Industries / Energy, water and waste / Carbon capture
Transport
Moving captured carbon dioxide from where it is captured to where it is used or stored, mostly by pipeline and, more recently, by ship.
7
Milestones achieved, from 1972 to 2025.
2
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
1972
A pipeline built for CO2
The Canyon Reef Carriers pipeline, built in 1972, carries carbon dioxide 140 miles from McCamey, Texas, to the SACROC oil field, where it is pumped underground to push out more oil, a method called enhanced oil recovery. Its owner, Kinder Morgan, calls it the oldest CO2 pipeline in West Texas. It is 16 inches across and carries about 270 million cubic feet of CO2 a day.
Credit
Kinder Morgan CO2, the current owner, which dates the line to 1972
1980s
Long lines from natural CO2
In 1972 drillers looking for natural gas near Walsenburg, Colorado, found wells that produced CO2 instead. ARCO bought the leases in 1974 and built a 405-mile pipeline to carry about 330 million standard cubic feet a day to its Wasson and Seminole oil fields in West Texas, as the trade journal Pipeline & Underground Utilities Construction reported in 1985. Kinder Morgan's Cortez pipeline now runs 500 miles from southwestern Colorado to Denver City, Texas, and can carry 1.5 billion cubic feet a day. Kinder Morgan says the main customers on its CO2 pipelines are still oil fields using enhanced oil recovery.
Credit
ARCO Oil and Gas; Kinder Morgan
2019
CO2 may cross borders
The London Protocol is the treaty that controls dumping at sea. Its parties allowed CO2 to be stored under the seabed in 2006, but Article 6 banned exporting waste for dumping, which blocked sending CO2 to another country's seabed. A 2009 amendment allows the export where the countries concerned have an agreement, but it takes force only after two-thirds of the parties accept it, and it has not. On 11 October 2019 the parties adopted resolution LP.5(14), which lets a country that files a declaration apply the amendment early. The International Maritime Organization (IMO) lists nine that have: Australia, Belgium, Denmark, the Netherlands, Norway, the Republic of Korea, Sweden, Switzerland and the United Kingdom.
LessonA treaty written to stop ocean dumping had to be changed before CO2 storage could become a trade between countries..aspx).pdf).
Credit
the Contracting Parties to the London Protocol, at the IMO
2020
Satartia's pipeline ruptures
On 22 February 2020 Denbury's 24-inch CO2 pipeline near Satartia, Mississippi, broke at a girth weld, the circular weld that joins two lengths of pipe, after the ground on a steep slope beside Highway 433 subsided. About 31,405 barrels of liquid CO2 escaped and turned to gas, which is heavier than air. Responders first took it for a chlorine leak. About 200 people were evacuated and 45 sought hospital care; none was admitted. The Pipeline and Hazardous Materials Safety Administration (PHMSA), the US pipeline safety regulator, found that Denbury's 2011 dispersion model, its estimate of where escaped gas would spread, "significantly underestimated" the area a release could reach, so Satartia had been left out of its public warnings. In May 2022 PHMSA proposed a penalty of $3,866,734. A federal rule announced on 15 January 2025 would have set the first design, installation and emergency-planning requirements for CO2 pipelines; it was withdrawn under the regulatory freeze of 20 January 2025, and the government's Fall 2025 regulatory agenda lists it as a long-term action with no date.
LessonEscaped CO2 flows downhill like water, so a hazard zone drawn without the terrain can miss the town below..pdf).
Credit
PHMSA's investigation; Mississippi Today's reporting
2023
CO2 shipped between countries
In March 2023 a consortium led by INEOS began injecting CO2 captured and liquefied at INEOS's oxide plant in Antwerp, Belgium, and carried in custom-built tank containers, into the depleted Nini West oil field about 1,800 m below the Danish North Sea seabed. The Chemical Engineer reported that the consortium had "for the first time, initiated a cross-border offshore CCS project," and that Belgium and Denmark were the first two countries to sign a bilateral agreement on moving CO2 across a border.
Credit
Project Greensand, led by INEOS
2025
Ships deliver CO2 to storage
Northern Lights, a company owned equally by Equinor, Shell and TotalEnergies, took two purpose-built ships, Northern Pioneer and Northern Pathfinder, each with tanks for 7,500 m3 of liquefied CO2. In August 2025 CO2 shipped from Heidelberg Materials' cement plant at Brevik, Norway, was unloaded at Øygarden on the Norwegian coast, piped 100 km offshore and injected into the Aurora reservoir 2,600 m below the seabed. Northern Lights stored 40,000 t in 2025. Oil & Gas Journal describes it as a "third-party" transport and storage project, one that stores other companies' CO2 for a fee.
Credit
Northern Lights JV (Equinor, Shell and TotalEnergies); ships built by Dalian Shipbuilding Industry Co. and run by "K" Line
2025
Landowners stop a network
Summit Carbon Solutions planned a 2,500-mile pipeline network to carry CO2 from nearly 60 ethanol plants to storage in North Dakota, a $9 billion project across five states by Harvest Public Media's count. In March 2025 South Dakota Gov. Larry Rhoden signed a ban on eminent domain, the power to take land for a project over the owner's objection, for CO2 pipelines. On 22 April 2025 the South Dakota Public Utilities Commission denied Summit's route permit 2–1, the second denial since Summit first applied in 2022. By September 2026 a North Dakota judge had revoked Summit's permit to store CO2 in that state, and the company was looking at destinations in Nebraska, Wyoming, Colorado and Kansas.
