 20% while shortening maintenance. It gives no plant or campaign data.

    Achieved whena steelmaker publishes campaign lengths and gunning-mix use for vessels run with and without the system.

    calderys.com

    Claimed by

    Calderys, October 2025

Open

  1. 01

    Robot-laid ladle brick, cold

    A robot cell that lays one full ring of working-lining brick inside a cold, full-size mockup of a section of steel ladle wall, a curved steel shell at room temperature, picking bricks from a pallet and setting them against the course below, with every attempt filmed and measured. The robot never goes near a real ladle.

    The brief
    Credit · unclaimed
  2. 02

    Dry-out schedules side by side

    A public table of the dry-out and heat-up schedules that refractory makers publish for their castables (heating rates, hold temperatures and hold times, by castable type and lining thickness), with every schedule run through an open drying model for one standard ladle wall to compare peak steam pressure, time to dry and fuel used. This is desk work on published instructions and simulations, not on a real lining.

    The brief
    Credit · unclaimed

Open 01 · the brief

Robot-laid ladle brick, cold

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A robot cell that lays one full ring of working-lining brick inside a cold, full-size mockup of a section of steel ladle wall, a curved steel shell at room temperature, picking bricks from a pallet and setting them against the course below, with every attempt filmed and measured. The robot never goes near a real ladle.

Why it is still open

Nippon Steel wrote in 2020 that wider use of monolithics had saved labor "to a certain extent, but most brick installation work is still done by human labor." Machines to lay ladle brick have been patented since 1972, when Combustion Engineering claimed a device that lined a ladle in 3 to 4 hours with one operator, and Paul Wurth patented converter bricklaying robots from 1986. Yet the converter relining machine HKM ordered in 2023 still leaves people inside the vessel to set the bricks, and FBR announced its ladle robot in February 2026 with no results published. On a smaller job, changing the refractory plates of a ladle's slide gate (the valve under the ladle that lets steel out), in a field trial at Hiroshima Metal & Machinery from March 2018 to April 2019, Krosaki Harima's general-purpose robot finished the full change in 6 of 34 attempts, then in 10 of 14 after a vibrating gripper was added, with four steps still done by people; the authors wrote that earlier joint efforts in Japan and Europe had not reached practical use. A November 2026 search of GitHub found student simulations, such as a tundish-spraying cell with a UR20 robot modeled in MATLAB, but no filmed tally of a robot laying refractory brick.

nipponsteel.compatents.google.comkrosaki.co.jpgithub.com

Built with what exists

A collaborative arm rated above the weight of the heaviest brick, such as a Universal Robots UR20; a vacuum or clamping gripper; a depth camera such as an Intel RealSense D435; ROS 2 with MoveIt for planned motions, or a policy fine-tuned from a few recorded demonstrations with NVIDIA's open GR00T 2 model (see the Note "Five demonstrations per task") and Hugging Face's LeRobot software (see the Note "No download"); new ladle bricks from a refractory distributor.

  1. First step

    Roll a quarter-ring section of the mockup from steel sheet, buy 50 bricks of one ladle wall shape, and film a mason laying them to set the baseline.

  2. Done looks like

    Twenty filmed attempts at laying one full ring, each scored for bricks laid per hour, the number of bricks a person had to touch, and the widest joint measured with feeler gauges, published with the videos beside a mason's time on the same mockup.

Open 02 · the brief

Dry-out schedules side by side

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public table of the dry-out and heat-up schedules that refractory makers publish for their castables (heating rates, hold temperatures and hold times, by castable type and lining thickness), with every schedule run through an open drying model for one standard ladle wall to compare peak steam pressure, time to dry and fuel used. This is desk work on published instructions and simulations, not on a real lining.

Why it is still open

T. M. Cunha and colleagues at the Federal University of São Carlos wrote in 2023 that industry commonly holds the temperature at set plateaus, but "there is not a specific consensus on how long it should take, whether that temperature is the optimal one", and they compared simulated single-hold curves for one castable ladle lining. The 2022 review by Luz and colleagues says schedules are "usually based on empirical knowledge" and are often conservative, which delays restarting equipment. Open simulation code now exists: a GitHub repository started in September 2026 publishes a thermohygromechanical phase-field model of explosive spalling in castables, written with FEniCS. Searches in November 2026 found makers' schedules published one product at a time, and no table that compares them.

doi.orgarxiv.orggithub.com

Built with what exists

Makers' installation instructions and data sheets; the open THM-PFM code and the method of Cunha and colleagues for scoring a heating curve; Python with pandas; an AI document reader to pull schedules out of PDF instructions, every number checked by hand (see the Note "Seven more flagged").

  1. First step

    Download the dry-out instructions for ten dense low-cement castables from five makers and tabulate their heating rates, holds and thickness rules.

  2. Done looks like

    At least 40 published schedules from at least 8 makers in one open table, each linked to its source, and for each the modeled peak steam pressure, drying time and energy for a 20 cm dense low-cement castable wall, with the spread across makers published.