BRENNEN

Industries / Energy, water and waste / Propane distribution

Bulk storage

This is the work of holding propane in quantity between the gas plants, refineries and import docks that supply it and the trucks that take it to customers: underground caverns at hubs, import terminals, and the pressure tanks of local bulk plants.

6

Milestones achieved, from 1956 to 2025.

1

To watch for: announced, not yet confirmed outside.

2

Open deliverables. Nobody has shipped them.

The road

AchievedWatch forOpen

Achieved

  1. 1956

    Propane goes underground

    A 1957 report of the US National Petroleum Council counted 90 underground storage projects for liquid petroleum products in the United States as of July 1956, holding "well over 25,000,000 barrels" against some 7 million in 1952. The council found that the growth was mainly in liquefied petroleum gas (LPG, propane and butane), stored in cavities washed out of underground salt with water, with costlier mined cavities built near markets where no salt lay.

    energy.gov

    Credit

    the council's Committee on Underground Storage for Petroleum, chaired by H. S. M. Burns of Shell Oil Company, working from questionnaires sent to every known owner

  2. 1973

    A railcar bursts at Kingman

    On 5 July 1973 two workers at the Doxol bulk plant in Kingman, Arizona, were unloading a railcar of propane into the plant's fixed tanks when a fitting leaked. A wrench struck against the fitting made a spark, the escaping gas caught fire, and the flames played on the top of the car while firefighters sprayed it from hand hoses. About 20 minutes after the fire department was called, the weakened shell failed in a boiling liquid expanding vapour explosion (BLEVE), the bursting of a heated tank of liquefied gas that releases its whole contents as a fireball. Eleven firefighters and one plant worker died and more than 100 people were hurt.

    LessonWater from hand hoses did not keep flame on the top of a pressure tank from weakening its steel, and the US National Fire Academy was teaching the case by 1981.

    firehouse.comfiredoc.nist.gov

    Credit

    Doxol Gas (Western Energy Co.); the fire was written up by the National Fire Protection Association's Fire Journal in January 1974

  3. 1984

    Homes beside a terminal

    At about 05:35 on 19 November 1984 an 8-inch pipe ruptured at the state oil company PEMEX's LPG terminal at San Juan Ixhuatepec, Mexico City, while it was being refilled from a refinery 400 km away. The gas cloud drifted to a flare stack and ignited, and for the next hour and a half the terminal's spheres and cylindrical tanks burst one after another. The UK Health and Safety Executive (HSE) puts the dead at about 500; the Institution of Chemical Engineers (IChemE) gives an official toll of 542 with 4,248 injured, notes that a shanty town had grown to 130 m from the fence, and lists among the causes no gas detection, too little space between vessels and a fire-water system lost in the first blast.

    LessonIChemE draws two rules from it: remotely operated isolation valves on bulk vessels, and enforced minimum distances between such sites and homes.

    hse.gov.ukicheme.org

    Credit

    PEMEX; analysed by the Dutch research body TNO in a 1985 report by C. M. Pietersen, cited by IChemE

  4. 1986

    Britain's LPG caverns open

    Two caverns excavated underground beside the Humber refinery at Immingham, Lincolnshire, opened in 1986 after six years of work; each holds 110,000 m³ of propane and butane. A trade report on their 40th anniversary in March 2026 calls them the only mined hydrocarbon storage caverns ever built in the UK, and the owners called them a strategic supply point through winter as the war involving Iran cut world LPG supplies that year.

    forecourttrader.co.uk

    Credit

    Calor and Phillips 66, the joint owners

  5. 2017

    Japan fills a state reserve

    In 2001 Japan National Oil Corporation (JNOC) set out plans for a government LPG stockpile of 1.5 million tonnes, with two of its bases, Namikata (450,000 t) and Kurashiki (400,000 t), built as underground caverns sealed by groundwater pressure in place of tanks. By Argus's July 2025 account the state energy agency JOGMEC has filled five state terminals since 2017; the state holds 1.4 million tonnes, about 50 days of imports, and private importers held another 1.1 million tonnes in May 2025. Japan had also moved its buying away from the Gulf: about 3.7% of the roughly 10 million tonnes it imported in 2024-25 came from Saudi Arabia, Qatar, Kuwait and the UAE. As demand fell, Japan's total LPG storage shrank by 15% to about 3.5 million tonnes from 4.2 million in 2024, with some tanks turned over to ammonia, by the Global LPG Storage Survey reported by Argus in July 2026.

    jstage.jst.go.jpargusmedia.comargusmedia.com

    Credit

    JNOC and JOGMEC; stock obligations are set by the trade ministry, METI

  6. 2025

    India's largest LPG cavern

    Hindustan Petroleum (HPCL) opened an 80,000-tonne underground LPG cavern at Mangalore, Karnataka, in 2025, joining the 60,000-tonne cavern at Visakhapatnam run by South Asia LPG Company, its joint venture with TotalEnergies. S&P Global put India's total LPG storage, tanks and caverns together, at roughly 22 days of supply in April 2026; at about 90,000 tonnes of use a day, the two caverns alone hold about two days, by the Takshashila Institution's count.

