Power supply is the work of getting a smelter the very large, steady flow of electricity it needs, at a price it can afford, and keeping it on.
7
Milestones achieved, from 1895 to 2024.
2
To watch for: announced, not yet confirmed outside.
2
Open deliverables. Nobody has shipped them.
The road
AchievedWatch forOpen
Achieved
1895
Smelting moves to Niagara
The Pittsburgh Reduction Company signed the first industrial contract to take hydroelectric power at Niagara Falls, New York, in 1893, and its plant there started in 1895, by a 2014 account in ASM International's magazine. An engineer's account in Cassier's Magazine describes the plant taking two-phase alternating current at 2,000 volts, stepping it down with transformers and turning it into direct current with rotary converters, for 10,000 amperes at 160 volts, or 1,600 kilowatts. ASM gives the ingot price as 78 cents a pound in 1893 and 33 cents in 1900.
Credit
Pittsburgh Reduction Company; Niagara Falls Power Company
2010s
Smelters build own coal plants
Smelters that make their own electricity in fossil-fuel plants built alongside them, called captive power, made 49% of the world's primary aluminum in 2021, up from 37% in 2012, by the count of Chang Tan and colleagues at Tsinghua University, who matched 249 smelters to 280 captive power units. Of the 91 gigawatts of captive capacity, 85% burned coal and 70 gigawatts had been built since 2010. Much of the building was in China, which in 2017 capped its smelting capacity at 45 million tonnes a year after a building boom strained its power system; a new smelter there must replace a closed one of the same capacity, by a Reuters column.
Lessonthe gains from more efficient pots were offset by dirtier power, and the same paper says the non-fossil share of the industry's electricity fell from 60% to 33% over three decades.
Credit
smelter owners, mostly in China, India and the Middle East; measured by Chang Tan and colleagues
2016
A smelter as battery
Trimet fitted shell heat exchangers, ducts on a pot's steel shell that draw air to cool it or are shut to insulate it, to 12 pots at its smelter in Essen, Germany. The pots kept a stable heat balance while run anywhere from 150 to 180 kA for up to 48 hours, so the smelter could raise or cut its power use for the grid, which the authors call a "virtual battery". In 2019 Trimet engineers reported converting a full potline to flexible operation, and EnPot reported in 2025 that the potline still runs that way.
Credit
Trimet Aluminium; Light Metals Research Centre, University of Auckland, whose system is sold as EnPot
2016
Five hours without power
On 1 December 2016 a fault on Victoria's transmission network cut power to both potlines of Alcoa's 300,000-tonne-a-year Portland smelter in Australia for more than five hours. Alcoa had to shut one of the two lines, and three weeks later the smelter was running at under 30% of capacity. It did not return to full output until August 2017.
Lessona few hours without power can cost a smelter months of output.
Credit
Alcoa
2022
Europe's smelters cut output
European gas prices reached an all-time high of €345 per megawatt-hour on the Dutch TTF benchmark in August 2022. By ING's count, Europe had suspended about 1.4 million tonnes a year of smelting capacity by the end of 2022, and its output had fallen by more than half since the energy crisis began. ING puts electricity at about 40% of the cost of making aluminum, at about 15 megawatt-hours per tonne. Speira said it would shut its Rheinwerk smelter in Germany.
Lessona smelter without a long-term power price is exposed to every spike in the market.
Credit
Ewa Manthey, ING (analysis, March 2023)
2022
Drought cuts hydro smelting
Yunnan province in southwest China gets about 80% of its electricity from hydropower, and smelters moved there for its lower emissions; its output rose 37% to 4.2 million tonnes in 2022. When drought cut hydropower, Yunnan's smelters had to reduce power use from September 2022, and by April 2023 about 2 million tonnes a year of capacity, 20% of the province's total, was offline, Reuters reported.
Lessonmoving smelting to hydropower trades fuel-price risk for rainfall risk.
Credit
Yunnan's smelters and provincial power authorities
2024
Smelter as dry-year reserve
In May 2024 New Zealand's Aluminium Smelters (NZAS), which runs Tiwai Point, signed contracts with Meridian Energy, Contact Energy and Mercury for 572 megawatts (MW) until at least 2044. They include demand response deals under which NZAS can be asked to cut its use by up to 185 MW. With hydro lakes low that winter, Meridian called on them: the smelter cut about 9% of its use from 22 June, 185 MW from 19 August, and 205 MW, or 36%, from 23 August. The Electricity Authority, the market regulator, estimates this saved about 330 gigawatt-hours of hydro storage between 10 June and 30 September, equal to 7% of New Zealand's hydro storage capacity.
Lessona smelter that is paid in advance to be interruptible can help carry a grid through a dry year.