LessonWithout the power to take land, a pipeline that crosses several states must win over every landowner on its route or go around them.
Credit
South Dakota landowners and legislature; the South Dakota Public Utilities Commission
Watch for
Five million tonnes a year
Northern Lights took an investment decision in 2025 to raise its capacity from 1.5 million to more than 5 million tonnes of CO2 a year, adding storage tanks, a jetty, injection wells and ships, with the expansion due to operate in the second half of 2028. Its third and fourth ships were launched on 6 June 2025 for delivery in 2026. It says it will start taking CO2 from Yara in the Netherlands and Ørsted in Denmark in 2026, and has agreed to take up to 900,000 t a year from Stockholm Exergi in Sweden.
Achieved whenNorthern Lights' annual report, or data from the Norwegian regulator, shows more than 5 million tonnes stored in one year, with cargoes from several countries.
Claimed by
Northern Lights JV, April 2026
A smaller Summit network
Summit asked the Iowa Utilities Commission in September 2025 to amend its permit, and has asked for a decision on its second phase by the end of 2026, while it weighs new destinations in Nebraska, Wyoming, Colorado and Kansas. Its website says the options will likely include using the CO2 for enhanced oil and gas drilling.
Achieved whena Summit line holds every state permit it needs and carries CO2 from ethanol plants to an injection site.
Claimed by
Summit Carbon Solutions, September 2025 to September 2026
Open
01
A terrain screen for pipelines
An open, fast screening tool that takes a CO2 pipeline route and a ground-elevation map and marks the low ground, such as valleys and river flats, where gas from a rupture would flow and collect, with a rough concentration estimate along each path. It is checked first against Satartia, where the screen should place the village inside the hazard zone that Denbury's 2011 model missed.
The briefCredit · unclaimed02
Count CO2 ship cargoes
A public monthly log of every CO2 ship voyage into Northern Lights' terminal at Øygarden, built from AIS, the radio signals ships broadcast with their identity and position and that satellites and coast stations collect. Each voyage gets a loading port, dates and a tonnage estimate from the ships' 7,500 m3 tanks. The yearly sum is compared with Northern Lights' reported stored tonnes.
The briefCredit · unclaimed
Open 01 · the brief
A terrain screen for pipelines
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
An open, fast screening tool that takes a CO2 pipeline route and a ground-elevation map and marks the low ground, such as valleys and river flats, where gas from a rupture would flow and collect, with a rough concentration estimate along each path. It is checked first against Satartia, where the screen should place the village inside the hazard zone that Denbury's 2011 model missed.
Why it is still open
PHMSA found Denbury's 2011 model "significantly underestimated" the reach of a release and told the company to redo it "considering terrain." PHMSA has since funded the Texas A&M Engineering Experiment Station to estimate the potential impact radius of CO2 pipelines with machine learning, and Natural Resources Canada's CanmetENERGY lab is modelling Satartia with computational fluid dynamics (CFD, a detailed simulation of airflow) in a project that runs from 2023 to 2028; neither has released a tool that others can run on a route, and CFD takes specialist time for each site. The 2025 federal rule that would have required operators to plan for releases that could harm people up to two miles from a pipeline was withdrawn. Searches of GitHub found open dense-gas dispersion models but none that follows terrain along a pipeline route..pdf)
primis.phmsa.dot.govadmlc.comnatural-resources.canada.caourtupelo.com
Built with what exists
USGS 3DEP elevation data; WhiteboxTools or GRASS GIS to trace downhill flow paths; ALOHA, the free air-hazard model from EPA and NOAA, which handles heavy gases but assumes flat ground, or slabx, an open Python version of the SLAB dense-gas model, for concentrations along each path; OpenFOAM for a few check runs; Python; the route maps that pipeline developers file with state utility commissions.
First step
Download the 3DEP elevation tiles around Satartia, place the rupture using PHMSA's description (northeast side of Highway 433, about one mile southeast of the village), and trace downhill flow paths to see whether they reach the village.
Done looks like
For Satartia, the screen puts the village inside the hazard zone and matches the plume direction in CanmetENERGY's published figures. The tool screens a 100-mile route in under an hour on a laptop. Results for three public routes are published with the code, and an outside reviewer reproduces the Satartia result from the published files.
Open 02 · the brief
Count CO2 ship cargoes
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public monthly log of every CO2 ship voyage into Northern Lights' terminal at Øygarden, built from AIS, the radio signals ships broadcast with their identity and position and that satellites and coast stations collect. Each voyage gets a loading port, dates and a tonnage estimate from the ships' 7,500 m3 tanks. The yearly sum is compared with Northern Lights' reported stored tonnes.
Why it is still open
Northern Lights reports one yearly total ("the first 40k tonnes" in 2025), not cargoes or tonnes from each customer, and from 2026 cargoes start to come from the Netherlands and Denmark as well as Norway. Searches of the web and GitHub found ship-tracking pages for both ships but no published count of voyages or delivered tonnes.
Built with what exists
Free AIS feeds from aisstream.io and the Norwegian Coastal Administration's Kystdatahuset portal; the ships' IMO numbers; Python and pandas; the annual reports of Northern Lights and its customers.
First step
Get a free aisstream.io key, subscribe to Northern Pioneer and Northern Pathfinder, and log a month of their port calls at Brevik and Øygarden.
Done looks like
Twelve months of voyages, each with its loading port and estimated tonnes, summing to within 10% of the stored volume Northern Lights reports for the same year, with the method and data published.