    LessonCaverns sized to smooth out import prices covered about two days of national use when supply was cut in 2026 (see Pricing and supply).

    argusmedia.comhellenicshippingnews.comtakshashila.org.in

    Credit

    HPCL; South Asia LPG Company

Watch for

  1. A 30-day reserve for India

    India's petroleum ministry has directed the three state refiners, IOC, BPCL and HPCL, to build an LPG reserve covering 30 days of demand and to draft a plan that weighs every storage option, floating storage included. Argus estimates the volume at about 2.8 million tonnes, against about 1 million tonnes of import-terminal capacity, and Reuters reported in August 2026 that the ministry was weighing a levy of ₹1.29 per kg of LPG to help fund a $42 billion strategic reserve programme that would include LPG for the first time.

    Achieved whenthe refiners hold stocks equal to 30 days of national demand and a body other than the refiners publishes or audits the stock figures.

    argusmedia.combusinesstoday.in

    Claimed by

    Sujata Sharma, joint secretary, Ministry of Petroleum and Natural Gas, June 2026

Open

  1. 01

    Homes near terminals, counted

    A public table of LPG import terminals and large storage depots worldwide, each with its location and the number of buildings within 250 m, 500 m and 1 km of its fence, and how that number has changed since 2000 where satellite images allow.

    The brief
    Credit · unclaimed
  2. 02

    India's LPG stocks, from outside

    A public monthly estimate of how India's LPG stocks rise and fall, worked out from published production, import and consumption figures, with stated error, and bounded above by the storage capacity that companies report.

    The brief
    Credit · unclaimed

Open 01 · the brief

Homes near terminals, counted

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public table of LPG import terminals and large storage depots worldwide, each with its location and the number of buildings within 250 m, 500 m and 1 km of its fence, and how that number has changed since 2000 where satellite images allow.

Why it is still open

At San Juanico housing had grown to 130 m from the terminal fence. Published checks of LPG sites against what surrounds them cover one city or site at a time; a 2026 study mapped LPG selling points and filling plants in Kano, Nigeria, against the regulator's 10 m road setback and found most of them in breach. A 2022 study of LPG filling stations in Poland notes that many countries lack clear legal rules on the distance between such sites and buildings at all. No worldwide count for terminals was found.

jees.fudutsinma.edu.ngpmc.ncbi.nlm.nih.govicheme.org

Built with what exists

OpenStreetMap for terminal outlines; open building footprints (Google Open Buildings, Microsoft Global ML Building Footprints, Overture Maps); Landsat and Sentinel-2 images through Google Earth Engine or Microsoft Planetary Computer for change over time; QGIS and DuckDB; a vision-language model to flag spheres and bullet tanks on images, each flag checked by a person.

  1. First step

    List India's 22 LPG import terminals (the count given by the Payne Institute) from the oil companies' own pages and run the 500 m count for five of them.

  2. Done looks like

    At least 100 terminals and depots in at least 15 countries, each with building counts at three distances and the source of its outline, published with code; a second person checks 20 sites picked at random against imagery, and the error rate is stated.

Open 02 · the brief

India's LPG stocks, from outside

Credit · unclaimed

The first to publish is credited on this line, and the deliverable moves from Open to Achieved.

What to build

A public monthly estimate of how India's LPG stocks rise and fall, worked out from published production, import and consumption figures, with stated error, and bounded above by the storage capacity that companies report.

Why it is still open

Argus reported in June 2026 that "the government does not provide data on domestic LPG inventories." Published estimates of India's cover in 2026 ranged from about 10 days (market participants, Argus) to roughly 22 days (S&P Global), while the government's "74 days of total reserve capacity" counts crude oil and all products together.

argusmedia.comnewsonair.gov.in

Built with what exists

The Petroleum Planning and Analysis Cell's (PPAC) monthly LPG production, import and consumption tables (the source of Takshashila's January 2026 figures); company statements of terminal and cavern capacity; Python and pandas.

  1. First step

    Download PPAC's monthly LPG figures for 2025-26 and compute the balance for those twelve months.

  2. Done looks like

    A monthly series from April 2015 to the latest month, each input linked to its PPAC table, with an error band; the series shows a stock draw in March to May 2026 consistent with the rationing announced, and its method is published so others can rerun it.