Credit
NZAS (Rio Tinto); Meridian Energy; Contact Energy
Watch for
Oklahoma smelter waits on power
Emirates Global Aluminium (EGA) and Century Aluminum plan a smelter at Inola, Oklahoma, of more than 750,000 tonnes a year, using EGA's EX pot technology. In September 2026 EGA said it was still negotiating a long-term power supply agreement with the Public Service Company of Oklahoma, and aimed to start construction in early 2027 with first metal by the end of the decade.
Achieved whena power agreement is signed, construction starts and the smelter pours its first metal.
Claimed by
EGA, September 2026
Flexible pots at 440 kA
EnPot fitted its shell heat exchangers to six 440 kA pots at the Binzhou Beihai Huihong smelter in China in February 2025, the largest pots it has equipped. In a paper written with the smelter and its parent group, Shandong Weiqiao, it reports that three pots given 10% more heat for two weeks responded well, and that trials went on to 12.5% and 15%. The authors call these initial results.
Achieved whena full potline of pots this size runs flexibly, and an outside party such as the grid operator reports the megawatts shifted and the pots' performance.
Claimed by
EnPot, Shandong Weiqiao and Beihai Huihong, October 2025
Open
01
Test flexibility models on Tiwai
A public test of published models for running smelters flexibly, checked against what Tiwai Point actually did in winter 2024, when it cut its load by up to 36% for weeks. Feed each model the smelter's real half-hourly load and check whether it judges the pots' heat balance safe through every cut and recovery.
The briefCredit · unclaimed02
Register of smelter power deals
A public register of the power behind each smelter: source (hydro, coal, gas or grid), supplier, contract length and end year, any demand response terms, and curtailments since 2020, each field linked to a public document.
The briefCredit · unclaimed
Open 01 · the brief
Test flexibility models on Tiwai
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public test of published models for running smelters flexibly, checked against what Tiwai Point actually did in winter 2024, when it cut its load by up to 36% for weeks. Feed each model the smelter's real half-hourly load and check whether it judges the pots' heat balance safe through every cut and recovery.
Why it is still open
Scheduling models for smelters in demand response are tested on simulations. Shen and colleagues (IEEE Transactions on Smart Grid, 2026) check their schedules against their own reference model of a 500 kA pot, and their public code holds no plant measurements. A 2025 model of six European smelters by Noda Technologie schedules them against four years of market prices, again with no plant's measured load. The Electricity Authority's account of Tiwai's 2024 cuts reports totals and tests no model. A search found no test of any model against Tiwai's record.
Built with what exists
The Electricity Authority's public half-hourly grid export files, where Tiwai's offtake is the node TWI2201 (a check of the August 2024 file shows its daily average falling from about 490 MW on 1 August to about 365 MW at month's end); the open code of Shen and colleagues (Python, Pyomo); published data on Tiwai's pot types, which Tabereaux lists as Kaiser P-69 and Comalco-Dubal CD-200.
First step
Download the grid export files for June to September 2024, extract node TWI2201, and mark each cut against the dates the Electricity Authority gives.
Done looks like
A public notebook that runs at least two published models on every Tiwai demand response event from June 2024 onward, and reports for each event the largest cut and longest duration the model calls safe beside what the smelter did, with the gap in megawatts and hours.
Open 02 · the brief
Register of smelter power deals
The first to publish is credited on this line, and the deliverable moves from Open to Achieved.
What to build
A public register of the power behind each smelter: source (hydro, coal, gas or grid), supplier, contract length and end year, any demand response terms, and curtailments since 2020, each field linked to a public document.
Why it is still open
The data is collected but sold. Wood Mackenzie's smelter asset reports list power type, source, supplier and contract, at US$2,250 for one smelter. The International Aluminium Institute publishes power use for regions, not single smelters. The Tsinghua inventory lists captive coal and gas units under coded smelter IDs and holds no contracts. The October 2026 open smelter registry notes that Global Energy Monitor, which tracks power plants, has no aluminum tracker.
woodmac.cominternational-aluminium.orgnature.comessd.copernicus.org
Built with what exists
The open smelter registry as the list of sites; company annual reports and stock-exchange releases (Rio Tinto's May 2024 Tiwai release, for example, names the suppliers, the megawatts and the end year); regulator decisions; Global Energy Monitor's power plant data for captive units; an AI model to draft entries from filings for a person to check (see the Note "Seven more flagged").
First step
Fill in the smelters of three countries that disclose well, such as New Zealand, Australia and Norway, and publish the field definitions.
Done looks like
At least 100 smelters with power source and supplier sourced, at least 40 with a contract end year, updated every quarter for a year, with owners invited to correct entries.