BRENNEN

Industries / Energy, water and waste / Electric transmission and distribution / Electric cooperatives

Power supply

This work is getting the power that co-ops deliver: most distribution co-ops buy it under long contracts from generation and transmission (G&T) co-ops they own, which run plants and lines or buy in wholesale markets.

6

Milestones achieved, from 1994 to 2026.

2

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1994

    Cajun's nuclear share

    Cajun Electric Power Cooperative owned 30% of the River Bend nuclear plant in Louisiana, which Gulf States Utilities built and ran. After the Louisiana Public Service Commission refused to let Cajun recover its River Bend investment in rates, Cajun filed for bankruptcy in December 1994, and a 1996 court settlement handed its share to the federal Rural Utilities Service, which held liens on most of its assets.

    Lessona co-op that cannot pass a plant's cost to its members has no one else to pass it to.

    fortnightly.com

    Credit

    the Louisiana Public Service Commission and the US District Court

  2. 2006

    Wind in Alaska villages

    The Alaska Village Electric Cooperative, which serves 58 rural communities, put three wind turbines up at Toksook Bay in 2006; a fourth, paid for by a state grant, brought the site to 400 kW, and a new line shares the power with two neighboring villages. From August 2009 to December 2014 the turbines made 991 MWh and displaced 69,000 gallons of diesel, saving $258,000, by the Alaska Energy Authority's count. AVEC now runs 32 turbines at 12 sites serving 20 communities.

    Lessonactual fuel savings ran at about half the estimate, 9,000 gallons a year against 17,520.

    akenergyauthority.orgakenergyauthority.org

    Credit

    the Alaska Village Electric Cooperative and the Alaska Energy Authority

  3. 2021

    A week that broke Brazos

    ERCOT, the Texas grid operator, charged Brazos Electric Power Cooperative, the state's oldest and largest G&T, more than $2.2 billion for a week of power during Winter Storm Uri in February 2021, and Brazos filed for bankruptcy. Its plan, confirmed on 14 November 2022, paid ERCOT up to $1.44 billion, wound down its power supply business and sold its plants so that it continues as a transmission and distribution co-op, and set up a $140 million hardship fund for low-income members facing bill surcharges.

    Lessona G&T that buys in a spot market during a week of scarcity can owe more than it can pay, and its members pay the rest through their bills.

    nortonrosefulbright.comnews.bloomberglaw.com

    Credit

    the US Bankruptcy Court for the Southern District of Texas

  4. 2024

    Paying to leave Tri-State

    Tri-State sells wholesale power to 42 member co-ops in four states under contracts lasting about 50 years. After Kit Carson and Delta-Montrose left, its largest member, United Power, spent four years seeking a price to leave; FERC set the formula in December 2023, and Tri-State then put the fee at $709.5 million less an $82 million equity credit, against United's first estimate of $150 million to $200 million and Tri-State's earlier $1.6 billion. United left on 1 May 2024.

    Lessonan all-requirements contract, a promise to buy all power from one supplier, ties members for decades, and setting the price of leaving took a federal regulator years.

    coloradosun.comcoloradosun.comcoloradosun.com

    Credit

    the Federal Energy Regulatory Commission (FERC)

  5. 2024

    Home batteries sell to ERCOT

    Bandera Electric Cooperative's virtual power plant, members' home batteries run together as one source of supply, qualified to join ERCOT's market on 20 August 2024 and was soon called on for half a megawatt. It had 26 participants from the co-op's battery lease program, and NRECA says it was the first co-op virtual power plant to sell into a real-time market.

    cooperative.com

    Credit

    Bandera Electric Cooperative, which built the control platform, Apolloware

  6. 2026

    A tariff for data centers

    On 14 August 2026 FERC approved Tri-State's High-Impact Load Tariff for new loads above 45 MW, such as data centers. It requires a security payment, a minimum contract term and minimum monthly demand and energy charges, and lets members bring their own power supply for these loads.

    tristate.coop

    Credit

    FERC; Tri-State and its members drafted it

Watch for

  1. New ERA money, still unspent

    USDA's $9.7 billion Empowering Rural America (New ERA) program awarded Tri-State nearly $2.5 billion on 25 October 2024 to buy 1,280 MW of wind and solar power and more than 100 MW of storage. In February 2026 E&E News found none of the program's money spent, according to federal records, while recipient co-ops said USDA officials had told them it is moving forward.

    Achieved whenfederal records show payments, and New ERA-funded plants appear as operating in EIA's monthly generator inventory (Form EIA-860M).

    electric.coopeenews.net

    Claimed by

    USDA and recipient co-ops, February 2026

  2. AI that predicts peaks

    NRECA says North Carolina Electric Membership Corporation, a G&T, built a machine learning model from past weather, load and load forecasts to narrow the window in which it expects the peak, so it calls fewer load-control events and makes better use of its batteries.

    Achieved whenNCEMC or an outside party publishes the model's peak-day hit rate against the old method for at least one full season.

    cooperative.com

    Claimed by

    NRECA, January 2026

Open

  1. 01

    A register of G&T contracts

    A public table of the wholesale contracts between G&Ts and their member co-ops: the end year, the exit terms, how the demand charge is set, and a link to each source document.

    The brief
    Credit · unclaimed
  2. 02

    Track New ERA projects

    A public tracker that matches each announced New ERA award to the plants and batteries it is meant to pay for, and checks their status each month.

    The brief
    Credit · unclaimed

Open 01 · the brief

A register of G&T contracts

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public table of the wholesale contracts between G&Ts and their member co-ops: the end year, the exit terms, how the demand charge is set, and a link to each source document.

Why it is still open

Contract terms surface one dispute at a time. Tri-State's roughly 50-year contracts and its exit price came out through a four-year FERC case, and no table comparing G&Ts was found.

coloradosun.com

Built with what exists

FERC's eLibrary; SEC EDGAR filings by G&Ts that issue public debt; the MSRB's EMMA bond disclosure site; court opinions through CourtListener; a browsing agent to gather documents (see the Note "Deleting 80% to start over"); a language model to pull terms (see the Note "The jobs agents repeat").

  1. First step

    Pull Tri-State's contract terms from its FERC filings and write the table's columns from them.

  2. Done looks like

    At least 40 US G&Ts listed with contract end year and exit clause, each linked to a primary document, and 10 entries checked by a second person.

Open 02 · the brief

Track New ERA projects

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public tracker that matches each announced New ERA award to the plants and batteries it is meant to pay for, and checks their status each month.

Why it is still open

E&E News found that none of the money had been spent by early 2026, and that USDA had said little publicly since lifting a funding pause in March 2025.

eenews.net

Built with what exists

USDA and co-op award announcements; EIA Form 860M monthly generator data; USAspending.gov award records; a language model to pull project names and megawatts; a spreadsheet.

  1. First step

    List the awards from USDA's and NRECA's announcements, starting with Tri-State's 1,280 MW.

  2. Done looks like

    Every announced award matched to named projects with megawatts and, where they exist, EIA plant IDs, updated monthly for six months, with each change linked to a record.